Multi-Location Single Award Task Order Contract (SATOC) for Design - Build and General Construction to support DOD agencies in the Georgia-North Carolina-South Carolina Region

Closed Pre-Solicitation Posted

This opportunity was awarded. See its 3 award notices in the notice history.

Solicitation number
W912HN20R4002
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
USA

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice seeks proposals for three Single Award Task Order Contracts to provide general construction services for the Department of the Army Corps of Engineers Savannah District across North Carolina, South Carolina and Georgia. The contracts will be awarded using a two-phase design-build selection procedure in accordance with FAR Part 36. Proposals will be evaluated based on past performance, design experience, technical approach, and price. The response deadline is July 6, 2020.

The contracts include one set-aside for small business at Fort Bragg, NC not to exceed $49M, one set-aside for HUBZone at Fort Gordon, GA not to exceed $49M, and one set-aside for HUBZone at Fort Stewart, GA not to exceed $30M. Task orders will range between $150K to $5M and the basic contracts are for a two year base period with three one year options. Construction services will include design-build, design-bid-build, and construction only projects. The primary NAICS code is 237310 and the dominant PSC code is V1Y9.

Notice text

2 versions

Update #2 · Latest ·

Two-Phase Design-Build Selection for three (3) Single Award Task Order Contracts (SATOC) under which task orders for General Construction are expected to be issued for projects within the three state region of North Carolina, South Carolina, and Georgia with the primary focus area of each SATOC being work at Ft. Bragg, Ft. Gordon and Ft. Stewart respectively.  Task Orders issued under any resultant contract(s) will be Firm-Fixed Price and may be either for Design-Build or Design-Bid-Build General Construction.

This acquisition is being offered as follows:

SRM02 Fort Bragg NC $49M Capacity – 100% Small Business Set-Aside

SRM05 Fort Gordon, GA $49M Capacity – 100% HUBZone Set-Aside

SRM08 Fort Stewart, GA $30M Capacity – 100% HUBzone Set-Aside

The life of the basic contract is for a base period of two (2) years and three (3) one year options. The Government will use a best value Two-Phase Design-Build selection procedure in accordance with Federal Acquisition Regulation (FAR) Part 36.301.  The order limitation of task orders shall range between $150K and $5M.  Task orders issued under these three (3) SATOC will be firm-fixed price.  All other resultant task orders may include options.

Description of work:  Task orders placed under these three (3) SATOC shall be that of a design-build, design-bid-build construction or construction only in nature.  These three (3) SATOC for General Construction projects are  intended to provide rapid response for new construction, upgrades, maintenance or repair of situations relating to site work, interior/exterior finishes, architectural woodwork, electrical, mechanical, plumbing, structural and fire suppression systems of Government facilities located across the three state region of Georgia, South Carolina and North Carolina and potentially within the geographic boundaries of the U.S. Army Corps of Engineers, Savannah District (SAS).  

Evaluation Criteria: The Government will use a Two-Phase Design-Build Selection evaluation process in rendering the best value decision for award of this contract.  The evaluation factors for this solicitation and are as follows:

PHASE I:

FACTOR 1:  PAST PERFORMANCE

FACTOR 2:  DESIGN EXPERIENCE

PHASE II:

FACTOR 3:  TECHNICAL APPROACH

PRICE: Price will not be rated but will be a factor in establishing the competitive range prior to discussions (if held) and in making the best value decision for award of any resultant contract(s). Coefficients for firm-fixed price type task orders shall be proposed and submitted on the Proposal Pricing Schedule as provided in the solicitation. All pricing submitted shall be binding across the life of the contract.

The successful Offeror(s), if any, will be awarded SATOCs with a maximum capacity of $49M (SB), $49M (HZ) and $30M (HZ), respectively, and either a Seed Task Order or a $2,500.00 guaranteed minimum for the base ordering period.No single Offeror shall receive more than one (1) base contract award from this solicitation.

For each of the three SATOCs, the Offeror that represents the best value to the government shall be awarded the base SATOC. Award will be made to the Offeror whose technical submittal and price proposal contain the combination of criteria requested which offers the best overall value to the Government.  Proposals shall include sufficient detailed information to allow complete evaluation.  The Government reserves the right to reject any and all offers.  Offerors are reminded that while the Government may elect to consider data obtained from other sources, the burden of proof of acceptability rests with the Offeror.

This solicitation will be issued in electronic format only.  Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.  This solicitation is anticipated to be available in July 2020.

Note:  The Response Date referenced under General Information does not refer to the PROPOSAL DUE DATE.  Information on the PROPOSAL DUE DATE will be stated in the solicitation.  Offerors must register in the System for Award Management (SAM) at www.sam.gov.  After completing SAM registration, contractors and their subcontractors must register at www.betaSAM.gov in order to download RFP documents. In order to locate this solicitation, Contractors can go to beta.SAM.gov and search for the solicitation number at www.beta.SAM.gov.  

Update #1 ·

Two-Phase Design-Build Selection for three (3) Single Award Task Order Contracts (SATOC) under which task orders for General Construction are expected to be issued for projects within the three state region of North Carolina, South Carolina, and Georgia with the primary focus area of each SATOC being work at Ft. Bragg, Ft. Gordon and Ft. Stewart respectively.  Task Orders issued under any resultant contract(s) will be Firm-Fixed Price and may be either for Design-Build or Design-Bid-Build General Construction.

This acquisition is being offered as follows:

SRM02 Fort Bragg NC $49M Capacity – 100% Small Business Set-Aside

SRM05 Fort Gordon, GA $49M Capacity – 100% HUBZone Set-Aside

SRM08 Fort Stewart, GA $30M Capacity – 100% HUBzone Set-Aside

The life of the basic contract is for a base period of two (2) years and three (3) one year options. The Government will use a best value Two-Phase Design-Build selection procedure in accordance with Federal Acquisition Regulation (FAR) Part 36.301.  The order limitation of task orders shall range between $150K and $5M.  Task orders issued under these three (3) SATOC will be firm-fixed price.  All other resultant task orders may include options.

Description of work:  Task orders placed under these three (3) SATOC shall be that of a design-build, design-bid-build construction or construction only in nature.  These three (3) SATOC for General Construction projects are  intended to provide rapid response for new construction, upgrades, maintenance or repair of situations relating to site work, interior/exterior finishes, architectural woodwork, electrical, mechanical, plumbing, structural and fire suppression systems of Government facilities located across the three state region of Georgia, South Carolina and North Carolina and potentially within the geographic boundaries of the U.S. Army Corps of Engineers, Savannah District (SAS).  

Evaluation Criteria: The Government will use a Price Performance Trade-Off evaluation process in rendering the best value decision for award of this contract.  The evaluation factors for this solicitation and are as follows:

PHASE I:

FACTOR 1:  PAST PERFORMANCE

FACTOR 2:  DESIGN EXPERIENCE

PHASE II:

FACTOR 3:  TECHNICAL APPROACH

PRICE: Price will not be rated but will be a factor in establishing the competitive range prior to discussions (if held) and in making the best value decision for award of any resultant contract(s). Coefficients for firm-fixed price type task orders shall be proposed and submitted on the Proposal Pricing Schedule as provided in the solicitation. All pricing submitted shall be binding across the life of the contract.

The successful Offeror(s), if any, will be awarded SATOCs with a maximum capacity of $49M (SB), $49M (HZ) and $30M (HZ), respectively, and either a Seed Task Order or a $2,500.00 guaranteed minimum for the base ordering period.No single Offeror shall receive more than one (1) base contract award from this solicitation.

For each of the three SATOCs, the Offeror that represents the best value to the government shall be awarded the base SATOC. Award will be made to the Offeror whose technical submittal and price proposal contain the combination of criteria requested which offers the best overall value to the Government.  Proposals shall include sufficient detailed information to allow complete evaluation.  The Government reserves the right to reject any and all offers.  Offerors are reminded that while the Government may elect to consider data obtained from other sources, the burden of proof of acceptability rests with the Offeror.

This solicitation will be issued in electronic format only.  Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored.  This solicitation is anticipated to be available in July 2020.

Note:  The Response Date referenced under General Information does not refer to the PROPOSAL DUE DATE.  Information on the PROPOSAL DUE DATE will be stated in the solicitation.  Offerors must register in the System for Award Management (SAM) at www.sam.gov.  After completing SAM registration, contractors and their subcontractors must register at www.betaSAM.gov in order to download RFP documents. In order to locate this solicitation, Contractors can go to beta.SAM.gov and search for the solicitation number at www.beta.SAM.gov.  

Notice history

Similar open opportunities

Opportunity Agency Set-aside Responses due
Emergency Operations Center Savannah River Site NAICS 236220 ENDIST Charleston No set-aside
PN 110205 - SOS Hangar Renovation - Progressive-Design-Build OT Pope Army Airfield, Fort Bragg, Cumberland County, North Carolina · NAICS 236220 ENDIST Wilmington No set-aside
Small Business D/B Military Construction MATOC NAICS 236220 ENDIST Louisville Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors