Building 497 Repair 497 RDF Offices, Kirtland Air Force Base (KAFB), Bernalillo County, New Mexico
Award Notice Posted
- Solicitation number
- W912PP-15-T-0141
- Agency
-
ENDIST Albuquerque
US Army Corps of Engineers, Department of Defense
- Awarded
- to Grancor Enterprises, Inc.
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W912PP-15-P-0105 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Not on record
- More information
Notice details come from SAM.gov. Updated .
Notice text
This contract action was accomplished using other than competitive procedures because a statute exists that expressly authorizes or requires that the acquisition be made from a specific source or through another agency (FAR 6.302-5); specifically, Sole source awards under the 8(a) Program. Per FAR 6.302-5 a J&A is not required for this award.
Demolition
1. Contractor shall remove door, frame, and hardware as indicated on drawings.
2. Contractor shall remove existing flooring and wall base as indicated on drawings.
3. Contractor shall remove existing walls as indicated on drawings.
4. Contractor shall remove existing sound soak as indicated on drawings.
5. Contractor shall remove existing projector controls as indicated on drawings.
6. Contractor shall remove existing radiant wall heater as indicated on drawings.
7. Contractor shall remove existing electrical and comm. as indicated on drawings.
8. Contractor shall remove existing projector and assembly as indicated on drawings.
9. Contractor shall remove existing light switch, ceiling grid, ceiling tiles, and
HVAC diffusers as indicated on drawings.
10. Contractor shall remove existing thermostat as indicated on drawings.
11. Contractor shall remove and relocate existing sprinklers as indicated on drawings.
12. Contractor shall remove existing ceiling fans as indicated in drawings.
Construction
1. Contractor shall provide and install new finished opening as indicated on drawings.
2. Contractor shall provide and install new floor transition strip as indicated on
drawings.
3. Contractor shall paint new walls as indicated on drawings.
4. Contractor shall provide and install new flooring as indicated on drawings.
5. Contractor shall provide and install new rubber wall base as indicated on drawings.
6. Contractor shall provide and install new walls as indicated on drawings.
7. Contractor shall provide and install new room signs as indicated on drawings.
8. Contractor shall provide and install new duplex receptacles as indicated on drawings.
9. Contractor shall provide and install new aluminum store front systems as indicated on drawings.
10. Contractor shall provide and install new phone and network lines as indicated
on drawings.
11. Contractor shall provide and install new doors as indicated on drawings.
12. Contractor shall provide and install new carpet tiles as indicated on drawings.
13. Contractor shall paint all existing window trim as indicated on drawings.
14. Contractor shall provide and install new light switch as indicated on
drawings.
15. Contractor shall provide and install new light fixtures as indicated on
drawings.
16. Contractor shall provide and install new ceiling grid and tiles as indicated on
drawings.
17. Contractor shall provide and install new plenum return grills as indicated on
drawings.
18. Contractor shall provide and install new hard-lid-ceiling as indicated on
drawings.
19. Contractor shall install salvaged thermostat as indicated on drawings.
20. Contractor shall install new light switch and tie into existing light circuit as
indicated on drawings.
21. Contractor shall skim coat wall and paint as indicated on drawings.