Idaho Panhandle NF, St. Joe Ranger Distirict - Fishhook Tunnel Remendiation - IMAT

Award Notice Posted

Solicitation number
12034318R0009
Agency
Awarded
to American Mining & Tunneling, LLC
Set-aside
No set-aside

Opportunity facts

Contract number
12034318C0064 Federal contract award
PSC
Not on record
Place of performance
Idaho Panhandle NF St Joe Ranger District Avery, Idaho 83802, United States

Notice details come from SAM.gov. Updated .

Notice text

Fishhook Tunnel Remediation

We are trying to determine the appropriate type set-aside for thie requirement, please have interested parties reply to Michael Allred mjallred@fs.fed.us by 3/23/2018. 

PROJECT DESCRIPTION AND LOCATION

(a) - Description of Work.


This project is for the remediation of an existing tunnel on the Fishhook Creek Road, (FDR 301). The work includes but is not limited to mobilization and demobilization, scaling the tunnel perimeter, furnishing and installing rock dowels, and furnishing, installing and testing wet-mix steel fiber reinforced shotcrete including installation of drainage mat prior to the application of shotcrete, and all other incidental items necessary to complete the project in accordance with the plans and specifications.

(b) - Project Location.


This project is located in the Idaho Panhandle National Forests. The tunnel is located on National Forest System Road No. 301 at Mile Post 3.78, in the NE ¼ of the SE ¼ Section 32, T.45 N., R.5 E., B.M., Shoshone County, Idaho (47.202384, -115.845134). The tunnel is on the St. Joe Ranger district.


The project can be accessed from Avery, Idaho by taking the old river road on the south side of the St. Joe River. Approximately 2 miles downstream from Avery is the intersection with forest road 301. Turn left on road 301 and proceed approximately 2.8 miles to the Fishhook tunnel.


(c) - Price Range. $1,000,000 - $5,000,000,


(d) - Pre-Bid Tour. No pre-bid tour is scheduled for this project. Interested Bidders are encouraged to visit the project site prior to submittal of prices and technical proposal.


(e) - Pre-Bid Conference: No pre-bid conference is scheduled for this project. Interested bidders may obtain additional information by contacting Michael Allred or Brent Briggs at:
Contracting Questions: Michael Allred, (208) 765-7456 or mjallred@fs.fed.us
Technical Questions: Brent Briggs, (208) 765-7436 or bbriggs@fs.fed.us


(f) - Start Work. It is estimated that the notice to proceed under this contract will be issued approximately mid-June, 2018 to facilitate the contract submittal process and contractor ordering of materials.


(g) - Period of Performance. All work under this contract has a completion date of October 30, 2018.


(h) - Restrictions. No wash water can be allowed to enter Fishhook creek. See Supplemental Specification Section 156 for requirements for accommodating public traffic during work.


(i) - Submittals. Allow 15 calendar days for government review of submittals.


ishhook Tunnel Remediation

Files

File Type Posted
6_FishhookPlans_2018_01_12.pdf PDF

Notice history

Notice Type Posted
IDAHO PANHANDLE NATIONAL FOREST, St. Joe Ranger District - Fishhook Tunnel Remediation - IMAT Latest Award Notice
This notice Original Award Notice