CO FLAP SUM 91(1), Fremont Pass Trail
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 6982AF19B000006
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- White River National Forest Summit County, Colorado 80443, United States
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
Project award 11/13/2019.
Update #2 ·
THIS PROJECT WILL BE ADVERTISED ON A SERVICE DISABLED VETERAN OWNED SMALL BUSINESS BASIS.
Project Details: CO FLAP SUM 91(1)
The project may consist of the following:
The project is located in Summit County, Colorado, near the Copper Mountain Ski Resort. The project is roughly parallel to State Highway 91 between the Copper Mountain Far East Parking Lot (approx. Milepost 21.7) and the Climax Mine Water Treatment Plant access road (approx. Milepost 18.6).
The general scope of improvements is construction of approximately 3.3 miles of a new multi-use trail described as follows:
- Approx. 3.2 miles of 12’ wide asphalt concrete pavement trail
- Approx. 460 feet of 12’ wide timber boardwalk;
- Approx. 260 feet, 12’ wide two-span prefabricated steel pedestrian bridge with simulated stone reinforced concrete abutments and pier.
Proposed new construction work includes linear grading, aggregate base, asphalt concrete pavement, drainage culvert installation, boardwalk, bridgework, pavement markings and signs.
The project is located on United State Forest Service lands within a Special Use Permit to Summit County Open Space and Trails and a portion within a CDOT Highway Easement Deed. The proposed trail alignment lies on top an existing utility corridor that contains natural gas, fiber optic, and electrical facilities that serve regional, statewide, and interstate customers. There are numerous wetlands adjacent to the proposed path, and the boardwalk will traverse a critical wetland restoration site. Environmental restrictions will be in effect. The contractor will need to exercise caution to ensure no unplanned disturbance to these critical facilities and resources. Access to and within the site is very limited, which will constrain the size and type of equipment capable of performing the work.
Schedule A:
|
Line Item |
Unit |
Estimated Quantity |
|
20420-0000 |
Embankment Construction |
17,300 CUYD |
|
30202-2000 |
Method 2 |
8,300 TON |
|
40301-0100 |
Asphalt Concrete Pavement |
3,850 TON |
|
55701-2000 |
Structural Timber and Lumber, Treated |
18 MFBM |
|
58202-0000 |
Helical Pile, In Place |
94 EACH |
|
58405-1000 |
Fiberglass Reinforced Plastic, Grating |
5,520 SQFT |
|
62406-0400 |
Placing Conserved Topsoil, 6-Inch Depth |
2.0 ACRES |
Option X:
|
Line Item |
Unit |
Estimated Quantity |
|
20420-0000 |
Embankment Construction |
900 CUYD |
|
30202-2000 |
Roadway Aggregate, Method 2 |
400 TON |
|
40301-0100 |
Asphalt Concrete Pavement |
200 TON |
|
55201-0200 |
Structural Concrete, Class A (AE) |
129 CUYD |
|
55401-1000 |
Reinforcing Steel |
7,000 LB |
|
55401-2000 |
Reinforcing Steel, Epoxy Coated |
4,200 LB |
|
55504-0000 |
Pre-fabricated Steel Bridge |
ALL LPSM |
|
62406-0400 |
Placing Conserved Topsoil, 6-Inch Depth |
0.1 ACRES |
Estimated total cost is $3 to $5 million.
Construction is anticipated between June 2020 and October 2020.
Anticipated advertisement in September 2019.
Bid opening October 22, 2019.
Anticipated Award in December 2019.
Update #1 ·
THIS PROJECT WILL BE ADVERTISED ON A SERVICE DISABLED VETERAN OWNED SMALL BUSINESS BASIS.
THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
Project Details: CO FLAP SUM 91(1)
The project may consist of the following:
The project is located in Summit County, Colorado, near the Copper Mountain Ski Resort. The project is roughly parallel to State Highway 91 between the Copper Mountain Far East Parking Lot (approx. Milepost 21.7) and the Climax Mine Water Treatment Plant access road (approx. Milepost 18.6).
The general scope of improvements is construction of approximately 3.3 miles of a new multi-use trail described as follows:
- Approx. 3.2 miles of 12’ wide asphalt concrete pavement trail
- Approx. 460 feet of 12’ wide timber boardwalk;
- Approx. 260 feet, 12’ wide two-span prefabricated steel pedestrian bridge with simulated stone reinforced concrete abutments and pier.
Proposed new construction work includes linear grading, aggregate base, asphalt concrete pavement, drainage culvert installation, boardwalk, bridgework, pavement markings and signs.
The project is located on United State Forest Service lands within a Special Use Permit to Summit County Open Space and Trails and a portion within a CDOT Highway Easement Deed. The proposed trail alignment lies on top an existing utility corridor that contains natural gas, fiber optic, and electrical facilities that serve regional, statewide, and interstate customers. There are numerous wetlands adjacent to the proposed path, and the boardwalk will traverse a critical wetland restoration site. Environmental restrictions will be in effect. The contractor will need to exercise caution to ensure no unplanned disturbance to these critical facilities and resources. Access to and within the site is very limited, which will constrain the size and type of equipment capable of performing the work.
Schedule A:
|
Line Item |
Unit |
Estimated Quantity |
|
20420-0000 |
Embankment Construction |
17,300 CUYD |
|
30202-2000 |
Method 2 |
8,300 TON |
|
40301-0100 |
Asphalt Concrete Pavement |
3,850 TON |
|
55701-2000 |
Structural Timber and Lumber, Treated |
18 MFBM |
|
58202-0000 |
Helical Pile, In Place |
94 EACH |
|
58405-1000 |
Fiberglass Reinforced Plastic, Grating |
5,520 SQFT |
|
62406-0400 |
Placing Conserved Topsoil, 6-Inch Depth |
2.0 ACRES |
Option X:
|
Line Item |
Unit |
Estimated Quantity |
|
20420-0000 |
Embankment Construction |
900 CUYD |
|
30202-2000 |
Roadway Aggregate, Method 2 |
400 TON |
|
40301-0100 |
Asphalt Concrete Pavement |
200 TON |
|
55201-0200 |
Structural Concrete, Class A (AE) |
129 CUYD |
|
55401-1000 |
Reinforcing Steel |
7,000 LB |
|
55401-2000 |
Reinforcing Steel, Epoxy Coated |
4,200 LB |
|
55504-0000 |
Pre-fabricated Steel Bridge |
ALL LPSM |
|
62406-0400 |
Placing Conserved Topsoil, 6-Inch Depth |
0.1 ACRES |
Estimated total cost is $3 to $5 million.
Construction is anticipated between June 2020 and October 2020.
Anticipated advertisement in September 2019.
Anticipated bid opening in October 2019.
Anticipated Award in December 2019.
Files
| File | Type | Posted |
|---|---|---|
| Bid_Tabulation.pdf | ||
| Bid_Opening_Summary_.pdf | ||
| QnA_10.18.19.pdf | ||
| A003_-_Plan_Sheet_B5.pdf | ||
| QnA_10.16.2019_.pdf | ||
| QnA_10.15.2019__.pdf | ||
| Amendment_002.pdf | ||
| QnA_10.10.19.pdf | ||
| QnA_10.7.19.pdf | ||
| QnA_10.4.19.pdf | ||
| QnA_10.3.19.pdf | ||
| Amendment_A001_.pdf | ||
| QnA_9.30.2019.pdf | ||
| QnA_09.23.19.pdf | ||
| CO_FLAP_SUM91(1)_XS_-_Final.pdf | ||
| Final_Geotechnical_Report.pdf | ||
| CO_FLAP_SUM_91(1)_Fremont_Trail_-_Final_Pavement_Tech_Memo.pdf | ||
| SUM91-1-Final_Hydraulics.pdf | ||
| 6982AF19B000006.pdf | ||
| CO_FLAP_SUM91(1)_Plans_-_Final.pdf |
Show all 20
Notice history
| Notice | Type | Posted |
|---|---|---|
| CO FLAP SUM 91(1), Fremont Pass Trail | Award Notice | |