Design and Construction of an Army Reserve Center at Loveland, Colorado
Award Notice Posted
- Solicitation number
- W912QR-12-R-0007
- Agency
-
ENDIST Louisville
US Army Corps of Engineers, Department of Defense
- Awarded
- to Liberty Mutual Insurance Company
- Set-aside
- HUBZone
Opportunity facts
- Contract number
- W912QR12C0028 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Not on record
- Place of performance
- Usace District, Louisville 600 Dr. Martin Luther King, Jr. Place, Room 821, Louisville KY 40202 US
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
SPECIAL NOTICE FOR INFORMATION PURPOSES ONLY.
On 4 January 2012, a pre-proposal conference was held for the Design and Construction of an Army Reserve Center at Loveland, CO. The following information includes the meeting minutes and the attendees.
MEETING MINUTES
PROJECT: Fort Collins Pre-proposal Meeting
Loveland, CO
LOCATION: Embassy Suites, Loveland
MEETING DATE &TIME: 04 January 2012, 0900 MST
ATTENDEES: See attached attendees list
ITEMS OF DISCUSSION:
1) Betty Beck, LRL Project Manager, opened the meeting with introductions. A sign-in sheet and agenda was circulated.
2) The Louisville District (LRL) is the design agent for the Army Reserve and will oversee the entire project.
3) Bids are due in Louisville, KY on 25 January 2012 at 11 AM EST. Bids will be good for 90 days.
4) Contract award is expected to be mid March 2012.
5) Fast tracking will be allowed and minor changes to the design are to be anticipated during the design phase of the project.
6) The Construction Cost Limit (CCL) is $10,710,000.
7) The bid will consist of two types of money: Military Construction Army Reserve (MCAR) and Operation & Maintenance Army Reserve (OMAR). The OMAR items are broken into two line items on the bid schedule. The OMAR line items are not part of the CCL.
8) The contract duration is 525 days from Notice to Proceed (NTP). The delivery method will be Design-Build.
9) Jon Miller, Mason and Hanger Project Manager, presented a project overview. The project is an FY 12 project for an Army Reserve Center to be located in Loveland/Windsor Colorado. The project controls are as follows:
a) 30,657 SF Training Building
b) 5811 SF Organizational Maintenance Shop (OMS)
c) 1217 SF Unheated Storage which is shown in the RFP as part of the OMS
d) 3370 SY Organizational Parking
10) The Tenant is the 409th, which is a vertical construction unit consisting of 4 platoons and a Headquarters Company. They are authorized 10 fulltime soldiers and 162 reservists. They are authorized 74 pieces of military equipment (52 trucks and 22 trailers). There are no tracked vehicles. They drill one weekend a month and the largest drill weekend is 162.
11) The primary guidance documents are UFC 4-171-05 and the RFP specification sections 01 02 00.00 48 and 00 80 00.00 06.
12) Mike Mayer, Mason and Hanger Civil Engineer, presented the site constraints. He discussed the easements on the property and the site setbacks. The topography was discussed as well as the drainage. EISA Section 438 is a requirement for this project. Post development run-off must not exceed pre development run-off. The project also must comply with Anti-terrorism standards UFC 4-010-01. This project shall be designed and constructed to achieve a LEED rating of Silver in accordance with LEED Version 3.0. The Contractor shall be responsible for certifying the project through the Green Building Certification Institute (GBCI).
13) The Contractor is responsible for making all permit applications and obtaining required municipal, utility, and regulatory agency coordination, reviews, permits, inspections and approvals, and is responsible for payment of any associated fees or charges.
14) Furniture is Government furnished, Government installed (GFGI). The Government contractor will be installing furniture during the final stages of construction. The D/B team will be responsible for coordinating with the furniture contractor. IT/Telecomm equipment is GFGI. The Government contractor will be installing IT/Telecomm equipment during the final 2-3 weeks of construction. The D/B team will be responsible for coordinating with the IT/Telecomm contractor.
15) Misty Jones, LRL Contracting Specialist, presented the unique contract requirements. The items discussed are listed below:
a) The project is a Hub zone set aside project.
b) The items discussed in this meeting are contractual.
c) The project will be awarded on best value.
d) Betterments are to be included into the overall bid and should be listed and priced.
e) Sign and acknowledge all amendments.
f) Please read and follow section 00114. Please be organized and don't be disqualified for none compliance.
g) Provide 5 copies of the proposal, one original and one electronic copy. Provide the original bid in a sealed envelope.
h) Evaluation factors are listed in the RFP in order of importance. Factors include Experience and Past Performance.
i) Bid Bonds are not required.
16) Jamie Benge, LRL Project Engineer, reviewed the post award design requirements. The following requirements of Specification Section 01 03 00.00 48 were discussed.
a) Identify the Designer of Record (DOR) for each discipline. The DOR shall be a registered professional Engineer or Architect.
b) A Registered Communication Distribution Designer (RCDD) is required to design the telecommunications system for this project.
c) A LEED Accredited Professional (LEED AP) is required for both design and construction.
d) A Registered Roof Observer (RRO) is required during all related construction activities.
e) The Contractor must submit, for Government acceptance, a Design Quality Control Plan (DQCP) before design may proceed. This plan must indicate the designer's integral role throughout design and construction.
f) A Design Charrette will be held to obtain an approved site and floor plan.
g) There will be four design submittals on this project: Interim, Final, Corrected Final, and Certified Final. The Certified Final Design is a submittal in which all review comments have been addressed and incorporated into the design. This design has been approved and is ready for construction.
h) Fast tracking is permitted and is further discussed in Section 00 80 00.00 06.
i) The Government will complete a review of each submittal. Government reviews are considered Quality Assurance reviews; not Quality Control reviews. The Contractor shall provide his own internal Quality Control before the design is submitted to the Government. Mason and Hanger, the RFP Preparer, will assist the Government in completing a compliance review to ensure the RFP requirements are being met.
j) A web-based system called Dr Checks will be used to input comments during reviews. The Contractor will be given access to this system and will be required to respond to all comments in the program.
k) This project is required to obtain a GBCI Silver Rating under LEED Version 3.0.
l) All drawings shall be prepared using Microstation Version 8i and Bentley BIM technology.
m) The furniture design is part of this contract and must meet the requirements of the "Army Reserve Design Process and Submittal Requirements Manual - Part C", which can be found on the Louisville District website.
n) Refer to Specification Section 01 03 00.00 48, Attachment A for specific furniture product specifications.
17) Jamie Benge also reviewed Specification Section 01 04 00.00 48 which describes the D/B process and the design schedule.
a) The schedule provided in this section is not intended to be the actual awarded D/B schedule. It should be used as guidance in preparing the schedule and sequence of work.
b) Government performance and review periods cannot be altered in the Contractor's proposed schedule which will be submitted for Government review and approval.
Site visit & Lunch
Meeting resumed at 01:00 p.m.
18) The Contractors wanted clarification on the water hook-ups fees. Does the Army Reserve own water rights on this property? This is to be clarified by Amendment.
19) Betty Beck thanked everyone for coming and wished all parties good luck. She then closed the meeting.
CORRECTIONS and OMISSIONS:
The preceding record is an accurate representation of the meeting as it transpired. Any person attending this meeting who has any additions, deletions or corrections should contact Misty Jones at misty.d.jones@usace.army.mil.
Minutes respectfully submitted by Jonathan Miller, Project Manager for Mason & Hanger.
Name Organization Phone
Charlie Harris McTech Corp 816-471-2039
Bruce Mellinger McTech Corp 816-471-2039
Matt Pagliasotti VEMAC 915-566-1911
Steven Hahn ECS & AMCS 303-282-4385
John Hess LMG Construction 816-474-4564
George Moore Encore Electric 720-279-5747
Erika Anderson Panduit 303-525-9501
Ben Winsor Patrick Engineering 303-532-8260
William Joyner PVC/Alliance 970-663-9700
Greg Wienberg Greenleaf Construction 816-714-3197
'Bo' Brown Brown Construction Consulting 970-222-6809
Scott Braband Champion Fence 303-467-1910
Les Trujillo Centerre Construction 303-220-9400
Brent Meisheid Centerre Construction 303-220-9400
Kile Morrison GLMV Architecture 816-444-4200
Dustin Graul Brinkmann Constructors 303-657-9700
Benjamin Barella Larimer Construction 3/534-7300
Wende Cook Panduit 720-205-9913
Joel Bennick Graygar 3/501-7203
Jeff Bowlus Guarantee Elec. 3/586-9141
Wendy Amann Huitt-Zollars 303-740-7325
Jack Tubbs McCauley Constructors 970-686-6300
Angelo Pereyra Epoxy & More 303-650-2525
Joseph Zorack Ground Engineering 970-622-0800
Richard Justice Anthony & Gordon 865-546-1776
Dino Ruffoni Gem City Roofing 307-745-5512
Jeff Richards MASS 719-243-2737
Brad Hix MASS 719-491-1178
Troy Eason MASS 719-240-2583
Bethany Beers Farnsworth Group 970-266-1066
Todd Krell Farnsworth Group 970-266-1066
Roger Hawkes CTI Construction Team 801-769-7300
Dave Mahan Stresscon Corp 719-205-4700
Brett Martinac Graybar 3/378-0628
Doug Donahue Gracon Corp 970-667-2203
Note: Information provided on the sign-in list may have been indiscernible and as a result interpreted incorrectly and/or omitted. Please refer to the Interested Vendor's list on FBO.gov for additional vendors/contractors.
Update #1 ·
Design/Build of a new Army Reserve Center, located in Loveland, Colorado. The project consists of two buildings and organizational parking: (1) The 150 - member Training Center (ARC) is approximately 30,657 SF; (2) The Organizational Maintenance Shop (OMS) is approximately 7,028 SF, which includes an Unheated Storage (US) Building; (3) The Organizational Parking consists of approximately 3,370 SY for the Military Equipment Parking (MEP) and 5,005 SY for the Privately Owned Vehicles (POV). The Training Center and OMS/US buildings are located in Larimer County, Colorado.
Primary facilities include land acquisition and construction of an Army Reserve Center (ARC) training building, Organizational Maintenance Shop (OMS), and unheated storage building. These buildings will be of permanent construction with reinforced concrete foundations, concrete floor slabs, structural steel frames, masonry veneer walls, standing seam metal roof, Heating, Ventilation, and Air Conditioning (HVAC), plumbing, mechanical systems, security systems, and electrical systems. Supporting facilities include land clearing, paving, fencing, general site improvements, and extension of utilities to serve the project.
This solicitation also contains option items for (1) OMAR equipment, (2) Bi-level loading ramp in the MEP, (3) Covered POV w/ Solar Arrays, (4) Additional gravel in the MEP Area, and (5) Additional gravel in the POV parking at the OMS.
This procurement is a HUBZone set aside.
The proposals will be evaluated using a Best Value Source Selection Process. The price range is $5,000,000 to $25,000,000. Proposals will be evaluated based on the following technical factors: Experience, Past Performance, Design/Technical Information, Safety, and Price and Pro Forma Requirements. All evaluation factors, other than cost or price, when combined, are equal to cost or price. The technical information contained in the proposal will be reviewed, evaluated, and rated by the Government. A construction cost limitation will be provided with the technical requirements package. The Solicitation package will provide site plans and floor plans of all buildings, the complete Statement of Work, and technical specifications. Furniture will be purchased by other contract.
The approximate solicitation issue date is 15 November 2011 and approximate proposal due date is 4 January 2012 at 11:00 a.m. Eastern Time. Refer to the solicitation for the official closing date, as it can change.
All Offerors are invited to attend the Pre-proposal Conference in the project vicinity. The exact date, time and location will be noted in the solicitation.
Project documents will be issued via the web only. Downloads are available via the Federal Business Opportunities (FedBizOpps) website http://www.fbo.gov. Amendments will be available only through the FedBizOpps website. This announcement serves as the advance notice for this project. The project will be awarded subject to availability of funds.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Design and Construction of an Army Reserve Center at Loveland, CO | Award Notice | |
| Special Notice regarding the Pre-proposal Conference held on 4 January 2012 for the Design and Construction of an Army Reserve Center at Loveland, CO. | Award Notice | |
| This notice | Award Notice |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity