About this opportunity
The Bureau of Engraving and Printing, Department of the Treasury, is seeking sources only for a design/build project to replace the Regenerative Thermal Oxidizer (RTO) and associated exhaust ventilation system at its Western Currency Facility, with responses due November 25, 2026. No set-aside is used. The work is performed at 9000 Blue Mound Road, Fort Worth, Texas 76131. The RTO is required by the Texas Commission on Environmental Quality (TCEQ) New Source Review air permit and treats volatile organic compound (VOC) emissions from 14 plate printing presses, 4 offset presses, and 4 rotary screen presses. The Clean Air Act, EPA regulations, and the facility's air permits require the control device to be maintained in good condition and operated properly whenever the attached facilities operate.
The scope includes a new RTO with a modern control panel using safe PLCs and lower working voltage, and an exhaust ventilation system that self-optimizes using feedback from performance-monitoring systems. It also calls for properly sized roof fans, accessible clean ducting where needed, and higher VOC capture efficiency, which the agency links to reduced supplemental fuel use. The existing system dates to the early 1990s and includes nine roof fans and a 48-inch main roof duct. The current RTO was commissioned in 2010, and offset presses were added in 2021. The product and service code is Z2AZ, and the NAICS code is 238220.
Notice text
SEEKING SOURCES ONLY - The Bureau of Engraving and Printing (BEP) Western Currency Facility (WCF) is located at 9000 Blue Mound Road, Fort Worth, TX, 76131. Construction began on the WCF in 1987 and was completed in 1989. The Modernized Regenerative Thermal Oxidizer (RTO) is an air pollution control device that is required by the NSR
(New Source Review) Air Permit issued by the TCEQ (Texas Commission on Environmental Quality) to treat Volatile Organic Compounds (VOC) emissions from Plate Printing presses (14), Offset presses (4), and Rotary Screen presses (4). The existing RTO was commissioned in 2010 to control VOC emissions from Plate Printing. In 2021, the Offset presses were added to the RTO system. The existing conveyance system, which currently includes ducting from each press to the roof, nine (9) roof fans, and a 48" main duct on the roof, has been in place since the facility was built in the early 90s. The system has been cobbled together as presses were added in Plate Printing, which originally only housed four (4) presses, without consideration for the wholistic efficiency of the system. It is a requirement of the Clean Air Act, EPA regulations, and the WCF air permits, that an air pollution control device associated with a "facility" (equipment or area that is emitting air pollutants as defined by EPA) must be maintained in good condition and operated properly while the attached "facilities" operate.
This design/build project shall replace the RTO and the associated exhaust ventilation system: a new RTO with a modern control panel including safe PLCs and lower working voltage, a properly designed exhaust ventilation system that self-optimizes with feedback from modern performance-monitoring systems, properly sized roof fans, accessibility to clean ducting where needed, and increased voe capture efficiency to better exhaust printing areas while allowing the RTO to operate using less supplemental fuel. The new system shall also incorporate features to decrease the amount of ink and oils that get conveyed into the exhaust ventilation system causing air flow issues and damaging ducting, fans, and other system components. Natural gas usage of the new RTO shall be metered and integrated into the BEP Supervisory Control And Data Acquisition (SCADA) system.
In 2025, the existing RTO underwent several upgrades including the installation of a new, modern control panel to address obsolete components and increasingly difficult troubleshooting. This project shall set the Western Currency Facility (WCF) up for success in providing operational redundancy alongside the newly overhauled RTO that is currently operating at the facility. The entire voe exhaust ventilation system shall feed into one of two RTOs (existing or new) with the capability to divert process flow from one RTO to the other in the event one RTO shuts down for any reason. This redundancy shall enable production to continue operating while the root cause of the issue is addressed.
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Hazardous Waste Disposal | Bureau of Engraving and Printing | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity