QnA_10.7.19.pdf

PDF 330 KB Posted

Attached to
CO FLAP SUM 91(1), Fremont Pass Trail
Solicitation number
6982AF19B000006
Issued by

View the file

Other files

File Type Posted
Bid_Tabulation.pdf PDF
Bid_Opening_Summary_.pdf PDF
QnA_10.18.19.pdf PDF
A003_-_Plan_Sheet_B5.pdf PDF
QnA_10.16.2019_.pdf PDF
QnA_10.15.2019__.pdf PDF
Amendment_002.pdf PDF
QnA_10.10.19.pdf PDF
QnA_10.4.19.pdf PDF
QnA_10.3.19.pdf PDF
Amendment_A001_.pdf PDF
QnA_9.30.2019.pdf PDF
QnA_09.23.19.pdf PDF
SUM91-1-Final_Hydraulics.pdf PDF
CO_FLAP_SUM_91(1)_Fremont_Trail_-_Final_Pavement_Tech_Memo.pdf PDF
6982AF19B000006.pdf PDF
CO_FLAP_SUM91(1)_Plans_-_Final.pdf PDF
CO_FLAP_SUM91(1)_XS_-_Final.pdf PDF
Final_Geotechnical_Report.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for CO FLAP SUM 91(1) Fremont Pass Trail

October 7, 2019

Questions Answers 1 Bore Hole BH-04 is shown at the south end of the proposed boardwalk. When this bore hole was augered the auger met refusal 3 times at 4 – 10 feet deep in this area. Since the helical piles are to have a 9ft minimum embed, pre-drilling will be required in this area. Is that what was contemplated? If it is, how much of the boardwalk will require pre-drilling for helicals? Two independent engineers have confirmed this soils condition.

The geotechnical report incorrectly presents the station for boring BH-04 as 47+75. The correct station is 49+10. As described in the geotechnical report, it is likely that refusal will be encountered at some helical pile locations. No estimate of the number of piles that will encounter refusal has been developed