Modification to original solicitation to add Walk Through discussion and questions and answers.

Award Notice Posted

Solicitation number
N1590110010
Agency
Awarded
to Rock Solid Solutions Corporation
Set-aside
Total Small Business

Opportunity facts

Contract number
INPC1590110010 Federal contract award
NAICS code
Not on record
PSC
Not on record
Place of performance
Zion National ParkSR-9 Springdale, UT 84767 84767 USA
More information

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

The purpose of this modification is to send out the minutes from the Site Visit held on May 5, 2011.

THIS MODIFICATION DOES NOT CHANGE THE ORIGINAL DUE DATE OF OFFERS BEING DUE ON MAY 24, 2011.

SITE VISIT - ROCK WALL CONTAINMENT Solicitation N1590110010 MAY 5, 2011

ATTENDEES:

Tracey Bullock, Airborne Veteran Service (702) 232-2475Marco Invernizza, Maccaferri Inc. (602) 677-8666Patrick Breagy, Rock Solid Solutions (970) 903-3028Ray Lisardo, E-Corp (435) 272-7669Alan Young, Federal Builder's (702) 467-0877Malinda Flatray, Contracting Officer (435) 772-0149 Zion National ParkMary Dillon, Contract Specialist (435) 772-0151 Zion National ParkEarl Cox, Maintenance, Zion National Park (435) 772-0143Dave Brooks, Maintenance (435) 772-7637 Zion National ParkJim Starling, Maintenance Supervisor (435) 772-0200 Zion National ParkStan Belinte, Maintenance, Zion National Park (435) 772-0202

Jim Starling began the meeting by leading everyone to the southeast end of the Maintenance Building by the Sign Shop. He gave a brief history of rock fall problems dating back to 1940's, 50-60 years ago. He stated that last October a rock came down through the Sign Shop. It happened at 5:00 a.m. on a Saturday in late October. He directed everyone's attention to the rock terrain to the south and east of the building; a specific ridge behind the building needs approximately 150 foot rock catchment. Look at the slope and rock type. He explained that we want a rock fence installed using a rockfall barrier system such as Geobrugg Barrier, using a computer modeling program similar to CRSP (see Scope of Work) to design the containment fence to the correct kijoule range, incorporating rock type, horizontal slope and vertical distance for fence installation.

The fence shall be vinyl coated or powder coated a dark brown. The installation needs to have the protection of natural resources in mind, using minimum impact techniques in accordance with National Park Service Resource Management Guidelines.

Question - Can we use cranes and a helicopter? Answer: No helicopter or large equipment (without prior authorization).

Jim said we will have to remove vegetation and boulders for the fence line placement with minimal impact. Try to make it as invisible as possible.

Question - Is the vinyl coating to include all of the fencing materials, posts and hardware. Answer: Yes, posts and fencing, all that is possible.

Jim said he'd like to show everyone where the rock that fell into the building hit so they could get a feel for the situation we are under here. He took the group into the Sign Shop and we observed the hole from the falling rock. Question: How long after you receive the offers do you anticipate to make award? Answer: The CO replied approximately within 2 to 3 weeks.

A question was asked: Do we send the proposal design with the offer? Will it be rated? The CO said yes, all proposals will be rated according to the criteria in the evaluation section of the solicitation (Section M.).

A question was asked if there was only one software program that could be used. No, it is up to the Contractor to propose, must be comparable to the Geobrugg.

Question raised could everyone attending could get a list of attendees? Yes, we will provide it in the modification of the solicitation.

Jim said if you have any additional questions, Malinda Flatray, Contracting Officer, is the one to ask.

It was asked if permission was granted to walk up the slope and look the project area over? Permission was granted.



Questions and Answers:

1. How far up do you want the fence to go?

The height, and horizontal and vertical slope will be determined using the Barrier system Geobrugg or similar with the computer modeling program similar to CRSP. You should design the system using the program.

2. Do you want a green fence?

The fence shall be dark brown.

3. Can we use powder coat vinyl?

Yes, if it is the same principle. The bottom line is: make it invisible as possible.

4. Will a right of way be issued?

No

5. Could we use cranes and helicopters?

No

6. Does the vinyl coating include all the fencing materials, posts, hardware, etc.?

Yes, fencing materials, posts, hardware, everything that can be painted or powder coated; color brown.

7. How long after you receive the offers do you anticipate to make award?

Within approximately 2 to 3 weeks.

8. Do we send the proposal design with the offer?

Yes, all proposals will be rated according to the criteria in the evaluation section of the solicitation (Section M.).

9. A question was asked if there was only one software program that could be used.

No, it is up to the Contractor to propose, must be comparable to the Geobrugg.

10. Question was raised could everyone attending could get a list of attendees?

Yes, we will provide it in the modification of the solicitation.

Update #1 ·

The U.S. Department of the Interior (DOI), Zion National Park, intends to issue a solicitation for Rock Fall Barrier Fencing. The Maintenance department requires a rock fall safety barrier fence be installed behind their support buildings located at the Maintenance Yard, Zion National Park, SR-9, Springdale, UT, 84767. The project requires contractor knowledge and ability to model the size and type of system required using the GEOBRUGG Modeling program to the correct kilojoule range considering the rock type, slope percentage and vertical distance and have capability to professionally install this system in order to meet resource protection standards of the National Park System. The system must be installed with minimal impact to the slope and provide transparency in the visual effect. The buildings are historical, therefore materials should blend in with the environmental backdrop.

A construction project is anticipated with an estimated price range between $250,000 and $500,000. The Contractor shall provide all materials (to include shipping), labor, equipment, and installation.

SOCIOECONOMIC PROGRAMS: This procurement is a set aside for small business. For information purposes, the North American Industry Classification Code (NAICS) is 237310, Highway, Street, and Bridge Construction, with a size standard of $33.5M.

NOTE: The solicitation package will be available via electronic commerce at http://ideasec.nbc.gov and http://www.fedbizopps.gov in accordance with FAR Subpart 4.5 and 5.102(a)(1); therefore, hard copies will not be provided. The solicitation will be issued on or about March 30, 2011 with offers due on or about April 30, 2011.

The solicitation will be competitive proposals and will be evaluated in accordance with FAR Subpart 15.304 using technical evaluation criteria and past performance with award to the contractor who meets the best value to the government.

In addition, offerors are required to be registered and current in the Central Contractor Registration (CCR) to be eligible for contract award. See www.ccr.gov and complete On line Representations and Certifications (ORCA) at www.bpn.gov to be eligible for award. Written questions may be submitted to Malinda A. Flatray at malinda_flatray@nps.gov or by fax at (435) 772-0149. Only written questions will be accepted and addressed.