About this opportunity

The Federal Bureau of Prisons (BOP) plans to award a firm fixed-price construction contract for the emergency replacement of wastewater treatment plant valves at the Federal Correctional Institution in Phoenix, Arizona. The contractor will be responsible for the removal and disposal of existing equipment, installation of new equipment, testing, and providing training on usage and maintenance. The project is expected to be completed within 180 calendar days from the issuance of the notice to proceed.

List of Products and Services:

  1. Removal of existing equipment
  2. Disposal of removed items
  3. Installation of new wastewater treatment plant valves
  4. Testing of the new valves
  5. Provision of divers
  6. Training on usage and maintenance of the new equipment
  7. Commissioning of equipment upon completion of installation and training.

Notice text

The Federal Bureau of Prisons (BOP) anticipates the award of a firm fixed-price construction contract entitled Emergency Replace Wastewater Treatment Plant Valves (WWTP) at the at Federal Correctional Institution (FCI) Phoenix.

FCI Phoenix is a Federal Correctional Facility located 37900 N. 45th Avenue, Phoenix, Arizona 85086.  The contractor will provide all labor and materials and will be responsible for the complete removal of all necessary existing equipment and dispose of all items properly and installing all new equipment, per all national/local codes, and Bureau of Prisons policies. This includes, but is not limited to, digging the valves, shoring the hole around the valves, replacing the valves, testing the valves, and providing divers. The Contractor will provide training on usage/maintenance of all equipment. Contractor and FBOP staff will commission equipment upon completion of installation and training.

The performance period for the project will be 180 calendar days from issuance of the notice to proceed.

Files

File Type Posted
Abstract.pdf PDF
Amendment 0002.pdf PDF
Instruction to Bidders.pdf PDF
Bid Bond SF-24.pdf PDF
Wage determination.pdf PDF
(8) 23Z6AM8 - Drawings.pdf PDF
ncic_check_form.pdf PDF
(7) 23Z6AM8 - Statement of Work.pdf PDF
Solicitation_3.pdf PDF

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
FCI Phoenix Emergency Repair Wasterwater Treatment Plant Valve Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Replace Water Tanks FCI Marion Marions, Illinois Illinois 62959, United States · NAICS 238220 BOP Field Acquisition Office Total Small Business
Mike Monroney Aeronautical Center (MMAC) Industrial Waste Water Treatment Plant Upgrades Oklahoma City, Oklahoma 73169, United States · NAICS 237110 Franchise Acquisition Servies Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors