Hope valley campground renovation
Awarded Award Notice Posted
- Solicitation number
- AG-0261-S-10-0060
- Agency
- Region 4 - Intermountain Region Forest Service, Department of Agriculture
- Awarded
- to Hce, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- AG-0261-C-10-0023 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
- Place of performance
- 1.2 Project Location A. The project is located in the Carson Ranger District of the Humboldt-Toiyabe National Forest, Alpine County, California, in Section 7, T 10 N, R 18 E. It is located approximately 24 miles south of Minden, Nevada. The project may be accessed from Blue Lakes Highway. Markleeville, California 96120, United States
Notice details come from SAM.gov. Updated .
Notice text
4 versions
Update #4 · Latest ·
Added: Jun 04, 2010 8:49 pm Modified: Jun 30, 2010 3:10 pmTrack Changes The US Forest Service, Humboldt-Toiyabe National Forest is seeking a contractor to renovate the Hope Valley Campgrounds in the Carson Ranger District near Markleeville, CA in Alpine County. The estimated range is between $250,000- $500,000 dollars. It is available for full and open competition under the Small Business Competitiveness Demonstration Program. SCOPE OF CONTRACT - May not be all-inclusive; see following specifications, drawings, and schedule of items for specific quantities and parameters. This project includes: Base Bid: a. Removing existing spurs, roads, site furniture, utilities, and other existing site features as designated. This shall include obliterating and recontouring compacted areas not covered with new features. b. Updating and replacing water distribution system. A new well and holding tank have already been installed. Tie in new waterline, yard hydrants, valves, and drains into the existing system. c. Reconstruct aggregate roads, spurs, parking areas, curbstops, and culverts. d. Construct new family units, tent pads, and pathways. Install signs, gates, bear-proof food lockers, and unit markers. 2. Optional Items: a. Install concrete picnic tables with inlaid redwood seat. b. Install pedestal utility tables. c. Install pedestal grills. d. Install campsite fire rings. e. Install tent pad border and surfacing. f. Install 3-panel kiosk. Solicitation package including all specs, drawings, clauses, terms and conditions, as well as all forms needed to provide and offer will be available at this site on or before June 18, 2010. ATTENTION ALL POTENTIAL BIDDERS. I WILL BE TRYING TO POST a Solicitation within the next couple of hours, but in case it doesn't get posted in time, please be aware that the pre-bid/site visit meeting will BE HELD ON THE WORK SITE OF THE PROJECT!!!!!!!!!!! NOT THE SPARKS SUPERVISOR'S OFFICE. I am posting the drawings and specifications NOW, and will hopefully follow with the solictation today. We apologize for the last minute notice, and hope to still see as many of you as possible. The time and date remain the same. 0930 on Monday, JUNE 14, 2010. The site of the meeting is Hope Valley Campground: The project worksite is located in the Carson Ranger District of the Humboldt-Toiyabe National Forest, Alpine County, California, in Section 7, T 10 N, R 18 E. It is located approximately 24 miles south of Minden, Nevada. The project may be accessed from Blue Lakes Highway. Please RSVP the Contracting Officer at sroehr@fs.fed.us if planning to attend the meeting. Technical point of contact is Jordan Burge at (775) 352-1273
Added: Jun 11, 2010 2:31 pm Modified: Jun 30, 2010 3:10 pmTrack Changes ATTENTION ALL POTENTIAL BIDDERS. I WILL BE TRYING TO POST a Solicitation within the next couple of hours, but in case it doesn't get posted in time, please be aware that the pre-bid/site visit meeting will BE HELD ON THE WORK SITE OF THE PROJECT!!!!!!!!!!! NOT THE SPARKS SUPERVISOR'S OFFICE. I am posting the drawings and specifications NOW, and will hopefully follow with the solictation today. We apologize for the last minute notice, and hope to still see as many of you as possible. The time and date remain the same. 0930 on Monday, JUNE 14, 2010. The site of the meeting is Hope Valley Campground: The project worksite is located in the Carson Ranger District of the Humboldt-Toiyabe National Forest, Alpine County, California, in Section 7, T 10 N, R 18 E. It is located approximately 24 miles south of Minden, Nevada. The project may be accessed from Blue Lakes Highway. Please RSVP the Contracting Officer at sroehr@fs.fed.us if planning to attend the meeting. Technical point of contact is Jordan Burge at (775) 352-1273 The estimated range is between $250,000- $500,000 dollars. It is available for full and open competition under the Small Business Competitiveness Demonstration Program.
Update #3 ·
Added: Jun 04, 2010 8:49 pm
Modified: Jun 11, 2010 5:42 pmTrack Changes
The US Forest Service, Humboldt-Toiyabe National Forest is seeking a contractor to renovate the Hope Valley Campgrounds in the Carson Ranger District near Markleeville, CA in Alpine County.
The estimated range is between $250,000- $500,000 dollars. It is available for full and open competition under the Small Business Competitiveness Demonstration Program.
SCOPE OF CONTRACT -
May not be all-inclusive; see following specifications, drawings, and schedule of items for specific quantities and parameters. This project includes:
Base Bid:
a. Removing existing spurs, roads, site furniture, utilities, and other existing site features as designated. This shall include obliterating and recontouring compacted areas not covered with new features.
b. Updating and replacing water distribution system. A new well and holding tank have already been installed. Tie in new waterline, yard hydrants, valves, and drains into the existing system.
c. Reconstruct aggregate roads, spurs, parking areas, curbstops, and culverts.
d. Construct new family units, tent pads, and pathways. Install signs, gates, bear-proof food lockers, and unit markers.
2. Optional Items:
a. Install concrete picnic tables with inlaid redwood seat.
b. Install pedestal utility tables.
c. Install pedestal grills.
d. Install campsite fire rings.
e. Install tent pad border and surfacing.
f. Install 3-panel kiosk.
Solicitation package including all specs, drawings, clauses, terms and conditions, as well as all forms needed to provide and offer will be available at this site on or before June 18, 2010.
ATTENTION ALL POTENTIAL BIDDERS. I WILL BE TRYING TO POST a Solicitation within the next couple of hours, but in case it doesn't get posted in time, please be aware that the pre-bid/site visit meeting will BE HELD ON THE WORK SITE OF THE PROJECT!!!!!!!!!!! NOT THE SPARKS SUPERVISOR'S OFFICE.
I am posting the drawings and specifications NOW, and will hopefully follow with the solictation today.
We apologize for the last minute notice, and hope to still see as many of you as possible.
The time and date remain the same. 0930 on Monday, JUNE 14, 2010. The site of the meeting is Hope Valley Campground:
The project worksite is located in the Carson Ranger District of the Humboldt-Toiyabe National Forest, Alpine County, California, in Section 7, T 10 N, R 18 E. It is located approximately 24 miles south of Minden, Nevada. The project may be accessed from Blue Lakes Highway.
Please RSVP the Contracting Officer at sroehr@fs.fed.us if planning to attend the meeting.
Technical point of contact is Jordan Burge at (775) 352-1273
Added: Jun 11, 2010 2:31 pm
Modified: Jun 11, 2010 5:42 pmTrack Changes
ATTENTION ALL POTENTIAL BIDDERS. I WILL BE TRYING TO POST a Solicitation within the next couple of hours, but in case it doesn't get posted in time, please be aware that the pre-bid/site visit meeting will BE HELD ON THE WORK SITE OF THE PROJECT!!!!!!!!!!! NOT THE SPARKS SUPERVISOR'S OFFICE.
I am posting the drawings and specifications NOW, and will hopefully follow with the solictation today.
We apologize for the last minute notice, and hope to still see as many of you as possible.
The time and date remain the same. 0930 on Monday, JUNE 14, 2010. The site of the meeting is Hope Valley Campground:
The project worksite is located in the Carson Ranger District of the Humboldt-Toiyabe National Forest, Alpine County, California, in Section 7, T 10 N, R 18 E. It is located approximately 24 miles south of Minden, Nevada. The project may be accessed from Blue Lakes Highway.
Please RSVP the Contracting Officer at sroehr@fs.fed.us if planning to attend the meeting.
Technical point of contact is Jordan Burge at (775) 352-1273
The estimated range is between $250,000- $500,000 dollars. It is available for full and open competition under the Small Business Competitiveness Demonstration Program.
Update #2 ·
Added: Jun 11, 2010 2:31 pm
ATTENTION ALL POTENTIAL BIDDERS. I WILL BE TRYING TO POST a Solicitation within the next couple of hours, but in case it doesn't get posted in time, please be aware that the pre-bid/site visit meeting will BE HELD ON THE WORK SITE OF THE PROJECT!!!!!!!!!!! NOT THE SPARKS SUPERVISOR'S OFFICE.
I am posting the drawings and specifications NOW, and will hopefully follow with the solictation today.
We apologize for the last minute notice, and hope to still see as many of you as possible.
The time and date remain the same. 0930 on Monday, JUNE 14, 2010. The site of the meeting is Hope Valley Campground:
The project wordsite is located in the Carson Ranger District of the Humboldt-Toiyabe National Forest, Alpine County, California, in Section 7, T 10 N, R 18 E. It is located approximately 24 miles south of Minden, Nevada. The project may be accessed from Blue Lakes Highway.
Please RSVP the Contracting Officer at sroehr@fs.fed.us if planning to attend the meeting.
Technical point of contact is Jordan Burge at (775) 352-1273
Update #1 ·
Added: Jun 04, 2010 8:49 pm
The US Forest Service, Humboldt-Toiyabe National Forest is seeking a contractor to renovate the Hope Valley Campgrounds in the Carson Ranger District near Markleeville, CA in Alpine County.
The estimated range is between 250 - 500 dollars. It is available for full and open competition under the Small Business Competitiveness Demonstration Program.
SCOPE OF CONTRACT -
May not be all-inclusive; see following specifications, drawings, and schedule of items for specific quantities and parameters. This project includes:
Base Bid:
a. Removing existing spurs, roads, site furniture, utilities, and other existing site features as designated. This shall include obliterating and recontouring compacted areas not covered with new features.
b. Updating and replacing water distribution system. A new well and holding tank have already been installed. Tie in new waterline, yard hydrants, valves, and drains into the existing system.
c. Reconstruct aggregate roads, spurs, parking areas, curbstops, and culverts.
d. Construct new family units, tent pads, and pathways. Install signs, gates, bear-proof food lockers, and unit markers.
2. Optional Items:
a. Install concrete picnic tables with inlaid redwood seat.
b. Install pedestal utility tables.
c. Install pedestal grills.
d. Install campsite fire rings.
e. Install tent pad border and surfacing.
f. Install 3-panel kiosk.
Solicitation package including all specs, drawings, clauses, terms and conditions, as well as all forms needed to provide and offer will be available at this site on or before June 18, 2010.
There is a pre-bid meeting to be held at the Humboldt-Toiyabe National Forest Supervisor's Office, 1200 Franklin Way, Sparks, NV 89431,
The conference will be held on JUNE 14, 2010 at 9:30 AM.
Please RSVP the Contracting Officer at sroehr@fs.fed.us if planning to attend the meeting.
Technical point of contact is Jordan Burge at (775) 352-1273
Attachments
| File | Type | Posted |
|---|---|---|
| FULL SOLICITATION.pdf | ||
| Hope.Valley.Drawings.signed.pdf | ||
| Hope.Valley.Specs.pdf |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities