Duluth Harbor, MN maintenance dredging
Closed Pre-Solicitation Posted
- Solicitation number
- PANGLR-24-P-0000-000859
- Agency
-
ENDIST Detroit
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y1KF Construction Of Dredging Facilities
- Place of performance
- Superior, Wisconsin 54880, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers Detroit District is seeking contractors to perform maintenance dredging in Duluth Harbor, Minnesota. The project involves mechanical dredging within the Duluth-Superior Federal navigation channel and placement of the dredged material along Wisconsin Point. Contractors must have the equipment and ability to perform in-water mechanical dredging to the required depths and implement best management practices to limit turbidity and debris at the placement site. The required dredging depths range from approximately 27 to 33 feet below Low Water Datum, and the quantity of dredged material may range from 50,000 to 80,000 cubic yards. The anticipated period of performance is from July 15, 2024, through October 15, 2024.
This is an unrestricted procurement with full and open competition. The North American Industrial Classification System (NAICS) code is 237990, which has a size standard of $37 million in average annual receipts. The estimated price range of construction is between $1 million and $5 million, and the government intends to issue a firm-fixed price contract. Interested contractors must register their firm at the System for Award Management (SAM) to conduct business with the federal government.
Notice text
The U.S. Army Corps of Engineers Detroit District is seeking contractors for maintenance dredging in Duluth Harbor, MN, zip code 54880-6818 (Superior).
The project consist of the following:
This project involves maintenance dredging in the Duluth-Superior Federal navigation channel located along the border of Wisconsin and Minnesota. The Contractor will be required to mobilize a dredge to the Duluth-Superior channel and perform mechanical dredging within the channel. Dredging will be required within the following areas:
• The mouth of the Duluth Entry
• Two separate areas of the Duluth Harbor Basin along the westerly channel limits
The contract may also include options to perform additional dredging within the East Gate Basin along the easterly channel limits.
Dredged material will be placed along Wisconsin Point adjacent to a closed former landfill between the Ordinary High Water Mark (OHWM) and the most landward 12 foot (ft) depth contour. The Contractor must have the equipment and ability to perform in-water mechanical dredging to the required depths, to transport and place material at the required placement area.
Placement at Wisconsin Point will require the implementation of various Best Management Practices (BMPs) to ensure turbidity is kept within state-approved limits at the placement site. BMPs will also be implemented to limit debris being placed along Wisconsin Point. Placement at Wisconsin Point is unrestricted for hydraulic or mechanical placement. An allowable transfer box location will be provided to allow for hydraulic placement operations and will be located adjacent to the southernmost limits of the Federal navigation channel (near Allouez Bay). An allowable pipeline path (for hydraulic placement) and staging area will be provided near a closed former landfill on Wisconsin Point, adjacent to the placement site. If the pipeline access route is utilized, the Contractor will be responsible for ensuring Wisconsin Point Road and Allouez Bay (pedestrian, vehicular and watercraft traffic) remains accessible to the public through the life of the project.
The required dredging depths will be approximately 27 ft to 33 ft below Low Water Datum (LWD) depending on the location within the harbor. The material is expected to be a mix of (predominantly) sand, with the potential of minor debris typical in an active harbor. The quantity of dredged material in the contract may range from approximately 50,000 cubic yards to 80,000 cubic yards.
The anticipated period of performance for dredging is 15 July 2024 through 15 October 2024.
The Contractor would then demobilize when dredging and material placement are complete.
General Information:
This announcement serves as the advance notice for this project.
The estimated price range of construction is between $1 Million and $5 Million.
This project will be advertised unrestricted with full and open competition.
The North American Industrial Classification System (NAICS) code is 237990, which has a size standard of $37 Million in average annual receipts.
The Government intends to issue a firm-fixed price contract.
Approximate solicitation posting date: the beginning of June 2024.
The contract is anticipated to have a completion date of 15 October, 2024.
A bid bond in the amount of the offer is required.
The solicitation package materials, documents, drawings, specifications, and attachments to the anticipated solicitation will be available only electronically via SAM.gov.
In order for interested contractors to conduct business with the Federal Government, contractors must register their firm at the System for Award Management (SAM). Contractors can access SAM for free at www.sam.gov.
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Pre-Solicitation | |
| Duluth Maintenance Dredging 2024 | Pre-Solicitation |