Maintenance Dredging of East Rockaway Inlet, New York, Federal Navigation Project
Award Notice Posted
- Solicitation number
- w912ds-16-b-0020
- Agency
-
ENDIST New York
US Army Corps of Engineers, Department of Defense
- Awarded
- to Great Lakes Dredge & Dock Co, LLC
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912DS17C0002 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of East Rockaway Inlet, New York, Federal Navigation Project, including dredging the deposition basins. The dredged sand would be placed in a beneficial manner along the Far Rockaway Beach shoreline as beach nourishment between Beach 27th Street and Beach 38th Street. The proposed maintenance dredging would remove approximately 250,000 cubic yards of sand from the East Rockaway Inlet and its deposition basins. Dredging would be required to a depth of -14 feet Mean Lower Low Water (MLLW) plus 2 feet allowable overdepth.
The purpose of the proposed work is to alleviate the effects of shoaling and maintain the authorized project dimensions, thereby providing safe and economical use of the East Rockaway Inlet by commercial and recreational boating interests while providing beneficial use of the dredged sand. Between maintenance operations, the bypassed sand placed at the feeder beach would be carried by littoral drift to feed down drift beaches. The maintenance operation would thus serve to place sand trapped in the channel back into the normal littoral movement that naturally replenishes the western beaches, while maintaining a safe channel for navigation.
Maintenance dredging of the channel and deposition basins at East Rockaway Inlet will be accomplished by pipeline dredge, hopper dredge or similar plant. The entire channel will generally not require maintenance dredging; only areas where shoaling has reduced the depth of the channel will require dredging. The dredged material would be required to meet all federal, state, and approved local criteria required by the government agencies having jurisdiction where the placement site is located.
The Contractor will be required to commence work within five (5) calendar days after the date of receipt by him of the notice to proceed, and to prosecute said work diligently and to complete the basic work ready for use not later than thirty-five (35) calendar days after the receipt by him of the notice to proceed (NTP). The contractor is required to maintain an integrated production of at least 12,000 cubic yards per calendar day.
The NAICS code will be 237990. The work is estimated to cost between $5,000,000 and $10,000,000. Plans and specifications for the subject project would be available in September 2016, with bid opening in October 2016. It is the intention of the government to award in October 2016 and issue the NTP in November 2016.
Liquidated Damages of $1,938.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete.
This is an unrestricted Procurement.