Comprehensive everglades restoration plan, indian river lagoon south C-23/24 stormwater treatment area ST. Lucie county, florida

Closed Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
W912EP21R0022
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Florida, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This notice seeks proposals for construction services related to the Comprehensive Everglades Restoration Plan in Indian River Lagoon South, Florida. The U.S. Army Corps of Engineers Engineering District Jacksonville will evaluate proposals based on technical merit, past performance, small business participation, and price. Proposals are due August 12, 2021 for a performance period of approximately 1,460 calendar days after notice to proceed.

The project has no set-aside designations. The NAICS code is 237990 for other heavy and civil engineering construction with a size standard of $39.5 million. The magnitude of construction is estimated between $100-175 million. Work includes building stormwater treatment areas, perimeter levees, collection channels, and associated structures. Phase 1 requires constructing a 7-foot culvert under the C-24 canal without impeding water flow.

Notice text

4 versions

Update #4 · Latest ·

A Pre-Proposal Conference will be held on Thursday, 29 July 2021 from 10:00am – 11:00am, Local Time via Web-Ex @ https://usace1.webex.com/meet/timothy.g.humphrey or teleconference: Call-in number: 1-844-800-2712 Access code: 199 392 9265 Attendee ID: 475877.  It is requested that an email be sent to Timothy.G.Humphrey@usace.army.mil to confirm attendance by your organization.

DESCRIPTION OF WORK: Project includes a Base and one Option. The base work includes construction of a stormwater treatment area consisting of two contiguous cells (about 410 acres) west of County Road (CR) 613, and three contiguous cells (about 1,560 acres) east of CR 613.  Cells are parallel, flowing west to east, and consist of about 18,400 feet of a perimeter levee and about 3,700 feet of a cell division levee west of CR 613. Said work is also inclusive of about 35,500 feet of a perimeter levee and 2 cell division levees of about 12,200 and 9,500 feet east of CR 613. Collection and distribution channels run along the east and west ends of each cell.

Work includes construction of one 2-barrel ungated culvert structure (8 feet diameter culverts) under CR 613; one 3-barrel gated culvert structure (5 feet diameter culverts) under CR 609; five gated 8 feet by 6 feet box culverts for release into cells; two ungated 5 feet diameter culverts for boundary seepage return; four ungated 3 feet diameter culverts with weirs for runoff relief; two gated 8 feet by 6 feet box culverts for release from cells; six 5 feet diameter culverts with operable weirs for release from cells; and a portion of one 7 feet diameter culvert.

Requisite work includes construction of site access from CR 613 and modification of CR 609 and CR 613 roadway drainage (swales and detention features); however, there is South Florida Water Management District (SFWMD) owned property east of CR 613 and north of the contiguous cells that can be used for staging.

Work is divided into phases as outlined below:

Phase 1

The work associated with Phase 1 includes construction of the S-425 Culvert and project initiation activities.  The work includes all required site demolition to construct S-425 Sag Culvert.  

Phase 2

The work associated with Phase 2 includes construction of the Connection Canal connecting the North St. Lucie River Water Control District (NSLRWCD) C-70 canal to the NSLRWCD C-69 canal.

Phase 3

Phase 3 includes construction of the two contiguous cells (about 410 acres) west of CR 613, referred to as Cells 1 and 2, and includes associated structures: S-431A Ungated Culvert, S-431B Ungated Culvert, S-432A Gated Box Culvert, S-432B Gated Box Culvert, S-433A Gated Box Culvert, S-433B Gated Box Culvert, S-434A Fixed Weir Drop Structure and Culvert, S-434B Fixed Weir Drop Structure and Culvert, and S-451 Ungated Culverts.  The work includes construction of the three contiguous cells (about 1,560 acres) east of CR 613, referred to as Cells 3, 4, and 5, including associated structures: S-435A Fixed Weir Drop Structure and Culvert, S-435B Fixed Weir Drop Structure and Culvert, S-436A Gated Box Culvert, S-436B Gated Box Culvert, S-436C Gated Box Culvert, S-437A Culvert With Operable Weir, S-437B Culvert With Operable Weir, S-438A Culvert With Operable Weir, S-438B Culvert With Operable Weir, S-439A Culvert With Operable Weir, S-439B Culvert With Operable Weir and S-441 Gated Culverts. In addition to the aforementioned work, Phase 3 includes modification of CR 613 and CR 609 roadway drainage.

Option A

The work includes installation of a temporary pump station.  The temporary pump station centerline will be located east of the C-24 canal, approximately 150 feet north of the S-425 Sag Culvert.  The temporary pump station will be turned over to the South Florida Water Management District for operation following construction completion.

PROPOSAL REQUIREMENTS:

Award will be made to the offeror whose proposal represents the best value to the Government. Proposals will be evaluated in the areas of Technical Merit, Past Performance, Small Business Participation and Price. The Request for Proposal (RFP) will be issued on or about 28 June 2021 and proposals will be due on or about 12 August 2021.

The performance period is approximately 1,460 calendar days after Notice to Proceed (NTP).

NAICS Code 237990, Other Heavy and Civil Engineering Construction. Size Standard $39.5 million.

Magnitude of construction is between $100,000,000.00 and $175,000,000.00.

THIS IS AN UNRESTRICTED ACQUISITION.  ALL RESPONSIBLE OFFERORS   ARE ENCOURAGED TO PARTICIPATE.

FAR Clause 52.219-9 Small Business Subcontracting Plan, will be included in the solicitation and resulting contract.

FAR Clause 52.219-4 Notice of Price Evaluation for HUBZone Small Business Concerns, will be included in the solicitation and resulting contract.

Solicitation will be issued in electronic format only and will be posted on the Sam.Gov website at https://sam.gov/.  In order to receive notification of any amendments to this solicitation, interested vendors must REGISTER AS AN INTERESTED VENDOR on the Sam website at https://.sam.gov/.  If you are not registered, the Government is not responsible with providing you with notification of any changes to this solicitation.  You must be registered in the System for Award Management (SAM) in order to be eligible to receive an award from this solicitation.  For additional information, please call 866-606-8220 or visit the SAM website at https://www.sam.gov/.

Update #3 ·

A Pre-Proposal Conference will be held on Wednesday, 28 July 2021 from 10:00am – 11:00am, Local Time via Web-Ex @ https://usace1.webex.com/meet/timothy.g.humphrey or teleconference: Call-in number: 1-844-800-2712 Access code: 199 392 9265 Attendee ID: 475877.  It is requested that an email be sent to Timothy.G.Humphrey@usace.army.mil to confirm attendance by your organization.

DESCRIPTION OF WORK: Project includes a Base and one Option. The base work includes construction of a stormwater treatment area consisting of two contiguous cells (about 410 acres) west of County Road (CR) 613, and three contiguous cells (about 1,560 acres) east of CR 613.  Cells are parallel, flowing west to east, and consist of about 18,400 feet of a perimeter levee and about 3,700 feet of a cell division levee west of CR 613. Said work is also inclusive of about 35,500 feet of a perimeter levee and 2 cell division levees of about 12,200 and 9,500 feet east of CR 613. Collection and distribution channels run along the east and west ends of each cell.

Work includes construction of one 2-barrel ungated culvert structure (8 feet diameter culverts) under CR 613; one 3-barrel gated culvert structure (5 feet diameter culverts) under CR 609; five gated 8 feet by 6 feet box culverts for release into cells; two ungated 5 feet diameter culverts for boundary seepage return; four ungated 3 feet diameter culverts with weirs for runoff relief; two gated 8 feet by 6 feet box culverts for release from cells; six 5 feet diameter culverts with operable weirs for release from cells; and a portion of one 7 feet diameter culvert.

Requisite work includes construction of site access from CR 613 and modification of CR 609 and CR 613 roadway drainage (swales and detention features); however, there is South Florida Water Management District (SFWMD) owned property east of CR 613 and north of the contiguous cells that can be used for staging.

Work is divided into phases as outlined below:

Phase 1

The work associated with Phase 1 includes construction of the S-425 Culvert and project initiation activities.  The work includes all required site demolition to construct S-425 Sag Culvert.  

Phase 2

The work associated with Phase 2 includes construction of the Connection Canal connecting the North St. Lucie River Water Control District (NSLRWCD) C-70 canal to the NSLRWCD C-69 canal.

Phase 3

Phase 3 includes construction of the two contiguous cells (about 410 acres) west of CR 613, referred to as Cells 1 and 2, and includes associated structures: S-431A Ungated Culvert, S-431B Ungated Culvert, S-432A Gated Box Culvert, S-432B Gated Box Culvert, S-433A Gated Box Culvert, S-433B Gated Box Culvert, S-434A Fixed Weir Drop Structure and Culvert, S-434B Fixed Weir Drop Structure and Culvert, and S-451 Ungated Culverts.  The work includes construction of the three contiguous cells (about 1,560 acres) east of CR 613, referred to as Cells 3, 4, and 5, including associated structures: S-435A Fixed Weir Drop Structure and Culvert, S-435B Fixed Weir Drop Structure and Culvert, S-436A Gated Box Culvert, S-436B Gated Box Culvert, S-436C Gated Box Culvert, S-437A Culvert With Operable Weir, S-437B Culvert With Operable Weir, S-438A Culvert With Operable Weir, S-438B Culvert With Operable Weir, S-439A Culvert With Operable Weir, S-439B Culvert With Operable Weir and S-441 Gated Culverts. In addition to the aforementioned work, Phase 3 includes modification of CR 613 and CR 609 roadway drainage.

Option A

The work includes installation of a temporary pump station.  The temporary pump station centerline will be located east of the C-24 canal, approximately 150 feet north of the S-425 Sag Culvert.  The temporary pump station will be turned over to the South Florida Water Management District for operation following construction completion.

PROPOSAL REQUIREMENTS:

Award will be made to the offeror whose proposal represents the best value to the Government. Proposals will be evaluated in the areas of Technical Merit, Past Performance, Small Business Participation and Price. The Request for Proposal (RFP) will be issued on or about 28 June 2021 and proposals will be due on or about 12 August 2021.

The performance period is approximately 1,460 calendar days after Notice to Proceed (NTP).

NAICS Code 237990, Other Heavy and Civil Engineering Construction. Size Standard $39.5 million.

Magnitude of construction is between $100,000,000.00 and $175,000,000.00.

THIS IS AN UNRESTRICTED ACQUISITION.  ALL RESPONSIBLE OFFERORS   ARE ENCOURAGED TO PARTICIPATE.

FAR Clause 52.219-9 Small Business Subcontracting Plan, will be included in the solicitation and resulting contract.

FAR Clause 52.219-4 Notice of Price Evaluation for HUBZone Small Business Concerns, will be included in the solicitation and resulting contract.

Solicitation will be issued in electronic format only and will be posted on the Sam.Gov website at https://sam.gov/.  In order to receive notification of any amendments to this solicitation, interested vendors must REGISTER AS AN INTERESTED VENDOR on the Sam website at https://.sam.gov/.  If you are not registered, the Government is not responsible with providing you with notification of any changes to this solicitation.  You must be registered in the System for Award Management (SAM) in order to be eligible to receive an award from this solicitation.  For additional information, please call 866-606-8220 or visit the SAM website at https://www.sam.gov/.

Update #2 ·

A Pre-Proposal Conference will be held on Wednesday, 14 July 2021 from 10:00am – 11:00am, Local Time via teleconference.  The call-in number is: 1-844-800-2712 Access code: 199 392 9265.  It is requested that an email be sent to Timothy.G.Humphrey@usace.army.mil to confirm attendance by your organization.

DESCRIPTION OF WORK: Project includes a Base and one Option. The base work includes construction of a stormwater treatment area consisting of two contiguous cells (about 410 acres) west of County Road (CR) 613, and three contiguous cells (about 1,560 acres) east of CR 613.  Cells are parallel, flowing west to east, and consist of about 18,400 feet of a perimeter levee and about 3,700 feet of a cell division levee west of CR 613. Said work is also inclusive of about 35,500 feet of a perimeter levee and 2 cell division levees of about 12,200 and 9,500 feet east of CR 613. Collection and distribution channels run along the east and west ends of each cell.

Work includes construction of one 2-barrel ungated culvert structure (8 feet diameter culverts) under CR 613; one 3-barrel gated culvert structure (5 feet diameter culverts) under CR 609; five gated 8 feet by 6 feet box culverts for release into cells; two ungated 5 feet diameter culverts for boundary seepage return; four ungated 3 feet diameter culverts with weirs for runoff relief; two gated 8 feet by 6 feet box culverts for release from cells; six 5 feet diameter culverts with operable weirs for release from cells; and a portion of one 7 feet diameter culvert.

Requisite work includes construction of site access from CR 613 and modification of CR 609 and CR 613 roadway drainage (swales and detention features); however, there is South Florida Water Management District (SFWMD) owned property east of CR 613 and north of the contiguous cells that can be used for staging.

Work is divided into phases as outlined below:

Phase 1

The work associated with Phase 1 includes construction of the S-425 Culvert and project initiation activities.  The work includes all required site demolition to construct S-425 Sag Culvert.  

Phase 2

The work associated with Phase 2 includes construction of the Connection Canal connecting the North St. Lucie River Water Control District (NSLRWCD) C-70 canal to the NSLRWCD C-69 canal.

Phase 3

Phase 3 includes construction of the two contiguous cells (about 410 acres) west of CR 613, referred to as Cells 1 and 2, and includes associated structures: S-431A Ungated Culvert, S-431B Ungated Culvert, S-432A Gated Box Culvert, S-432B Gated Box Culvert, S-433A Gated Box Culvert, S-433B Gated Box Culvert, S-434A Fixed Weir Drop Structure and Culvert, S-434B Fixed Weir Drop Structure and Culvert, and S-451 Ungated Culverts.  The work includes construction of the three contiguous cells (about 1,560 acres) east of CR 613, referred to as Cells 3, 4, and 5, including associated structures: S-435A Fixed Weir Drop Structure and Culvert, S-435B Fixed Weir Drop Structure and Culvert, S-436A Gated Box Culvert, S-436B Gated Box Culvert, S-436C Gated Box Culvert, S-437A Culvert With Operable Weir, S-437B Culvert With Operable Weir, S-438A Culvert With Operable Weir, S-438B Culvert With Operable Weir, S-439A Culvert With Operable Weir, S-439B Culvert With Operable Weir and S-441 Gated Culverts. In addition to the aforementioned work, Phase 3 includes modification of CR 613 and CR 609 roadway drainage.

Option A

The work includes installation of a temporary pump station.  The temporary pump station centerline will be located east of the C-24 canal, approximately 150 feet north of the S-425 Sag Culvert.  The temporary pump station will be turned over to the South Florida Water Management District for operation following construction completion.

PROPOSAL REQUIREMENTS:

Award will be made to the offeror whose proposal represents the best value to the Government. Proposals will be evaluated in the areas of Technical Merit, Past Performance, Small Business Participation and Price. The Request for Proposal (RFP) will be issued on or about 28 June 2021 and proposals will be due on or about 12 August 2021.

The performance period is approximately 1,460 calendar days after Notice to Proceed (NTP).

NAICS Code 237990, Other Heavy and Civil Engineering Construction. Size Standard $39.5 million.

Magnitude of construction is between $100,000,000.00 and $175,000,000.00.

THIS IS AN UNRESTRICTED ACQUISITION.  ALL RESPONSIBLE OFFERORS   ARE ENCOURAGED TO PARTICIPATE.

FAR Clause 52.219-9 Small Business Subcontracting Plan, will be included in the solicitation and resulting contract.

FAR Clause 52.219-4 Notice of Price Evaluation for HUBZone Small Business Concerns, will be included in the solicitation and resulting contract.

Solicitation will be issued in electronic format only and will be posted on the Sam.Gov website at https://sam.gov/.  In order to receive notification of any amendments to this solicitation, interested vendors must REGISTER AS AN INTERESTED VENDOR on the Sam website at https://.sam.gov/.  If you are not registered, the Government is not responsible with providing you with notification of any changes to this solicitation.  You must be registered in the System for Award Management (SAM) in order to be eligible to receive an award from this solicitation.  For additional information, please call 866-606-8220 or visit the SAM website at https://www.sam.gov/.

Update #1 ·

A Pre-Proposal Conference will be held on Wednesday, 14 July 2021 from 10:00am – 11:00am, Local Time via teleconference.  The call-in number is: 1-844-800-2712 Access code: 199 392 9265.  It is requested that an email be sent to Timothy.G.Humphrey@usace.army.mil to confirm attendance by your organization.

DESCRIPTION OF WORK: Project includes a Base and one Option. The base work includes construction of a stormwater treatment area consisting of two contiguous cells (about 410 acres) west of County Road (CR) 613, and three contiguous cells (about 1,560 acres) east of CR 613.  Cells are parallel, flowing west to east, and consist of about 18,400 feet of a perimeter levee and about 3,700 feet of a cell division levee west of CR 613. Said work is also inclusive of about 35,500 feet of a perimeter levee and 2 cell division levees of about 12,200 and 9,500 feet east of CR 613. Collection and distribution channels run along the east and west ends of each cell.

Work includes construction of one 2-barrel ungated culvert structure (8 feet diameter culverts) under CR 613; one 3-barrel gated culvert structure (5 feet diameter culverts) under CR 609; five gated 8 feet by 6 feet box culverts for release into cells; two ungated 5 feet diameter culverts for boundary seepage return; four ungated 3 feet diameter culverts with weirs for runoff relief; two gated 8 feet by 6 feet box culverts for release from cells; six 5 feet diameter culverts with operable weirs for release from cells; and one 7 feet diameter sag culvert under the C-24 canal.

Requisite work includes construction of site access from CR 613 and modification of CR 609 and CR 613 roadway drainage (swales and detention features); however, there is South Florida Water Management District (SFWMD) owned property east of CR 613 and north of the contiguous cells that can be used for staging.

Work is divided into phases as outlined below:

Phase 1

The work associated with Phase 1 includes construction of the S-425 Sag Culvert and project initiation activities.  The work includes all required site demolition to construct S-425 Sag Culvert.  As identified in the plans, a portion of the S-425 Sag Culvert installation must be performed in the wet. This must be completed without plugging the C-24 canal and impeding conveyance.

Phase 2

The work associated with Phase 2 includes construction of the Connection Canal connecting the North St. Lucie River Water Control District (NSLRWCD) C-70 canal to the NSLRWCD C-69 canal.

Phase 3

Phase 3 includes construction of the two contiguous cells (about 410 acres) west of CR 613, referred to as Cells 1 and 2, and includes associated structures: S-431A Ungated Culvert, S-431B Ungated Culvert, S-432A Gated Box Culvert, S-432B Gated Box Culvert, S-433A Gated Box Culvert, S-433B Gated Box Culvert, S-434A Fixed Weir Drop Structure and Culvert, S-434B Fixed Weir Drop Structure and Culvert, and S-451 Ungated Culverts.  The work includes construction of the three contiguous cells (about 1,560 acres) east of CR 613, referred to as Cells 3, 4, and 5, including associated structures: S-435A Fixed Weir Drop Structure and Culvert, S-435B Fixed Weir Drop Structure and Culvert, S-436A Gated Box Culvert, S-436B Gated Box Culvert, S-436C Gated Box Culvert, S-437A Culvert With Operable Weir, S-437B Culvert With Operable Weir, S-438A Culvert With Operable Weir, S-438B Culvert With Operable Weir, S-439A Culvert With Operable Weir, S-439B Culvert With Operable Weir and S-441 Gated Culverts. In addition to the aforementioned work, Phase 3 includes modification of CR 613 and CR 609 roadway drainage.

Option A

The work includes installation of a temporary pump station.  The temporary pump station centerline will be located east of the C-24 canal, approximately 150 feet north of the S-425 Sag Culvert.  The temporary pump station will be turned over to the South Florida Water Management District for operation following construction completion.

PROPOSAL REQUIREMENTS:

Award will be made to the offeror whose proposal represents the best value to the Government. Proposals will be evaluated in the areas of Technical Merit, Past Performance, Small Business Participation and Price. The Request for Proposal (RFP) will be issued on or about 28 June 2021 and proposals will be due on or about 12 August 2021.

The performance period is approximately 1,460 calendar days after Notice to Proceed (NTP).

NAICS Code 237990, Other Heavy and Civil Engineering Construction. Size Standard $39.5 million.

Magnitude of construction is between $100,000,000.00 and $175,000,000.00.

THIS IS AN UNRESTRICTED ACQUISITION.  ALL RESPONSIBLE OFFERORS   ARE ENCOURAGED TO PARTICIPATE.

FAR Clause 52.219-9 Small Business Subcontracting Plan, will be included in the solicitation and resulting contract.

FAR Clause 52.219-4 Notice of Price Evaluation for HUBZone Small Business Concerns, will be included in the solicitation and resulting contract.

Solicitation will be issued in electronic format only and will be posted on the Sam.Gov website at https://sam.gov/.  In order to receive notification of any amendments to this solicitation, interested vendors must REGISTER AS AN INTERESTED VENDOR on the Sam website at https://.sam.gov/.  If you are not registered, the Government is not responsible with providing you with notification of any changes to this solicitation.  You must be registered in the System for Award Management (SAM) in order to be eligible to receive an award from this solicitation.  For additional information, please call 866-606-8220 or visit the SAM website at https://www.sam.gov/.

Notice history

Similar open opportunities

Opportunity Agency Set-aside Responses due
Kissimmee River Restoration (KRR) Project, S-69 Weir Repair Okeechobee, Florida, United States · NAICS 237990 ENDIST Jacksonville No set-aside
St. Lucie South Jetty Repair Industry Day Stuart, Florida, United States · NAICS 237990 ENDIST Jacksonville No set-aside
Timucuan Ecological and Historic Preserve TIMU-335 NAICS 237990 National Office No set-aside
Mill Creek Section 205 Flood Risk Management Improvements Mill Creek Flood Control ChannelWalla Walla, WA 99362Walla Walla County 99362 · NAICS 237990 ENDIST Walla Walla No set-aside
Pass-a-grille-pass, maintenance dredging, pinellas county, florida NAICS 237990 ENDIST Jacksonville Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity