(FTG251) Maintenance Support Facility Ft Greely, AK
Closed Special Notice Posted
- Solicitation number
- W911KB26RWP04
- Agency
-
ENDIST Alaska
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Place of performance
- Fort Greely, Alaska 99731, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers Alaska District issued a Request for Information on August 27, 2026 regarding market intelligence and acquisition strategy for the Maintenance Support Facility at Fort Greely, Alaska, with responses due September 10, 2026 at 14:00 Alaska Time. This is a sources-sought announcement for informational purposes only; no formal solicitation is currently available, and participation is voluntary and will not obligate the Government to award any contract.
The project involves design and construction of a 56,000 square-foot heated and ventilated multipurpose maintenance facility with a target budget of $80.8 million in MILCON funding, scheduled for performance during FY28-FY30. The facility includes vehicle storage with warm capability and washing station, maintenance areas with receiving/loading docks, environmentally controlled storage for equipment and hazardous materials, administrative offices, lockers, shower facilities, and a fuel station. Construction must comply with Anti-Terrorism Force Protection requirements and match nearby Missile Defense Complex facilities.
The Government is evaluating three delivery methods: Accelerated Design-Build to Budget under FAR, Construction Manager at Risk under OTA, or Progressive Design-Build under OTA. Industry responses should address eight project-specific challenges including MDA/ATFP design coordination, site handover procedures, winter construction mitigation, temporary space requirements, schedule realism, mobilization timelines, and unidentified risks. Respondents must also address budget realism, primary cost drivers, supply chain risks, collaboration priorities, contract incentives, and bonding capacity. Companies should identify their status, bonding capacity, teaming structure, and intent to propose as prime or subcontractor. Responses should be submitted to Michelle Nelsen and Brittney Morrison at USACE Alaska District. NAICS 236220; small business size standard $45 million.
Notice text
REQUEST FOR INFORMATION (RFI) / MARKET INTELLIGENCE NOTICE
Notice: This is a Request for Information (RFI) for market intelligence and for informational purposes only. This announcement does not constitute a Solicitation or a Request for Proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should a formal solicitation be issued in the future.
NAICS Code: 236220 – Commercial and Institutional Building Construction
(Note: While Other Transaction Authority is not subject to FAR-based small business regulations, this NAICS code is provided for market research to help the Government understand the size and demographics of the interested industrial base.)
Small Business Size Standard: $45 Million
PROJECT OVERVIEW
The U.S. Army Corps of Engineers (USACE), Alaska District, has a requirement for Maintenance Support Facility consists of a heated and ventilated, multipurpose maintenance facility separated into a vehicle storage area and maintenance area. The vehicle storage area includes warm storage capability for mission vehicles and a vehicle washing station. The maintenance area includes receiving/loading docks; environmentally controlled storage areas for interceptor equipment, tools and maintenance equipment, spares, forklift/s and hazardous material spill response materials, arctic clothes and equipment, and maintaining Facility Systems Operation and Maintenance manuals, drawings and other documentation; offices, workstations, and conference space for related management and administrative personnel; lockers, latrines and shower facilities; and breakroom. Construction includes a Fuel Station for organizational vehicle fueling. Cyber-security measures include Facility Related Control Systems for Electronic Security System, Building Automation System, Electric Power Management System, Lighting Control, and Fire Alarm / Mass Notification Systems. Construction to match nearby facilities on the Missile Defense Complex (MDC). Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage.
Estimated Acquisition Magnitude: Between $75,000,000-$85,000,000.
Planned Acquisition Strategy: Anticipated to utilize Progressive Design Build via Other Transaction Authority (OTA)
The Alaska District is conducting market intelligence to assess industry capability and interest in supporting this effort utilizing an Other Transaction (OT) Agreement under the authority of 10 U.S.C. § 2808a, Facility Construction or Repair: Transactions Other Than Contracts and Grants. This authority is distinct from the Department of Defense prototype OT authorities commonly associated with 10 U.S.C. § 4021 and 4022. This authority is intended for military construction projects that involve testing and experimentation associated with new and emergent construction technologies to achieve potential benefits such as enhanced mission resilience, improved installation support, or cost and schedule reduction. The anticipated delivery method is Progressive Design Build.
- Phase 1: Design and Pre-Construction Services - The OT Awardee shall assist the Government collaboratively in achieving its goals with respect to the project’s scope, constructability, budget, quality, schedule, and in coordination with the Designer of Record (DOR).
- Phase 2: Final Design and Construction - Upon reaching an agreed-upon level of design (e.g., 95 to 100%), the Awardee will propose a Guaranteed Maximum Price (GMP). If the GMP is accepted, the Government will exercise construction execution. If a GMP cannot be agreed upon, the Government retains an "off-ramp" to complete the construct the facility via alternative methods.
SUBMISSION INSTRUCTIONS: Please see the attached Market Intelligence Questionnaire pdf and email your response to Michelle Nelsen Michelle.Nelsen@usace.army.mil and Brittney Morrison at Brittney.morrison@usace.army.mil by 10 September 2026 at 14:00 Alaska Time. Any questions regarding the requirement or issues please reach out to Brittney Morrison at brittney.morrison@usace.army.mil and Michelle Nelsen at michelle.nelsen@usace.army.mil
Files
| File | Type | Posted |
|---|---|---|
| Market Research Intelligence Questionnaire FTG251.pdf |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| JBR041 – Pallet Processing Facility/JBR044 – Rapid Deployment Facility | Department of Defense | No set-aside | |
| Market Intelligence for EIE483 and EIE484 | ENDIST Alaska | No set-aside | |
| Market Intelligence for EIE480 and EIE482 | ENDIST Alaska | No set-aside | |
| FTG247 Replace UPS at IDT1, Fort Greely, Alaska | ENDIST Alaska | Total Small Business | |
| EIE485 Consolidated Munitions on Quarry Hill, Eielson AFB, AK | Department of Defense | No set-aside |