About this opportunity

This Special Notice from the General Services Administration Public Buildings Service concerns a justification for other than full and open competition for a construction project at the Denver Federal Center in Lakewood, Colorado. The project involves replacing equipment and underground cabling throughout the site and upgrading items identified in engineering reports for Building 41 Service C and Buildings 54 and 55 transformers. The work includes replacing three on-site transformers and demolishing a portion of a brick wall enclosure for one transformer and rebuilding it expanded. Only one responsible source is available that is capable of performing the construction activity to alter the existing electrical grid due to the incumbent contractor's specialized experience working with the existing infrastructure at the Denver Federal Center over the past five years.

The purpose of the Special Notice is to provide details on the construction activity to alter the existing electrical grid at the Denver Federal Center, which includes replacing equipment and underground cabling throughout the site and upgrading items identified in engineering reports. Contractors must review the justification for other than full and open competition and provide any feedback by August 18, 2022. Only the contractor with specialized experience working with the existing infrastructure at the Denver Federal Center over the past five years is eligible for this sole source procurement opportunity.

Notice text

Construction activity to alter the existing electrical grid at the Denver Federal Center, Lakewood,  Colorado. Project would replace equipment  and underground cabling throughout the site and upgrade items identified in the engineering reports  for Building 41 Service C and Buildings 54 and 55 transformers at the Denver Federal Center, work  that includes replacement of three on-site transformers and all necessary related work. The related  work includes partial demolition of a brick wall enclosure for the electrical transformer that serves  Building 41,  and then replacing the demolished portion with an expanded brick wall for that enclosure.

Files

File Type Posted
2022-06-29 JOTFOC Sole Source B41CUP redacted.pdf PDF