About this opportunity

The Department of Agriculture Forest Service R4-Intermountain Region is seeking proposals for the replacement of the Mike Harris Bridge over Trail Creek in Driggs, Idaho. The existing single-lane timber bridge, installed in the 1960s, requires replacement due to increased visitor traffic to the adjacent trailhead and campground. The new bridge will be a prefabricated steel structure with precast concrete grade beams, and the approach roads will be widened to accommodate three lanes of traffic. The contract will be a Firm-Fixed Price award, with a period of performance of 360 days. Preliminary work may begin immediately, but on-site construction cannot start until September 3, 2024, and the road and bridge closure will not occur until the contractor has a confirmed delivery date for the new bridge.

This opportunity is set aside for small businesses. The NAICS code is 237310 (Highway, Street, and Bridge Construction), and the PSC code is Y1DJ (Construction of Roads, Bridges, and Rail Tracks). The estimated magnitude of the project is between $500,000 and $1,000,000. The solicitation package, including project drawings, will be available through SAM.gov within 15 days of this notice, and prospective contractors must be registered in the SAM database to be eligible for award.

Notice text

The Mike Harris Bridge over trail creek is a single lane timber structure installed in the 1960s. Since that time, visitation to the Mike Harris Trailhead and Campground has increased significantly. Due to the age of the bridge and the increased use, replacing the bridge will be a significant benefit to the public. The Teton Basin Ranger District has secured funding to replace the bridge with a new structure that will meet current and future needs.

The old bridge will be removed and disposed of. The stream channel will be reconstructed with riprap installed to protect the substructure of the new bridge while maintaining and restoring the natural stream channel and surrounding riparian area.

There is an electrical utility line attached to the existing bridge that will need to be removed, protected, and reinstalled on the new bridge. Its underground location is not known.

The new bridge will be a prefabricated steel bridge placed on precast concrete grade beams. The bridge design shall be performed by the contractor to fit the envelope shown on the Forest Service drawings. Design calculations and shop drawings shall be submitted to the Forest Service for approval 2 weeks prior to fabrication.

The approach between Highway 33 and the bridge shall be widened to accommodate 3 lanes of traffic; one lane to exit the highway and enter the Mike Harris Trailhead, a left turn lane to enter the highway northbound and a right turn lane to enter the highway southbound.

The base bid includes aggregate approaches and an aggregate wearing surface on the bridge deck. Option A deletes some of the aggregate approach surface and the aggregate deck wearing surface and replaces them with asphalt surfaces. Option B increases the length of the asphalt surface.

Preliminary work may begin immediately after the contract is awarded but work on the ground cannot begin until September 3, 2024. The road and bridge closure may occur on or after September 4th, 2024. The road closure and existing bridge removal shall not take place until the contractor has a confirmed delivery date for the new bridge. Periods of delay that extend the duration of road closure shall be minimized; the contractor should not close the road and existing bridge unless on-site work to install the new bridge will continue.

The Mike Harris Bridge over trail creek is a single lane timber structure installed in the 1960s. Since that time, visitation to the Mike Harris Trailhead and Campground has increased significantly. Due to the age of the bridge and the increased use, replacing the bridge will be a significant benefit to the public. The Teton Basin Ranger District has secured funding to replace the bridge with a new structure that will meet current and future needs.

The old bridge will be removed and disposed of. The stream channel will be reconstructed with riprap installed to protect the substructure of the new bridge while maintaining and restoring the natural stream channel and surrounding riparian area.

There is an electrical utility line attached to the existing bridge that will need to be removed, protected, and reinstalled on the new bridge. Its underground location is not known.

The new bridge will be a prefabricated steel bridge placed on precast concrete grade beams. The bridge design shall be performed by the contractor to fit the envelope shown on the Forest Service drawings. Design calculations and shop drawings shall be submitted to the Forest Service for approval 2 weeks prior to fabrication.

The approach between Highway 33 and the bridge shall be widened to accommodate 3 lanes of traffic; one lane to exit the highway and enter the Mike Harris Trailhead, a left turn lane to enter the highway northbound and a right turn lane to enter the highway southbound.

The base bid includes aggregate approaches and an aggregate wearing surface on the bridge deck. Option A deletes some of the aggregate approach surface and the aggregate deck wearing surface and replaces them with asphalt surfaces. Option B increases the length of the asphalt surface.

Preliminary work may begin immediately after the contract is awarded but work on the ground cannot begin until September 3, 2024. The road and bridge closure may occur on or after September 4th, 2024. The road closure and existing bridge removal shall not take place until the contractor has a confirmed delivery date for the new bridge. Periods of delay that extend the duration of road closure shall be minimized; the contractor should not close the road and existing bridge unless on-site work to install the new bridge will continue.

Files

File Type Posted
Presolicitation Notice 1.docx DOCX document

Notice history

Notice Type Posted
Mike Harris Bridge Replacement Latest solicitation Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
ID FLAP KOOTEN 8450(1), Yellowstone Trail Road, Segment 1 Coeur d Alene, Idaho, United States · NAICS 237310 Federal Highway Administration No set-aside
Cisco Branch Ontonagon River Bridge Replacement Watersmeet, Michigan 49969, United States · NAICS 237310 Forest Service Total Small Business
Big Springs Horse Corral Replacement Lava Hot Springs, Idaho 83246, United States · NAICS 238990 Forest Service Total Small Business
YELL 338223 - Bridge Preservation NAICS 237310 National Office No set-aside
Acadia National Park Maine, United States · NAICS 237310 Federal Highway Administration Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity