Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture

Closed Solicitation Posted

Solicitation number
N4523A23Q5721
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
332999 All Other Miscellaneous Fabricated Metal Product Manufacturing
PSC
J028 Maint/Repair/Rebuild Of Equipment- Engines, Turbines, And Components

Notice details come from SAM.gov. Updated .

Notice text

9 versions

Update #9 · Latest ·

June 21 2023:

Solicitation resposted until June 23, 2023 until 2PM PT.  No offers were received during last posting.

June 13 2023:

Solicitation is reposted to revise the PWS to add repair of Hansen Gearbox and shaft.  CLIN 0002 is revised  to add the requirement for the repair of a Hansen Gearbox and shaft. GFP Attachmnet is revised to add Hansen Gearbox.

May 25 2023:

RFQ extended to 5/26/23 at 2pm PT. PWS revised changing Period of Performance from 16 weeks to 18 weeks.

May 10 2023 Questions and answers:

See C09.0 10 May 2023 Questions and Answers in the attachments.

May 09 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised. SeeTechnical Exhibit 2 Condition Found Report.  CLIN 0002 Added. See revised solictation attachment C09.0 N4523A23Q5721 5.9.23

Questions and Answers
1.  Question 1: There is still nothing in the contract allowing to quote the bearings and seals 
after the evaluation of the disassembled gearbox.

Answer: RFQ amendment has included CLIN 0002 for additional repairs found not contained within the 
original PWS.

2. The schedule is requiring a condition report within 5 days of receiving the gearbox. This is not 
possible.

Answer: The PWS has been amended from 5 days to 14 days of gearbox receipt at contractor
facility.  See PWS Technical Exhibit 2 Condition Found Report. 

May 01 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised.  See revised solictation attachment C09.0 N4523A23Q5721 5.1.23

April 18 2023:

Solicitation is extended until 25 April 2023 at 2:00PM PT.

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #8 ·

June 13 2023:

Solicitation is reposted to revise the PWS to add repair of Hansen Gearbox and shaft.  CLIN 0002 is revised  to add the requirement for the repair of a Hansen Gearbox and shaft. GFP Attachmnet is revised to add Hansen Gearbox.

May 25 2023:

RFQ extended to 5/26/23 at 2pm PT. PWS revised changing Period of Performance from 16 weeks to 18 weeks.

May 10 2023 Questions and answers:

See C09.0 10 May 2023 Questions and Answers in the attachments.

May 09 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised. SeeTechnical Exhibit 2 Condition Found Report.  CLIN 0002 Added. See revised solictation attachment C09.0 N4523A23Q5721 5.9.23

Questions and Answers
1.  Question 1: There is still nothing in the contract allowing to quote the bearings and seals 
after the evaluation of the disassembled gearbox.

Answer: RFQ amendment has included CLIN 0002 for additional repairs found not contained within the 
original PWS.

2. The schedule is requiring a condition report within 5 days of receiving the gearbox. This is not 
possible.

Answer: The PWS has been amended from 5 days to 14 days of gearbox receipt at contractor
facility.  See PWS Technical Exhibit 2 Condition Found Report. 

May 01 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised.  See revised solictation attachment C09.0 N4523A23Q5721 5.1.23

April 18 2023:

Solicitation is extended until 25 April 2023 at 2:00PM PT.

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #7 ·

May 25 2023:

RFQ extended to 5/26/23 at 2pm PT. PWS revised changing Period of Performance from 16 weeks to 18 weeks.

May 10 2023 Questions and answers:

See C09.0 10 May 2023 Questions and Answers in the attachments.

May 09 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised. SeeTechnical Exhibit 2 Condition Found Report.  CLIN 0002 Added. See revised solictation attachment C09.0 N4523A23Q5721 5.9.23

Questions and Answers
1.  Question 1: There is still nothing in the contract allowing to quote the bearings and seals 
after the evaluation of the disassembled gearbox.

Answer: RFQ amendment has included CLIN 0002 for additional repairs found not contained within the 
original PWS.

2. The schedule is requiring a condition report within 5 days of receiving the gearbox. This is not 
possible.

Answer: The PWS has been amended from 5 days to 14 days of gearbox receipt at contractor
facility.  See PWS Technical Exhibit 2 Condition Found Report. 

May 01 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised.  See revised solictation attachment C09.0 N4523A23Q5721 5.1.23

April 18 2023:

Solicitation is extended until 25 April 2023 at 2:00PM PT.

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #6 ·

May 10 2023 Questions and answers:

See C09.0 10 May 2023 Questions and Answers in the attachments.

May 09 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised. SeeTechnical Exhibit 2 Condition Found Report.  CLIN 0002 Added. See revised solictation attachment C09.0 N4523A23Q5721 5.9.23

Questions and Answers
1.  Question 1: There is still nothing in the contract allowing to quote the bearings and seals 
after the evaluation of the disassembled gearbox.

Answer: RFQ amendment has included CLIN 0002 for additional repairs found not contained within the 
original PWS.

2. The schedule is requiring a condition report within 5 days of receiving the gearbox. This is not 
possible.

Answer: The PWS has been amended from 5 days to 14 days of gearbox receipt at contractor
facility.  See PWS Technical Exhibit 2 Condition Found Report. 

May 01 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised.  See revised solictation attachment C09.0 N4523A23Q5721 5.1.23

April 18 2023:

Solicitation is extended until 25 April 2023 at 2:00PM PT.

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #5 ·

May 09 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised. SeeTechnical Exhibit 2 Condition Found Report.  CLIN 0002 Added. See revised solictation attachment C09.0 N4523A23Q5721 5.9.23

Questions and Answers
1.  Question 1: There is still nothing in the contract allowing to quote the bearings and seals 
after the evaluation of the disassembled gearbox.

Answer: RFQ amendment has included CLIN 0002 for additional repairs found not contained within the 
original PWS.

2. The schedule is requiring a condition report within 5 days of receiving the gearbox. This is not 
possible.

Answer: The PWS has been amended from 5 days to 14 days of gearbox receipt at contractor
facility.  See PWS Technical Exhibit 2 Condition Found Report. 

May 01 2023:

Combined Synopsis and solicitation reposted as full and open.  The PWS is revised.  See revised solictation attachment C09.0 N4523A23Q5721 5.1.23

April 18 2023:

Solicitation is extended until 25 April 2023 at 2:00PM PT.

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #4 ·

May 01 2023:

Solicitation reposted as full and open.  The PWS is revised.  See revised solictation attachment C09.0 N4523A23Q5721 5.1.23

April 18 2023:

Solicitation is extended until 25 April 2023 at 2:00PM PT.

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #3 ·

April 18 2023:

Solicitation is extended until 25 April 2023 at 2:00PM PT.

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #2 ·

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

03 April 2023 Question and Answer

Question 1:  What is the shipping address?

Answer 1:  1400 Farragut AVE, Bldg. 455 door 10, Bremerton WA 98314

Update #1 ·

Browning Gearbox OTN 2703S1V33CAP and Shaft Remanufacture.

Files

Show all 11

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors