Update #2 · Latest ·

The U.S. Army Corps of Engineers (USACE), Portland District, intends to award a firm fixed price Job Order under a Master Ship and Repair Agreement (MSRA) for overhaul, maintenance, and repair to the Dredge Essayons.

Major work items that may be associated with the overhaul and dry docking can be found at the bottom of this announcement. The list is not totally inclusive of all items.

All overhaul work shall be performed at the Contractor's facility. The Government will deliver the vessel to the contractor facility. Upon completion of the overhaul, the USACE personnel will conduct and pass dock and sea trials prior to delivery and acceptance of the vessel back to the Government.

USACE ESSAYONS is a trailing arm suction Hopper Dredge built in 1984. It has the following Characteristics:

Length Overall 350 Feet

Length between perpendiculars 333 Feet Beam Molded 68 Feet

Beam Overall (With Drag Arms Lowered) 108 Feet Registered Gross Tonnage 7,248 Long Tons Normal Light, Draft Forward 19'-0"

Normal Light, Draft Aft 21'-0" Class ABS Loadline

The period of performance is expected to start August 2022 and last through February 2023. The shipyard availability is anticipated to go from December 2022 through February 2023 with a sixty (60) day drydock period during this availability. Optional items (tasks) will be included in this job order and the period of performance for these items will be concurrent with the above period of performance.

The American Bureaus of Shipping International Load Line Certificate will be endorsed during this availability. The Drydock Examination, Internal Structural Review and the Annual Inspection for renewal of the U.S. Coast Guard Certificate of Inspection will be performed during this availability.

Prospective contractors must have, or be capable of, entering into a MSRA with USACE, Portland District. Every prospective contractor that wishes to be considered for the award of the job order under this solicitation must hold a MSRA for overhaul of the ESSAYONS with USACE, Portland District. If a prospective contractor wishes to submit a bid for this job order and has not already entered into a MSRA for overhaul of the ESSAYONS with Portland District, then the following procedures shall be followed:

1.         The prospective contractor shall submit a capabilities package in accordance with the sources sought notice titled “USACE; Portland District Dredge Vessel MSRA” posted on beta.sam.gov under W9127N22R0031.

The capabilities package shall be received by Portland District no later than the time identified within the Sources Sought.

2.         If there are any questions regarding the MSRA for overhaul of the ESSAYONS or the procedures to submit a capabilities package for consideration for the award of a MSRA, please contact Mr. Brandon Lasich at Brandon.M.Lasich@usace.army.mil and Mr. Mitchell Johnson at Mitchell.J.Johnson@usace.army.mil.

The area of consideration for award is limited to Alaska, California, Oregon, Washington, and Hawaii. Contractors outside of this area will not be considered.

A mandatory pre-bid site visit will be required as part of the solicitation. The anticipated dates for the site visits will be advertised in the solicitation. Final site visit information will be included in the solicitation. To schedule a site visit, please contact Mr. Brandon Lasich at Brandon.M.Lasich@usace.army.mil and CC Mr. Mitchell Johnson at Mitchell.J.Johnson@usace.army.mil.

The job order award will not be considered commercial in nature. Award will be made as a whole to one Offeror. The acquisition will be solicited using the procurement process prescribed in Part 14, Sealed Bidding, of the Federal Acquisition Regulations (FAR).

Award will not be made to any company that does not have a MSRA in place that meets the qualification requirements found in the sources sought announcement above.

A location differential will be added to total price/cost of bids for all locations in excess of 300 Nautical Miles (NM) from the Essayons’s home base location (Portland, OR). The method of calculation will include using the General Services Administration (GSA) standard rates for travel and per diem for personnel who will not be at their home base location combined with the cost of ship travel to location.

This full and open solicitation will be issued in electronic format only. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored. This solicitation is anticipated to be available approximately July 01, 2022 under Solicitation Number W9127N22B0009. NOTE: The Response Date referenced in this notice does not refer to the BID DUE DATE. Information on the BID DUE DATE will be stated in the solicitation.

Any prospective Offeror must first register in the System for Award Management (SAM) at www.sam.gov. After completing SAM registration, interested Contractors and their Subcontractors must then register at https://www.beta.sam.gov in order to obtain solicitation documents, plans and specifications for this solicitation. It is the contractor's responsibility to monitor beta.sam.gov for any amendments.

The NAICS Code is 336611; PSC Code J999.

The Point of Contact for small business questions or assistance is the Portland District Small Business Specialist, Carol McIntyre, 503-808-4602 or Carol.A.Mcintyre@usace.army.mil.

Major Items included are as follows, but are not limited to:

Transportation

Tug Services

Crane Services

Connection/Disconnection of Services

Field Office

Parking

Drydock Lift and Lay Days

Wet Berth

Electricity

Steam

Marine Chemist Certificates

Fire Suppression Services

Bilge Maintenance

Lower Hull - Zinc Coat

Coatings Upper and Lower Hull - Anti Corrosive Coat

Coatings Upper and Lower Hull - Final Coat 

Coatings Lower Hull - Anti Foulant Coat

Irathane 155 Urethane Coating Hull Degreasing

Hull Fire Hose Washing

Hull 10,000 PSI Water Washing

Hull Zinc Anode Renewal

Sluice Valve Replacement/Overhaul

Hopper Jetting Gate Valve

Main Sea Strainer Repairs

Drag Wire Replacement

Purchase Drag Wires

Dragarm Sheave Inspection

Discharge Piping Inspection

Hopper Jetting System Cleaning

Weir Seal Replacement

Hopper Inspection Staging

Tower Staging

Propeller Blade Inspection/Replacement

Propeller Hub Replacement

Tailshaft Replacement

Stern Tube Shaft Seal Replacement

Bow Thruster - Lower Gearbox LGB/Pod Change Out

ABS Support

Audio Gauge Reading

Elevator Inspection and Repair

Anchor Chain Locker Reconditioning

Life Raft Annual Service

Sludge Tank Annual Maintenance

Strut and Stern Tube Bearing Inspection

Rudder Bushing Clearance Documentation

Dock and Sea Trials

ALMO Pipe Chute and Lower Pump Room Dredge Pipe Removal

Main Pedestal Crane Replacement

Update #1 ·

THIS IS A PRESOLICITATION NOTICE FOR THE MOUNT SAINT HELENS SEDIMENT RETENTION STRUCTURE (SRS) CREST RAISE

The Government intends to procure this requirement on a competitive basis in accordance with the provisions as set forth in FAR Part 15, Contracting by Negitiation. A formal solicitation will follow this announcement on or around May 31, 2022. 

SOLICITATION NUMBER: W9127N22R0021

NAICS Code: 237990

SIZE STANDARD: $39.5M

SET-ASIDE: Full and Open

DESCRIPTION OF REQUIREMENT

The work will involve the construction of a second crest raise at the SRS. The second crest raise will raise the spillway channel by 10 feet. Along with construction of the second crest raise, a new plunge pool will have to be constructed, and a low flow channel excavated in rock. As part of the project, the contractor will be required to construct water diversion structures so that the work can be performed in the middle of a river. 

BACKGROUND

The SRS was constructed in the late 1980s to store the sediment coming off the avalanche area at Mount Saint Helens so that the sediment does not flow down to the low Cowlitz River. The main objective for the project is to keep the level of protection on the levee systems from Castle Rock to Lexington. A crest raise has already been completed in 2012. This will be the second of three planned crest raises. 

Files

File Type Posted
Industry Day.pptx PPTX presentation

Notice history

Notice Type Posted
FY23 Essayons Overhaul Award Award Notice
FY23 Essayons Overhaul Latest solicitation Solicitation
FY23 Essayons Overhaul Special Notice
This notice Pre-Solicitation
Crest Raise at MSH SRS Special Notice
Crest Raise at MSH SRS Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity