Brookville Left Bypass Gate Valve Replacement
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912QR24Q0062
- Agency
- ENDIST Louisville US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- PSC
- N048 Installation Of Equipment- Valves
- Place of performance
- Brookville, Indiana 47012, United States
- Points of contact
-
- Matthew P Judd matthew.p.judd@usace.army.mil (502) 315-7425
- Justin Mcpherson justin.m.mcpherson@usace.army.mil (502) 315-7057
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Corps of Engineers Engineering District Louisville is seeking to procure the removal of an existing bypass valve and the purchase and installation of a new 30-inch bypass valve at Brookville Lake in Brookville, Indiana. The contractor shall provide all personnel, equipment, supplies, and materials necessary, with pricing to include mobilization, fuel, labor, and equipment. The new bypass valve must meet specified technical requirements and be approved by the Technical Point of Contact prior to purchase. Quotes are due by June 4, 2024 at 12:00 PM Eastern Time, and the work must be completed within 365 calendar days after the Notice to Proceed.
This solicitation is set aside 100% for small businesses, with an estimated construction cost between $100,000 and $250,000. Payment will be made by Electronic Funds Transfer (EFT), and all contractors must be registered in the System for Award Management prior to award. The government has provided information regarding the U.S. Army Corps of Engineers process for settling requests for equitable adjustments and duration goals to achieve definitization of equitable adjustments for change orders under construction contracts.
Notice text
The scope of work the removal of the existing Delta bypass valve, purchase, and installation of a new bypass valve. The contractor shall furnish all personnel, equipment, supplies and materials necessary. Prices should include mobilization & de-mobilization, fuel, labor, material, and equipment.
Note: Lead time for this bypass valve is expected to be 36 weeks after order acknowledgement. The contractor shall not start construction until new bypass valve and all necessary personnel, equipment, supplies, and materials are onsite and ready for assembly. The contractor shall be required to submit supplied valve to Technical Point of Contact (TPOC) listed below for review prior to purchase. If not reviewed before purchase, the contractor may be financially responsible for valve without repayment by the Government.
****************************
Information regarding the U.S. Army Corps of Engineers process for settling requests for equitable adjustments and duration goals to achieve definitization of equitable adjustments for change orders under construction contracts can be found by going to https://www.usace.army.mil/Business-With-Us/Partnering/ then clicking on “View FFP Contract Changes Playbook Here”.
Attachments
| File | Type | Posted |
|---|---|---|
| W912QR24Q0062.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Brookville Left Bypass Gate Valve Replacement | Award Notice | |
| Brookville Left Bypass Gate Valve Replacement | Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity