Grand Prairie Pump Station Re-Procurement
Closed Solicitation Posted
- Solicitation number
- W912EQ23R0005
- Agency
-
ENDIST Memphis
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
Notice details come from SAM.gov. Updated .
About this opportunity
The contract opportunity involves the construction of a pump station superstructure, including dewatering, demolition of existing covers, equipment installation, and earthwork activities for the Grand Prairie Project. It also requires the installation of twin steel pipes, surge tanks, manways, cathodic protection, and an access road. The Request for Proposal due date has been extended to 17 August 2023.
- Construction of pump station superstructure
- Dewatering and demolition of existing covers
- Equipment installation
- Installation of twin steel pipes, surge tanks, and manways
- Installation of cathodic protection and access road.
Notice text
5 versions
Update #5 · Latest ·
Original scope of work consists of construction of the (base bid) pump station superstructure above elevation 190.0, including dewatering, demolition of existing covers, equipment installation, discharge header pipes to pipeline station 13+50 and all earthwork activities necessary to provide a completed pump station for the Grand Prairie Project. [Note: Portions of the earthwork were subsequently deleted from the scope of work in Modification No. P00018.] The work also required the installation of twin, 10 foot inside diameter steel pipes from pipeline station 13+50 to station 22+00, including all earthwork, installation of surge tanks and accessories, manways, cathodic protection and access road. There are 16 attachments to this solicitation. The following summarizes the revisions being issued through Amendment 0001.Request for Proposal due date has been extended. Revised Liquidated damages Lakey Report in its entirety as an amendment to Attachment 10Manuals for pumps and motors as ?Attachment 13Amendment 0002-Request for Proposal due date has been extended to17 August 2023. Amendment 0003 Revised Specif ication 01 91 00.15 for Total Building Commissioning, Paragraph 1.7.2.Additional supplemental sheet (Attachment 12) X-101 provided for recent hydrographs.Revised ?Attachment 4? to clarif y ref erenced PTA 4222 f ix.Revised ?Attachment 5? to include assumptions f or Modif ications.Revised ?Attachment 7? to add communication f or a hydrostatic lif t system.Attachment 14 Mud Valve SubmittalAmendment 0004 to revise the proposal due date due to an administrative error. Offerors do not have to acknowledge amendment 0004
Update #4 ·
Original scope of work consists of construction of the (base bid) pump station superstructure above elevation 190.0, including dewatering, demolition of existing covers, equipment installation, discharge header pipes to pipeline station 13+50 and all earthwork activities necessary to provide a completed pump station for the Grand Prairie Project. [Note: Portions of the earthwork were subsequently deleted from the scope of work in Modification No. P00018.] The work also required the installation of twin, 10 foot inside diameter steel pipes from pipeline station 13+50 to station 22+00, including all earthwork, installation of surge tanks and accessories, manways, cathodic protection and access road. There are 16 attachments to this solicitation. The following summarizes the revisions being issued through Amendment 0001.Request for Proposal due date has been extended. Revised Liquidated damages Lakey Report in its entirety as an amendment to Attachment 10Manuals for pumps and motors as ?Attachment 13Amendment 0002-Request for Proposal due date has been extended to17 August 2023. Amendment 0003 Revised Specif ication 01 91 00.15 for Total Building Commissioning, Paragraph 1.7.2.Additional supplemental sheet (Attachment 12) X-101 provided for recent hydrographs.Revised ?Attachment 4? to clarif y ref erenced PTA 4222 f ix.Revised ?Attachment 5? to include assumptions f or Modif ications.Revised ?Attachment 7? to add communication f or a hydrostatic lif t system.Attachment 14 Mud Valve Submittal
Update #3 ·
Original scope of work consists of construction of the (base bid) pump station superstructure above elevation 190.0, including dewatering, demolition of existing covers, equipment installation, discharge header pipes to pipeline station 13+50 and all earthwork activities necessary to provide a completed pump station for the Grand Prairie Project. [Note: Portions of the earthwork were subsequently deleted from the scope of work in Modification No. P00018.] The work also required the installation of twin, 10 foot inside diameter steel pipes from pipeline station 13+50 to station 22+00, including all earthwork, installation of surge tanks and accessories, manways, cathodic protection and access road. There are 16 attachments to this solicitation. The following summarizes the revisions being issued through Amendment 0001.Request for Proposal due date has been extended. Revised Liquidated damages Lakey Report in its entirety as an amendment to Attachment 10Manuals for pumps and motors as ?Attachment 13Amendment 0002-Request for Proposal due date has been extended to17 August 2023.
Update #2 ·
Original scope of work consists of construction of the (base bid) pump station superstructure above elevation 190.0, including dewatering, demolition of existing covers, equipment installation, discharge header pipes to pipeline station 13+50 and all earthwork activities necessary to provide a completed pump station for the Grand Prairie Project. [Note: Portions of the earthwork were subsequently deleted from the scope of work in Modification No. P00018.] The work also required the installation of twin, 10 foot inside diameter steel pipes from pipeline station 13+50 to station 22+00, including all earthwork, installation of surge tanks and accessories, manways, cathodic protection and access road. There are 16 attachments to this solicitation.The following summarizes the revisions being issued through Amendment 0001.Request for Proposal due date has been extended.Revised Liquidated damagesLakey Report in its entirety as an amendment to Attachment 10Manuals for pumps and motors as ?Attachment 13
Update #1 ·
Original scope of work consists of construction of the (base bid) pump station superstructure above elevation 190.0, including dewatering, demolition of existing covers, equipment installation, discharge header pipes to pipeline station 13+50 and all earthwork activities necessary to provide a completed pump station for the Grand Prairie Project. [Note: Portions of the earthwork were subsequently deleted from the scope of work in Modification No. P00018.] The work also required the installation of twin, 10 foot inside diameter steel pipes from pipeline station 13+50 to station 22+00, including all earthwork, installation of surge tanks and accessories, manways, cathodic protection and access road.There are 16 attachments to this solicitation.
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| Grand Prairie Pump Station Re-Procurement | Pre-Solicitation | |
| Grand Prairie Pump Station Re-Procurement | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity