Design-build services - boiler modernization - beltsville, maryland

Closed Pre-Solicitation Posted

Not the latest version. See the latest solicitation from .

Solicitation number
1232SA21R0009
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Beltsville MD 20705, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is for design-build services to modernize three existing 5000 MBH boilers at the National Agricultural Library in Beltsville, Maryland. The USDA Agricultural Research Service intends to issue a request for proposal for this project to be completed using a two-phase design-build delivery method. Phase one will evaluate past performance, management approach, and technical approach to shortlist up to four contractors to participate in phase two. Phase two will evaluate the specific technical approach and schedule for the boiler modernization. Proposals are due by June 25, 2021 and the contract is valued over $1 million.

This requirement is set aside for total small businesses and uses NAICS codes 238220 for construction and 541330 for engineering with a size standard of $16.5 million. The project will replace three existing boilers with new high efficiency boilers, provide final design and sizing of boilers and associated mechanical equipment, piping, and accessories. The work must be completed while the laboratory remains open and is estimated to take 365 calendar days to design and construct once a notice to proceed is issued.

Notice text

The USDA, Agricultural Research Service, intends to issue a Request for Proposal (RFP) for the Modernization of Boilers for the National Agricultural Library (NAL), located in Beltsville, Maryland. This NAL Boiler Modernization Project will be implemented by the Design-Build project delivery method and will involve the modernization and renovation of a current research campus. The USDA has developed a set of Bridging Documents (plans and specifications) showing and describing the project’s essential elements. 

BACKGROUND:  The boilers at NAL have far exceeded their service life.  The original boilers have outlived their original functional provisions and the employees and staff would benefit from a modernization of the boilers to allow for improved heat and hot water function. 

REQUIREMENT:  This requirement is a design-build effort to replace three (3) existing 5000 MBH Boilers with new high efficiency boilers.  It will provide the final design to size the boilers, pumps, hydronic system, lay out the equipment and piping, replace the domestic water system, and eliminate the full height boiler stack.

Work planned for this project includes installation of new boilers and appurtenant mechanical equipment, piping, accessories, capping of roof curbs, construction of new concrete equipment pads, and infill of opening in existing exterior concrete wall.

The work will be completed while the laboratory remains open. The Bridging Documents will consist of a complete 50% design submission. The Design Build Contractor (DBC) will use these documents as the basis to complete a set of construction documents.

BASE:

Base Item – All project design and construction work is contained in the Base Item.

GENERAL:

The contract performance time is approximately 365 calendar days (to include design completion and construction) after the issuance of the Notice to Proceed. Total Design-Build cost is estimated to be more than $1 million.

The North American Industry Classification System (NAICS) codes are 238220 (Construction) and 541330 (Engineering), with a size standard of $16.5 million.

This project will be initiated by a two-phase solicitation process. This procurement is being issued as a Total Small Business Set Aside utilizing the negotiated method by issuing a Request for Proposal (RFP).

The solicitation criteria rely upon industry standards, where allowable, to afford the offeror a degree of design flexibility while meeting certain specific project requirements. The successful DBC must design and construct complete and useable facilities, as described in the RFP documents.

One solicitation will be issued covering both phases. Phase One is the pre-selection phase. This phase does NOT include the submission of a price proposal.

Evaluation factors under Phase One may consist of the following:  Past Performance, Management Approach, and General Technical Approach.

Proposals will be evaluated in Phase One to determine which offerors are eligible to submit proposals for Phase Two, and an amendment to the RFP will be issued to those selected offerors (maximum of four). The detailed project performance requirements for this project will be included in the amended RFP package for Phase Two.

The Evaluation Factors for Phase Two will consist of the following:  NAL Boiler Specific Technical Approach and NAL Boiler Schedule.

The contract will be awarded, based on the Best Value "Trade-off" process, to the firm whose proposal, in the judgment of the Contracting Officer, provides the best combination of design features and cost or price reasonableness. In making this determination, all evaluation factors other than cost or price, when combined, are approximately equal to cost or price. The Government reserves the right to make the contract award to other than the lowest price offeror, price and other factors considered.

Bid Bonds are required. Performance and Payment Bonds will be required of the successful offeror. It is anticipated that the solicitation documents will be available for viewing and downloading on beta SAM (www.beta.SAM.gov) on or about May 27, 2021.

Plans and specifications will NOT be provided in hard paper copy. The solicitation and all amendments for the RFP will be posted on www.beta.SAM.gov.

Proposals are due on or about June 25, 2021, by 4:30 pm EST., via electronic format.  All proposals shall be emailed to angela.wingert@usda.gov.  All format requirements outlined in the solicitation shall be followed for electronic submission.  All proposals must be received in electronic format by the date and time specified.  All responsible sources may submit a proposal which will be considered.

Offerors will have the maximum timeframe expressed in calendar days below to develop proposals in response to Phase I and Phase II. In Phase I, the Government will evaluate Performance Capability proposals to “Shortlist” a maximum of four (4) of the most highly qualified Offerors. ONLY those firms selected in Phase I will be invited to participate in Phase II.

    1. PHASE I - 30 Calendar Days
    1. PHASE II – 30 Calendar Days

It is the responsibility of the contractor to check www.beta.SAM.gov frequently for any amendments or changes to the solicitation. The Government is not responsible for any loss of internet connectivity or for an offeror’s inability to access the documents posted at the referenced website. No copies on electronic storage (USBs, DVDs, CDs, etc...) or hard copies will be made available.

If an offeror would like to be listed so that others can see that the offeror is an interested vendor, the offeror must click the “Add Me to Interested Vendors” button in the listing for this solicitation on www.beta.SAM.gov

 

Notice history

Notice Type Posted
Design-Build Services for the Replacment of Boilers, Beltsville, Maryland Latest solicitation Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
16292 Steam Boiler Replacement Hill AFB, Utah 84056, United States · NAICS 238220 Air Force Sustainment Center Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors