FY21-22 Baltimore Harbor and Channels Maintenance Dredging Amendment 0001
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912DR22B0001
- Agency
- ENDIST Baltimore US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z1KF Maintenance Of Dredging Facilities
- Place of performance
- Baltimore, Maryland 21201, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks maintenance dredging services for navigation channels in the Port of Baltimore. The U.S. Army Corps of Engineers, Baltimore District will procure dredging of approximately 1.5 million cubic yards of material from three channels to a depth of 51 feet MLLW plus overdepth allowances. The work must be performed between November 2021 and March 2022 using equipment such as clamshell dredges, hydraulic unloaders, tugs, scows, and attendant plant and pipeline over a 130-day period. Bids are due by 11:00 AM on January 6, 2022 and will be evaluated for price.
There is no set-aside designation for this procurement. The primary NAICS code is 237990 and PSC code is D203. Incumbent contractors include Cashman Dredging & Marine Contracting Co., LLC, Great Lakes Dredge & Dock Company, LLC, and Weeks Marine, Inc. Bid amounts ranged from $18.1 million to $36.1 million including optional items. The dredged material will be placed at containment sites in Baltimore, Maryland, which is also the place of performance. Approximately 525,000 cubic yards will be disposed at the Masonville Confined Disposal Facility and 945,000 cubic yards at the Poplar Island Ecosystem Restoration Project.
Notice text
3 versions
Update #3 · Latest ·
Abstract of Bids.
Update #2 ·
Amendment 0001
FY 22-1 Baltimore Harbor & Channel Maintenance Dredging- Maryland Channels, Chesapeake Bay, Maryland.
The purpose of this amendment (0001) is to:
1. Remove DFARS Clause 252.223-7999 (Dev)
2. Provide a revised Price Schedule
3. Provide responses to the Request for Information (RFI's)
4. Extend the bid opening date to 12 JAN 2022, 11:00am
5. Provide Cox Inflow Plan
6. Provide XYZ survey plans
7. Provide an updated wage decision dated 17 DEC 2021
Update #1 ·
Scope of Work
FY22-1 Baltimore Harbor & Channels Maintenance Dredging – Maryland Channels, Chesapeake Bay, Maryland
Project Description: The project consists of maintenance dredging approximately 1,500,000 cubic yards (cy) from the deep-draft federal navigation channels serving the Port of Baltimore. The work is to be performed between November 2021 through March 2022. The dredging depth is planned for 51 feet mean lower low water (MLLW) with an additional 1 to 2 feet of allowable overdepth for three channel reaches including: Fort McHenry, Craighill Entrance, and Cutoff Angle Channels. The channels vary in width from 700 to 1,740 feet. The material dredged from the Fort McHenry Channel (approx. 525,000 cy) will be placed in the Masonville Dredged Material Containment Facility. The material dredged from the Craighill Entrance and Cutoff Angle channels (totaling approx. 945,000 cy) will be placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island. The work will include an optional item for dragging of an approximate 2,000,000 square foot area of the Northwest Branch East Channel, which is authorized to a depth of 49 feet MLLW. A large portion of the work may be performed during the winter months when weather conditions are most severe and will be accomplished in a heavy commercial waterway supporting the Port of Baltimore. The equipment required for this work commonly consists of two 30 plus cubic yard clamshell dredges, one 24-30 inch hydraulic unloader, six to eight large tugs, six to eight 2,500 – 6,000 cubic yard material scows, a drag bar and barge, and appropriate attendant plant and pipeline. The material will be dredged by clamshell/bucket and scow and placed within an anticipated period of performance of 130 calendar days from receipt of Notice-to-Proceed. 10 additional calendar days will be allowed if optional item 0008 is exercised and no additional construction time will be allowed if optional item 0009 is exercised.
Attachments
| File | Type | Posted |
|---|---|---|
| C.04.01 Abstract of Bids W912DR22B0001 Baltimore Harbor.pdf | ||
| B.08.03_AMD 0001_W912DR22B0001-0001_12-28-21.pdf | ||
| B.08.02_Final Plans FY22 MD.pdf | ||
| B.08.02_W912DR22B0001 Baltimore Harbor Dredging.pdf | ||
| B.08.02_Specs - Baltimore Harbor Maintenance Dredging - MD Channels - FY22-1.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| FY21-22 Baltimore Harbor and Channels Maintenance Dredging Amendment 0001 | Award Notice | |
| FY21-22 Baltimore Harbor and Channels Maintenance Dredging Amendment 0001 | Solicitation | |
| FY21-22 Baltimore Harbor and Channels Maintenance Dredging | Pre-Solicitation | |
| FY21-22 Baltimore Harbor and Channels Maintenance Dredging | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity