Carlyle Water Line and Hydrant Installation
Closed Solicitation Posted
- Solicitation number
- W912P922Q0008
- Agency
- ENDIST St Louis US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Place of performance
- Carlyle, Illinois 62231, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Contractor shall supply all equipment, labor, and materials used for the installation of new water lines in Dam East Recreation Area. The contractor shall trench, install & backfill approximately 2150 linear feet of 3” SDR21 pipe, 150 linear feet of 1” HDPE pipe, 2 3” MJ Gate Valves, 2 valve boxes, 11 1” CTS curb stops, 11 curb boxes, and 11 Woodford S3-2 yard hydrants. The contractor shall tap into existing 1½” water line using a saddle & corp and connect all water lines to hydrants and valves as needed. A curb box shall be placed over the new CTS valves and a valve box shall be placed over the new MJ gate valves to provide access to all valves. When complete, the access holes will allow a water wrench to be used to turn the valves on and off. After all lines, valves, and
hydrants have been installed, the contractor shall pressure test the complete system to ensure no leaks. All waterlines
will be laid with detection wire and “caution water line” locating tape. The waterline trench will have water line
locating tape located approximating 18” below finished grade. All installations and connections of the water line and
hydrants shall be in accordance with State and local plumbing codes by an IL licensed plumber. Water line field
locations will be field located by the Government. All materials for water line installation and associated
connections shall be furnished by the contractor. Installation shall be all inclusive to include all cost for parts, pipe,
hydrants, materials, trenching, backfill, marking tape, detection wire, labor, supervision, equipment, testing, and
incidentals required to install water lines per linear foot. Installation of new water lines will require contractor to
trench through two roadways. The contractor is responsible for backfilling and repairing roadways with asphalt
material after completion of installation. The contractor is responsible for locating any and all public, private and/or
Government owned utilities prior to commencing work. Any damage to any utilities caused by the Contractor’s
operations shall be replaced by the contractor at no expense to the Government.
Remit questions to Elena.C.Coleman@USACE.ARMY.MIL
Site visit is scheduled April 19th at 9:00 a.m. 801 Lake Carlyle, IL 62231. POC is Jody Harris.
Questions deadline is 4/20/22 at10:00 a.m. Central.
Update #1 ·
Contractor shall supply all equipment, labor, and materials used for the installation of new water lines in Dam East Recreation Area. The contractor shall trench, install & backfill approximately 2150 linear feet of 3” SDR21 pipe, 150 linear feet of 1” HDPE pipe, 2 3” MJ Gate Valves, 2 valve boxes, 11 1” CTS curb stops, 11 curb boxes, and 11 Woodford S3-2 yard hydrants. The contractor shall tap into existing 1½” water line using a saddle & corp and connect all water lines to hydrants and valves as needed. A curb box shall be placed over the new CTS valves and a valve box shall be placed over the new MJ gate valves to provide access to all valves. When complete, the access holes will allow a water wrench to be used to turn the valves on and off. After all lines, valves, and
hydrants have been installed, the contractor shall pressure test the complete system to ensure no leaks. All waterlines
will be laid with detection wire and “caution water line” locating tape. The waterline trench will have water line
locating tape located approximating 18” below finished grade. All installations and connections of the water line and
hydrants shall be in accordance with State and local plumbing codes by an IL licensed plumber. Water line field
locations will be field located by the Government. All materials for water line installation and associated
connections shall be furnished by the contractor. Installation shall be all inclusive to include all cost for parts, pipe,
hydrants, materials, trenching, backfill, marking tape, detection wire, labor, supervision, equipment, testing, and
incidentals required to install water lines per linear foot. Installation of new water lines will require contractor to
trench through two roadways. The contractor is responsible for backfilling and repairing roadways with asphalt
material after completion of installation. The contractor is responsible for locating any and all public, private and/or
Government owned utilities prior to commencing work. Any damage to any utilities caused by the Contractor’s
operations shall be replaced by the contractor at no expense to the Government.
Remit questions to Elena.C.Coleman@USACE.ARMY.MIL
Questions deadline is 4/20/22 at10:00 a.m. Central.
Attachments
| File | Type | Posted |
|---|---|---|
| A11_Combined Synopsis Solicitation -.pdf | ||
| A22_Past Performance Questionnaire.pdf |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity