About this opportunity

This Award Notice from the Department of the Army Corps of Engineers Engineering District Albuquerque awarded a contract to ORCOM, A Division of Ortega Companies, Inc. for $248,932.53 to complete repairs and renovations to Building 497 at Kirtland Air Force Base. Under the terms of the 8(a) sole source set-aside contract, the contractor will demolish and remove existing structures, materials, and equipment before providing and installing new flooring, walls, doors, lighting, furniture, and HVAC systems as outlined in the drawings and specifications.

Notice text

This action was awarded as an 8(a) Sole Source Set-Aside under the authority of section 8(a) of the Small Business Act.

The contractor shall furnish all parts, material, labor, equipment and supervision necessary to complete the work for Building 497 Repair RDM Front Office.

  1. Demolition
  1. Contractor shall remove existing doors, frames and hardware, as indicated on drawings.
  2. Contractor shall remove existing flooring and rubber wall base, as indicated on drawings.
  3. Contractor must abate asbestos as required.
  4. Contractor shall remove existing walls, as indicated on drawings.
  5. Contractor shall remove existing comm and power, as indicated on drawings.
  6. Contractor shall remove existing furniture and salvage for reinstallation, as indicated on drawings.
  7. Contractor shall remove lighting as indicated on drawings.
  8. Contractor shall remove existing ceiling tiles as indicated on drawings.
  9. Contractor must remove existing HVAC diffusers and return air grills as indicated on drawings.
  10. Contractor shall remove existing wall heaters, as indicated on drawings.
  1. Construction
  1. Contractor shall provide and install new carpet tile and rubber wall base, as indicated on drawings.
  2. Contractor shall provide and install new floor transition strip, as indicated on drawings.
  3. Contractor shall provide and install new power and comm, as indicated on drawings.
  4. Contractor shall provide and install new doors, frames and hardware, as indicated on drawings.
  5. Contractor shall provide and install new signage, as indicated on drawings.
  6. Contractor shall construct new walls, as indicated on drawings.
  7. Contractor shall provide and install new ceiling grid and tiles, as indicated on drawings.
  8. Contractor shall provide and install new ceiling tile, as indicated on drawings.
  9. Contractor shall provide and install new LED lighting, as indicated on drawings.
  10. Contractor shall provide and install new light switch, as indicated on drawings.
  11. Contractor shall provide and install new furniture, as indicated on drawings.
  12. Contractor must clean and paint window frames as indicated on drawings.
  13. Contractor must provide and install HVAC duct extensions, diffusers and return air grills as indicated on drawings.

Awarded contract W912PP20P0060 to ORCOM, A DIVISION OF ORTEGA COMPANIES, INC. for 248932.53 on 2020-09-28.