Decommissioning of Lower Peverly Dam, Great Bay NW

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
140F0520R0020
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
238910 Site Preparation Contractors
Place of performance
Newington, Nh Usa
More information

Notice details come from SAM.gov. Updated .

About this opportunity

The Fish and Wildlife Service seeks to decommission the Lower Peverly Dam in the Great Bay National Wildlife Refuge in New Hampshire. Offerors must have experience removing dams and restoring waterways to meet contract objectives. Proposals will be evaluated on technical approach, past performance on similar projects, and price. The deadline for proposals is July 22, 2020.

There is no set-aside designation for this procurement. The projected NAICS code is 237990 and PSC code is R499. The single award contract will cover removal of the dam structure and restoration of one mile of riverbank at the project site in Newington, NH, with all work to be completed within 12 months of award. The government estimates the contract value to be between $2-5 million.

Notice text

4 versions

Update #4 · Latest ·

The Purpose of this Amendment#3 is to provide the following Items/updates to the solicitation;

1. Additional Question & Answer from firms.

2. Provide minor update to specification sections and an additional Supplemental Document , Ref; Hydrologic and Hydraulic Analysis (Supl#5 added)

3. Closing date is extended to Wednesday July 22, 2020, 1600 ET

There are no further updates or changes as a result of this Amendment#3

Update #3 ·

The Purpose of this Amendment#2 is to provide the following Items/updates to the solicitation;

1. Additional Question & Answer from the on site visit held June 24, 2020, provided as Amend 2 Attach 1.

2. Clarify closing date mentioned in Amendment#1, closing date for proposals remains unchanged for July 20, 2020 as stated in the SF1442

There are no further updates or changes as a result of this Amendment#2

Update #2 ·

Decommissioning of Lower Peverly Dam, Great Bay NWR, NH

The Purpose of this Amendment#1 is to provide the following Items/updates to the solicitation;

1. Minutes and the questions/answers from the on site visit held June 24, 2020.

2. Addendum 1 to the Specifications and Drawings related to tree trimming limitations.

3. Add to list of attachments four Supplemental Documents listed in specifications as supplement information (for information only)

There are no further updates or changes as a result of this Amendment#1, closing date for proposals remains the same (July 17, 2020)

Update #1 ·

Decommissioning of Lower Peverly Dam, Great Bay NWR, NH

Notice history

Notice Type Posted
Decommissioning of Lower Peverly Dam, Great Bay NW Award Award Notice
This notice Latest solicitation Solicitation
Decommissioning of Dam, Great Bay NWR, NH Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Float Well Pipe Repairs, Surry Mountain Dam, Surry, NH Surry, New Hampshire, United States · NAICS 237990 ENDIST New England No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors