Heise Roberts Levee Rehab

Closed Pre-Solicitation Posted

Solicitation number
W912EF26RSS029
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

PSC
Not on record

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers, Walla Walla District, intends to solicit a firm-fixed-price contract for riprap revetment and levee stabilization work at four damage sites along the Upper Snake River in Madison and Jefferson Counties, Idaho, with responses to this sources-sought announcement due by June 4, 2026, and contract award expected in August 2026.

No set-aside is anticipated. Work encompasses approximately 2,100 linear feet across four discrete locations: Site #1 (600 linear feet on the right bank, 1 mile upstream of Lorenzo Bridge) requires excavation to approximately 8 feet and riprap armoring; Site #2 (600 linear feet near Lorenzo Bridge) requires riprap keying and toe protection; Site #3 (300 linear feet near Roberts Bridge) requires riprap revetment with keying to existing materials; and Site #4 (600 linear feet on the left bank, 1.5 miles downstream of Lorenzo Bridge) requires riprap toe bench placement and keying. The period of performance is four months, with in-water work restricted to October 1 through November 30, 2026.

NAICS 237990 applies. The small business size standard is $45 million. Responses to the sources sought should address relevant project experience with narratives, references, business size classification, bonding capacity, CAGE Code, and SAM.GOV Unique Entity ID. The Site Safety and Health Officer must have minimum three years' construction safety experience and current 30-Hour OSHA Construction Safety training; a Certified Erosion and Sediment Control Lead is also required. All work must comply with USACE Safety and Health Requirements Manual (EM 385-1-1) and utilize the Government-furnished Construction Contractor Module (QCS) of the Resident Management System. Submit responses to richard.w.bonnell@usace.army.mil.

Notice text

Heise-Roberts Right Bank Upper System Damage Site # 1 ? This site is located on the right bank levee system approximately 1 mile upstream of Lorenzo Bridge. At this levee segment, the river is eroding the streambank to the point of encroaching on the toe of the levee. This levee segment is not armored with riprap. The levee needs riprap revetment to protect the toe and slope of the levee prior to the next flood event. Excavating down approximately 8? to the toe of the levee and armoring the levee with riprap on the riverside side of the levee is necessary to protect the levee from eroding. This site is approximately 600 linear feet in length.Heise-Roberts Right Bank Upper System Damage Site # 2 ? This site is located on the right bank levee near Lorenzo Bridge. At this levee segment the large, dumped stone upstream of the railroad bridge abutment has been undercut and washed downstream. Additional riprap is needed to key in the remaining riprap and protect the toe of the levee and areas of erosion on the slope of the levee. This site is approximately 600 linear feet in length.Heise-Roberts Right Bank Lower System Damage Site # 3 ? This site is located on the right bank levee system near Roberts Bridge. This site has experienced erosion at the toe of slope, and the riprap has slid down the slope of the levee, leaving the upper levee exposed to erosion. Riprap revetment would need to be keyed in with existing riprap to protect the upper part of the levee and existing riprap needs to be keyed in to create a stable toe. This site is approximately 300 linear feet in length.Heise-Roberts Left Bank Levee System Damage Site # 4 - This site is located on the left bank levee system, approximately 1.5 miles downstream of Lorenzo Bridge. This site is at an impingement point that eroded a large amount of riverbank that was repaired during a flood fight. A Riprap toe bench needs to be placed and keyed in with the existing slope riprap revetment placed during previous flood fight conditions. This site is approximately 600 linear feet in length.

Files

Similar open opportunities

Opportunity Agency Set-aside Responses due
Mill Creek Section 205 Flood Risk Management Improvements Mill Creek Flood Control ChannelWalla Walla, WA 99362Walla Walla County 99362 · NAICS 237990 ENDIST Walla Walla No set-aside
Upper mississippi river restoration (UMRR) pool 12 floodplain forest stage one (1) - habitat rehabilitation and enhancement project (HREP) Mississippi River Basin Pool 12, from Lock and Dam 12 near Bellevue, Iowa, to Lock and Dam 11 in Dubuque, Iowa and Jo Davies County, Illinois 52001 · NAICS 237990 ENDIST Rock Island No set-aside
USACE SPK DBB Construction - Sacramento River East Levee Contract 5 (SREL C5), Sacramento, California California 95691, United States · NAICS 562910 ENDIST Sacramento Total Small Business
St Francis Town Levee Renovation Saint Francis, Arkansas, United States · NAICS 237990 ENDIST Memphis No set-aside
Natural Resource Investigations in the Upper Mississippi River Basin, Mississippi Valley Division (MVD) Rock Island, Illinois 61299, United States · NAICS 541690 ENDIST Rock Island No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors