Construct 35TH brigade multifunctional warehouses

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W912ER23R0013
Agency
ENDIST Middle East US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1GZ Construction Of Other Warehouse Buildings
More information

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation from the Department of the Army Corps of Engineers Engineering District Middle East seeks the construction of five identical pre-engineered metal building system warehouses at the 35th Armor Brigade Base in Kuwait to house military vehicles and equipment. Each warehouse will house 44 Abrams M1A2K tanks and 4 M88 recovery vehicles, and include administrative offices, maintenance bays, storage, and mechanical systems. Proposals will be evaluated using the Best Value Trade-Off method, with evaluation criteria defined in the forthcoming RFP to be issued on SAM.GOV. Questions may be asked by December 28, 2023.

There is no set-aside designated for this procurement. The work involves the construction of facilities estimated to cost between $25-100 million and be completed within 723 calendar days of the notice to proceed. Each of the five warehouses will cover approximately 7,800 square meters and house 218 tanks total. The place of performance is the 35th Armor Brigade Base in Kuwait.

Notice text

5 versions

Update #5 · Latest ·

The purpose of Amendment 0004 is to add revised specs and drawings documents as well as extend the proposal due date to 28 December 2023, and change the Bidder Inquiry date to close on 14 December 2023. TAM is issuing a solicitation for Design-Bid-Build (DBB) award for the Construction of new pre-engineered metal building system warehouses located at the 35th Armor Brigade Base, Kuwait. PROJECT SCOPE: The scope of the project consists of the construction of five new warehouses to house 44 Abrams M1A2K tanks and 4 M88 recovery vehicles each. These warehouses include the addition of two administrative office areas, two maintenance bays, a 10 ton crane, and storage for tools and spare parts. Optional pavement and parking are included in the scope for this project. The five new warehouses are identical and will house 218 tanks total. Each warehouse is to be constructed for each of the M1A2K Armored Battalions within the 35th Brigade (2nd, 7th, 8th, 9th, 55th Battalions). Each warehouse is approximately 7,800 square meters consisting of open bay storage areas for the M1A2K tanks, maintenance bays with a bridge crane, and mezzanines with admin office areas for the approximate (50) personnel. The sites will include hardstands for tank maneuvering and inspection purposes. Existing utilities will be extended and rerouted as shown in the design drawings to be connected to the new facilities. Each warehouse will include fire suppression, humidity control, plumbing, electrical, HVAC systems, and communication (data and phone) per the design. The warehouses have electrically operated roll-up doors, with a forklift sized door, and additional fire hydrants as shown in the design. Storm-water drainage features are also included per the design to accommodate the runoff from the new facilities.1. The period of Performance is anticipated to be seven hundred and twenty-three (723) calendar days from Notice to Proceed (NTP) for the entire scope of work.2. The magnitude of the project is between $25 Million and $100 Million. PROPOSAL PROCEDURES: The Request for Proposal (RFP) will be issued on SAM.GOV. It is anticipated that the Best Value Trade-Off (BVTO) contracting method will be used to evaluate proposals. Evaluation criteria will be stated in the RFP. RESPONSE PERIOD: This is a pre-solicitation notice and is not a request for proposal (RFP) nor does it restrict the Government as to the ultimate acquisition approach. A response to this notice is not required. The Government will not reimburse respondents for any costs incurred in preparation of a response to this notice. Questions can be sent to Maria Martin, e-mail: Maria.L.Martin@usace.army.mil and Teliya Stevenson, e-mail: Teliya.J.Stevenson@usace.army.mil.

Update #4 ·

The purpose of Amendment 0003 is to add revised specs and drawings documents as well as extend the proposal due date to 18 December 2023, and change the Bidder Inquiry date to close on 06 December 2023. TAM is issuing a solicitation for Design-Bid-Build (DBB) award for the Construction of new pre-engineered metal building system warehouses located at the 35th Armor Brigade Base, Kuwait. PROJECT SCOPE: The scope of the project consists of the construction of five new warehouses to house 44 Abrams M1A2K tanks and 4 M88 recovery vehicles each. These warehouses include the addition of two administrative office areas, two maintenance bays, a 10 ton crane, and storage for tools and spare parts. Optional pavement and parking are included in the scope for this project. The five new warehouses are identical and will house 218 tanks total. Each warehouse is to be constructed for each of the M1A2K Armored Battalions within the 35th Brigade (2nd, 7th, 8th, 9th, 55th Battalions). Each warehouse is approximately 7,800 square meters consisting of open bay storage areas for the M1A2K tanks, maintenance bays with a bridge crane, and mezzanines with admin office areas for the approximate (50) personnel. The sites will include hardstands for tank maneuvering and inspection purposes. Existing utilities will be extended and rerouted as shown in the design drawings to be connected to the new facilities. Each warehouse will include fire suppression, humidity control, plumbing, electrical, HVAC systems, and communication (data and phone) per the design. The warehouses have electrically operated roll-up doors, with a forklift sized door, and additional fire hydrants as shown in the design. Storm-water drainage features are also included per the design to accommodate the runoff from the new facilities.1. The period of Performance is anticipated to be seven hundred and twenty-three (723) calendar days from Notice to Proceed (NTP) for the entire scope of work.2. The magnitude of the project is between $25 Million and $100 Million. PROPOSAL PROCEDURES: The Request for Proposal (RFP) will be issued on SAM.GOV. It is anticipated that the Best Value Trade-Off (BVTO) contracting method will be used to evaluate proposals. Evaluation criteria will be stated in the RFP. RESPONSE PERIOD: This is a pre-solicitation notice and is not a request for proposal (RFP) nor does it restrict the Government as to the ultimate acquisition approach. A response to this notice is not required. The Government will not reimburse respondents for any costs incurred in preparation of a response to this notice. Questions can be sent to Maria Martin, e-mail: Maria.L.Martin@usace.army.mil and Teliya Stevenson, e-mail: Teliya.J.Stevenson@usace.army.mil.

Update #3 ·

The purpose of Amendment 0002 is to add site visit photos and extend the proposal due date to 4 December 2023. TAM is issuing a solicitation for Design-Bid-Build (DBB) award for the Construction of new pre-engineered metal building system warehouses located at the 35th Armor Brigade Base, Kuwait. PROJECT SCOPE: The scope of the project consists of the construction of five new warehouses to house 44 Abrams M1A2K tanks and 4 M88 recovery vehicles each. These warehouses include the addition of two administrative office areas, two maintenance bays, a 10 ton crane, and storage for tools and spare parts. Optional pavement and parking are included in the scope for this project. The five new warehouses are identical and will house 218 tanks total. Each warehouse is to be constructed for each of the M1A2K Armored Battalions within the 35th Brigade (2nd, 7th, 8th, 9th, 55th Battalions). Each warehouse is approximately 7,800 square meters consisting of open bay storage areas for the M1A2K tanks, maintenance bays with a bridge crane, and mezzanines with admin office areas for the approximate (50) personnel. The sites will include hardstands for tank maneuvering and inspection purposes. Existing utilities will be extended and rerouted as shown in the design drawings to be connected to the new facilities. Each warehouse will include fire suppression, humidity control, plumbing, electrical, HVAC systems, and communication (data and phone) per the design. The warehouses have electrically operated roll-up doors, with a forklift sized door, and additional fire hydrants as shown in the design. Storm-water drainage features are also included per the design to accommodate the runoff from the new facilities.1. The period of Performance is anticipated to be seven hundred and twenty-three (723) calendar days from Notice to Proceed (NTP) for the entire scope of work.2. The magnitude of the project is between $25 Million and $100 Million. PROPOSAL PROCEDURES: The Request for Proposal (RFP) will be issued on SAM.GOV. It is anticipated that the Best Value Trade-Off (BVTO) contracting method will be used to evaluate proposals. Evaluation criteria will be stated in the RFP. RESPONSE PERIOD: This is a pre-solicitation notice and is not a request for proposal (RFP) nor does it restrict the Government as to the ultimate acquisition approach. A response to this notice is not required. The Government will not reimburse respondents for any costs incurred in preparation of a response to this notice. Questions can be sent to Maria Martin, e-mail: Maria.L.Martin@usace.army.mil and Teliya Stevenson, e-mail: Teliya.J.Stevenson@usace.army.mil.

Update #2 ·

The purpose of Amendment 0001 is to replace the corrupt MEP file with ATTACHMENT 1 FOR 23R00133 - 497741 - 35TH BDE CONSTR-RENOV WAREHOUSE.pdf. TAM is issuing a solicitation for Design-Bid-Build (DBB) award for the Construction of new pre-engineered metal building system warehouses located at the 35th Armor Brigade Base, Kuwait. PROJECT SCOPE: The scope of the project consists of the construction of five new warehouses to house 44 Abrams M1A2K tanks and 4 M88 recovery vehicles each. These warehouses include the addition of two administrative office areas, two maintenance bays, a 10 ton crane, and storage for tools and spare parts. Optional pavement and parking are included in the scope for this project. The five new warehouses are identical and will house 218 tanks total. Each warehouse is to be constructed for each of the M1A2K Armored Battalions within the 35th Brigade (2nd, 7th, 8th, 9th, 55th Battalions). Each warehouse is approximately 7,800 square meters consisting of open bay storage areas for the M1A2K tanks, maintenance bays with a bridge crane, and mezzanines with admin office areas for the approximate (50) personnel. The sites will include hardstands for tank maneuvering and inspection purposes. Existing utilities will be extended and rerouted as shown in the design drawings to be connected to the new facilities. Each warehouse will include fire suppression, humidity control, plumbing, electrical, HVAC systems, and communication (data and phone) per the design. The warehouses have electrically operated roll-up doors, with a forklift sized door, and additional fire hydrants as shown in the design. Storm-water drainage features are also included per the design to accommodate the runoff from the new facilities.1. The period of Performance is anticipated to be seven hundred and twenty-three (723) calendar days from Notice to Proceed (NTP) for the entire scope of work.2. The magnitude of the project is between $25 Million and $100 Million. PROPOSAL PROCEDURES: The Request for Proposal (RFP) will be issued on SAM.GOV. It is anticipated that the Best Value Trade-Off (BVTO) contracting method will be used to evaluate proposals. Evaluation criteria will be stated in the RFP. RESPONSE PERIOD: This is a pre-solicitation notice and is not a request for proposal (RFP) nor does it restrict the Government as to the ultimate acquisition approach. A response to this notice is not required. The Government will not reimburse respondents for any costs incurred in preparation of a response to this notice. Questions can be sent to Maria Martin, e-mail: Maria.L.Martin@usace.army.mil and Teliya Stevenson, e-mail: Teliya.J.Stevenson@usace.army.mil.

Update #1 ·

TAM is issuing a solicitation for Design-Bid-Build (DBB) award for the Construction of new pre-engineered metal building system warehouses located at the 35th Armor Brigade Base, Kuwait. PROJECT SCOPE: The scope of the project consists of the construction of five new warehouses to house 44 Abrams M1A2K tanks and 4 M88 recovery vehicles each. These warehouses include the addition of two administrative office areas, two maintenance bays, a 10 ton crane, and storage for tools and spare parts. Optional pavement and parking are included in the scope for this project. The five new warehouses are identical and will house 218 tanks total. Each warehouse is to be constructed for each of the M1A2K Armored Battalions within the 35th Brigade (2nd, 7th, 8th, 9th, 55th Battalions). Each warehouse is approximately 7,800 square meters consisting of open bay storage areas for the M1A2K tanks, maintenance bays with a bridge crane, and mezzanines with admin office areas for the approximate (50) personnel. The sites will include hardstands for tank maneuvering and inspection purposes. Existing utilities will be extended and rerouted as shown in the design drawings to be connected to the new facilities. Each warehouse will include fire suppression, humidity control, plumbing, electrical, HVAC systems, and communication (data and phone) per the design. The warehouses have electrically operated roll-up doors, with a forklift sized door, and additional fire hydrants as shown in the design. Storm-water drainage features are also included per the design to accommodate the runoff from the new facilities.1. The period of Performance is anticipated to be seven hundred and twenty-three (723) calendar days from Notice to Proceed (NTP) for the entire scope of work.2. The magnitude of the project is between $25 Million and $100 Million. PROPOSAL PROCEDURES: The Request for Proposal (RFP) will be issued on SAM.GOV. It is anticipated that the Best Value Trade-Off (BVTO) contracting method will be used to evaluate proposals. Evaluation criteria will be stated in the RFP. RESPONSE PERIOD: This is a pre-solicitation notice and is not a request for proposal (RFP) nor does it restrict the Government as to the ultimate acquisition approach. A response to this notice is not required. The Government will not reimburse respondents for any costs incurred in preparation of a response to this notice. Questions can be sent to Maria Martin, e-mail: Maria.L.Martin@usace.army.mil and Teliya Stevenson, e-mail: Teliya.J.Stevenson@usace.army.mil.

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Construct 35TH brigade multifunctional warehouses Award Award Notice
Construct 35TH brigade multifunctional warehouses This notice · Latest solicitation Solicitation
Sources Sought - W912ER23R0013 Dive Recompression Chamber Pre-Solicitation
PRESOLICITATION NOTICE for W912ER23R0013 CONSTRUCT 35TH BRIGADE MULTIFUNCTIONAL WAREHOUSES Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity