Concrete Saw Cutting at Emsworth Locks and Dams

Award Notice Posted

Solicitation number
W911WN-15-B-0002
Agency
Awarded
to Matcon Diamond Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
W911WN15C0002 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Emsworth Locks and Dams Pittsburgh, Pennsylvania 15202, United States

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

The Emsworth Locks and Dam Concrete Saw Cutting Contract consists of wire saw cutting and core drilling concrete and embedded items for the new maintenance closure system in the upstream and downstream approaches to
the 110-ft x 600-ft primary land lock chamber. The wire sawing will be from the top of the land and middle wall monoliths to the underwater poiree and boule dam sills at the elevations indicated. Portions of this work will occur underwater. Core drilling, wire sawing, line drilling, or other precision cutting methods shall be utilized for the concrete cutting. Steel corner protection and wall armor will also be cut at locations of the proposed concrete wire sawing. The contractor is responsible to cut concrete free as indicated and install a temporary Government supplied stability system. The Government will remove the concrete sections at a later date.

Construction will occur in close proximity to waterway traffic in the land lock chamber. All work shall be performed in a manner that will not interfere with the duties of project personnel or lock operation. Limited, minor lock closures will be accommodated. The lock chambers at Emsworth L/D are currently operated 24 hours a day, 7 days a week.


The source selection process that will be utilized to award this contract will be an Invitation for Bid. All detailed information will be set forth in the solicitation

Update #1 ·

The Emsworth Locks and Dam Concrete Saw Cutting Contract consists of
wire saw cutting and core drilling concrete and embedded items for the new
maintenance closure system in the upstream and downstream approaches to
the 110-ft x 600-ft primary land lock chamber. The wire sawing will be from the
top of the land and middle wall monoliths to the underwater poiree and boule
dam sills at the elevations indicated. Portions of this work will occur
underwater. Core drilling, wire sawing, line drilling, or other precision cutting
methods shall be utilized for the concrete cutting. Steel corner protection and
wall armor will also be cut at locations of the proposed concrete wire sawing.
The contractor is responsible to cut concrete free as indicated and install a
temporary Government supplied stability system. The Government will remove
the concrete sections at a later date.

Files

File Type Posted
BidResults15B0002.pdf PDF