Maintenance Dredging Morehead City Harbor Ocean Bar Range A & Range B, Carteret County, North Carolina

Award Notice Posted

Solicitation number
GROUP4-10-R-W003
Agency
Awarded
to Weeks Marine Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W912EP-13-D-0012-DQ01 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

Award Notice

Update #1 ·

THIS NOTICE IS POSTED FOR INFORMATIONAL PURPOSES ONLY: THIS OPPORTUNITY IS AVAILABLE ONLY TO THE FOLLOWING CONTRACTORS AWARDED A CONTRACT UNDER SOLICITATION NUMBER
GROUP 4: W912EP-10-R-0026: Orion Marine Construction (W912EP-13-D-0003); Cavache, Inc. (W912EP-13-D-0004); Cashman Dredging & Marine Contracting (W912EP-13-D-0005); Cottrell Contracting Corporation (W912EP-13-D-0006); Great Lakes Dredge & Dock Company, LLC (W912EP-13-D-0007); Dutra Dredging Company (W912EP-13-D-0008); Marinex Construction, Inc. (W912EP-13-D-0009); Norfolk Dredging Company (W912EP-13-D-0010); Mike Hooks, Inc. (W912EP-13-D-0011); Weeks Marine, Inc. (W912EP-13-D-0012); Southern Dredging Co., Inc. (W912EP-13-D-0013); Manson Construction Company (W912EP-13-D-0014); C. F. Bean LLC (W912EP-13-D-0015)
PROPOSALS WILL NOT BE CONSIDERED FROM ANY ENTITY OTHER THAN THE PREVIOUSLY LISTED FIRMS INCLUDED IN THE GROUP 4 DREDGING MATOC POOL.
DESCRIPTION OF WORK: Project work consists of dredging, transporting, placing and shaping of dredged material on the beach and performing all pre and post construction beach surveys. Channel reaches to be dredged include Range A and Range B. The work will require removal and disposal of shoaled material that has accumulated in the channels since they were last dredged. The dredging shall be performed by hydraulic cutterhead suction dredge and/or hopper dredge. Dredging depth is 44 feet plus 2 feet of allowable overdepth. The estimated quantity of material to be dredged, including allowable overdepth, is approximately 600,000 to 700,000 cubic yards. Disposal of dredged material will be on the Fort Macon and Atlantic Beaches. The
ORDERING GUIDE
APPENDIX B
environmental window for beach disposal is 16 November to 30 April. The environmental window for dredging by hopper dredge is 1 December to 15 April. Beach disposal will be limited to 16 November 2013 thru 30 April 2014 and all work must be completed NLT 30 April 2014.
Magnitude of construction is between $ 5,000,000.00 and $10,000,000.00
Coast Guard Certified Equipment is required for this project. The request for proposal will be issued on 12 November 2013 and proposals will be due on or about 27 November 2013. The award of the task order will be made on the basis of Lowest Price Technical Acceptable (LPTA). The technical evaluation factors are:
- Availability of technically acceptable plant and equipment. Dredging shall be performed by an ocean certified dredge.
- Past Performance
See attached request for proposal for submission requirements.
The request for proposal will be issued in electronic format only and will be posted on the Army Single Face to Industry (ASFI) website at https://acquisition.army.mil/asfi/. In order to receive notification of any amendments, firms must REGISTER TO RECEIVE NOTIFICATION on the Federal Business Opportunities website at http://www.fedbizopps.gov/. If you are not registered, the Government is not responsible with providing you with notification of any changes to this solicitation. NAICS Code 237990, size standard $20 million.