John day powerhouse DC system upgrade
Awarded Award Notice Posted
- Solicitation number
- W9127N-14-R-0003
- Agency
- ENDIST Portland US Army Corps of Engineers, Department of Defense
- Awarded
- to Ross-Brandt Electric Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W9127N-14-C-0007 Federal contract award
- NAICS code
- 238210 Electrical Contractors and Other Wiring Installation Contractors
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
5 versions
Update #5 · Latest ·
Added: Oct 03, 2013 10:09 am
Modified: Dec 18, 2013 1:50 pmTrack Changes
The purpose of this project is to replace and upgrade significant portions of the DC and preferred AC system at John Day Dam Powerhouse, Sherman County, Oregon.
The DC and preferred AC system in the John Day Powerhouse consists of several 125VDC, 250VDC, and 48VDC battery banks, along with associated chargers, switchboards, panelboards, and inverters. This system is used to provide Uninterruptible Power to critical station service loads in the event of a power failure.
This project covers all work required to furnish, install, commission, and place in service the new DC and preferred AC system at John Day. This includes but is not limited to replacing and upgrading the batteries, battery racks, chargers, switchboards, panelboards, feeders, and feeder breakers associated with this system. Battery monitoring systems and hydrogen gas detection modules are also within the scope of this project. This work will also include power and control wiring replacement, conduit modification and installation, concrete core drilling, battery room ventilation, seismic anchorage of installed equipment, temporary DC power during construction, and mitigation of all environmental concerns, including possible asbestos abatement for older wiring, associated with work of this nature.
Update #4 ·
Added: Oct 03, 2013 10:09 am
Modified: Oct 18, 2013 9:29 amTrack Changes
The purpose of this project is to replace and upgrade significant portions of the DC and preferred AC system at John Day Dam Powerhouse, Sherman County, Oregon.
The DC and preferred AC system in the John Day Powerhouse consists of several 125VDC, 250VDC, and 48VDC battery banks, along with associated chargers, switchboards, panelboards, and inverters. This system is used to provide Uninterruptible Power to critical station service loads in the event of a power failure.
This project covers all work required to furnish, install, commission, and place in service the new DC and preferred AC system at John Day. This includes but is not limited to replacing and upgrading the batteries, battery racks, chargers, switchboards, panelboards, feeders, and feeder breakers associated with this system. Battery monitoring systems and hydrogen gas detection modules are also within the scope of this project. This work will also include power and control wiring replacement, conduit modification and installation, concrete core drilling,
battery room ventilation, seismic anchorage of installed equipment, temporary DC power during construction, and mitigation of all environmental concerns, including possible asbestos abatement for older wiring, associated with work of this nature.
This acquisition will be a Total Small Business Set-Aside under NAICS 238210. Small business size standard is $14,000,000.00. Point of Contact for small business questions or assistance is the Portland District Deputy for Small Business, Carol McIntyre at 503-808-4602 or carol.a.mcintyre@usace.army.mil.
A formal Request for Proposal (RFP) will be issued on or about 15 October 2013.
Update #3 ·
Added: Oct 03, 2013 10:09 am
Modified: Oct 16, 2013 12:52 pmTrack Changes
The purpose of this project is to replace and upgrade significant portions of the DC and preferred AC system at John Day Dam Powerhouse, Sherman County, Oregon.
The DC and preferred AC system in the John Day Powerhouse consists of several 125VDC, 250VDC, and 48VDC battery banks, along with associated chargers, switchboards, panelboards, and inverters. This system is used to provide Uninterruptible Power to critical station service loads in the event of a power failure.
This project covers all work required to furnish, install, commission, and place in service the new DC and preferred AC system at John Day. This includes but is not limited to replacing and upgrading the batteries, battery racks, chargers, switchboards, panelboards, feeders, and feeder breakers associated with this system. Battery monitoring systems and hydrogen gas detection modules are also within the scope of this project. This work will also include power and control wiring replacement, conduit modification and installation, concrete core drilling,
battery room ventilation, seismic anchorage of installed equipment, temporary DC power during construction, and mitigation of all environmental concerns, including possible asbestos abatement for older wiring, associated with work of this nature.
This acquisition will be a Total Small Business Set-Aside under NAICS 238210. Small business size standard is $14,000,000.00. Point of Contact for small business questions or assistance is the Portland District Deputy for Small Business, Carol McIntyre at 503-808-4602 or carol.a.mcintyre@usace.army.mil.
A formal Request for Proposal (RFP) will be issued on or about 15 October 2013.
Update #2 ·
Added: Oct 03, 2013 10:09 am
Modified: Oct 16, 2013 10:20 amTrack Changes
The purpose of this project is to replace and upgrade significant portions of the DC and preferred AC system at John Day Dam Powerhouse, Sherman County, Oregon.
The DC and preferred AC system in the John Day Powerhouse consists of several 125VDC, 250VDC, and 480VDC battery banks, along with associated chargers, switchboards, panelboards, and inverters. This system is used to provide Uninterruptible Power to critical station service loads in the event of a power failure.
This project covers all work required to furnish, install, commission, and place in service the new DC and preferred AC system at John Day. This includes but is not limited to replacing and upgrading the batteries, battery racks, chargers, switchboards, panelboards, feeders, and feeder breakers associated with this system. Battery monitoring systems and hydrogen gas detection modules are also within the scope of this project. This work will also include power and control wiring replacement, conduit modification and installation, concrete core drilling,
battery room ventilation, seismic anchorage of installed equipment, temporary DC power during construction, and mitigation of all environmental concerns, including possible asbestos abatement for older wiring, associated with work of this nature.
This acquisition will be a Total Small Business Set-Aside under NAICS 238210. Small business size standard is $14,000,000.00. Point of Contact for small business questions or assistance is the Portland District Deputy for Small Business, Carol McIntyre at 503-808-4602 or carol.a.mcintyre@usace.army.mil.
A formal Request for Proposal (RFP) will be issued on or about 15 October 2013.
Update #1 ·
Added: Oct 03, 2013 10:09 am
The purpose of this project is to replace and upgrade significant portions of the DC and preferred AC system at John Day Dam Powerhouse, Sherman County, Oregon.
The DC and preferred AC system in the John Day Powerhouse consists of several 125VDC, 250VDC, and 48VDC battery banks, along with associated chargers, switchboards, panelboards, and inverters. This system is used to provide Uninterruptible Power to critical station service loads in the event of a power failure.
This project covers all work required to furnish, install, commission, and place in service the new DC and preferred AC system at John Day. This includes but is not limited to replacing and upgrading the batteries, battery racks, chargers, switchboards, panelboards, feeders, and feeder breakers associated with this system. Battery monitoring systems and hydrogen gas detection modules are also within the scope of this project. This work will also include power and control wiring replacement, conduit modification and installation, concrete core drilling,
battery room ventilation, seismic anchorage of installed equipment, temporary DC power during construction, and mitigation of all environmental concerns, including possible asbestos abatement for older wiring, associated with work of this nature.
This acquisition will be a Total Small Business Set-Aside under NAICS 238210. Small business size standard is $14,000,000.00. Point of Contact for small business questions or assistance is the Portland District Deputy for Small Business, Carol McIntyre at 503-808-4602 or carol.a.mcintyre@usace.army.mil.
A formal Request for Proposal (RFP) will be issued in November 2013.