About this opportunity

The U.S. Army Corps of Engineers, Rock Island District, has issued a Special Notice announcing an Industry Day for the Brandon Road Interbasin Project on April 7, 2026. This special notice invites contractors to participate in an informational session from 8:30 a.m. to 12:00 p.m. at the Davenport River Center in Davenport, Iowa. The Brandon Road Interbasin Project is a critical infrastructure initiative designed to prevent invasive species, particularly invasive carp, from entering the Great Lakes through a series of electric, hydroacoustic, and bubble deterrent systems. The project will be executed in three construction increments, with the Industry Day focusing specifically on Increment II, which encompasses Flushing Lock and Right Descending Bank construction. This special notice provides potential contractors with advance notice of upcoming contract opportunities and an avenue to engage with the government agency prior to formal solicitation.

The primary purpose of this Industry Day is to inform contractors about the significant infrastructure project and solicit feedback on design improvements that could enhance construction efficiency and cost-effectiveness. Interested contractors must register by April 7, 2026, using the online registration link provided (https://forms.osi.apps.mil/r/EGBRszaBQX). There are no specific eligibility restrictions mentioned in the notice, suggesting that contractors in heavy and civil engineering construction are welcome to attend. The notice includes draft plan sets for both the Flushing Lock and Right Descending Bank Wall components, which will be presented during the session to provide contractors with detailed technical information about the scope of work. By attending, contractors will gain insights into the project requirements and have the opportunity to provide input that may influence the final contract specifications for Increment II.

Notice text

The U.S. Army Corps of Engineers, Rock Island District invites you to an Industry Day on Tuesday 7 April 2026 from 8:30am – 12:00pm for the Brandon Road Interbasin Project.

Agenda
8:30 - 9:00 a.m.    Check-In
9:30 - 11:30 a.m.  Presentation and Question and Answer Session

Location: 
Davenport River Center - Arkansas Room
136 E 3rd St
Davenport, Iowa 52801

**Please see the following link for registration for the Brandon Road Interbasin Project Industry Day.**

https://forms.osi.apps.mil/r/EGBRszaBQX


This is your opportunity to learn about this significant infrastructure project and how your company can be a part of it.

Project Overview:

The Brandon Road Interbasin Project is a critical control point in preventing Invasive Species, including Invasive Carp fish, from becoming established in the Great Lakes. This project will construct a series of deterrent measures in the lock chamber and approach channel. Once complete, a series of electric, hydroacoustic, and bubble deterrents will be operational while facilitating river navigation traffic. The project is broken into 3 construction increments (shown below). This presentation will focus on Increment II – Flushing Lock and Right Descending Bank Construction Contract. The purpose of this engagement is to provide contractors awareness of the upcoming contract and also to solicit feedback during this presentation regarding ways to improve the design to allow for more efficient and cost-effective construction.


The project is designed in 3 construction increments, as follows:

Increment I - Leading Edge

  • Automated Barge Clearing (ABC) Deterrent
  • Bubble Curtain Deterrent
  • Acoustic Deterrent (Leading Edge)
  • Leading Edge Support Facilities
  • Upstream Boat Ramp
  • Channel Rock Excavation

Increment II – Flushing Lock and Right Descending Bank

  • Flushing Lock (FL)
  • Right Descending Bank (RDB) Wall
  • Channel Rock Excavation

Increment III - Engineered Channel

  • Electric Deterrent
  • Acoustic Deterrent (Eng Channel)
  • Support Facilities Building
  • Engineered Channel Floor & Walls
  • Downstream Boat Ramp


Industry Day Highlights:

  • Attend the presentation with detailed information about the project scope, timeline, and specific requirements for each phase.
  • Get your questions answered by USACE representatives and project engineers during Q&A.
  • Provide feedback on how to improve design to allow for more efficient and cost-effective construction.
  • Network with potential prime contractors, subcontractors, and suppliers to explore partnerships and innovative solutions.

Presentation will include:

  • Project Background
  • Construction Phasing and Sequencing
  • Status of Increment II Design
  • Details of Increment II Design
  • Industry Questions

**Draft Plan Sets for the Flushing Lock and RDB Wall are attached below in the Attachments/Links section**

Files

Similar open opportunities

Opportunity Agency Set-aside Responses due
Mississippi River Basin Bettendorf, Iowa Local Flood Protection Bettendorf, Iowa 2024 Event PL84-99 Flood Repairs Bettendorf, Iowa 52722, United States · NAICS 237990 ENDIST Rock Island Service-Disabled Veteran-Owned Small Business
Winfield Locks and Dam Major Rehab Industry Day Red House, West Virginia 25168, United States ENDIST Huntington No set-aside
Illinois River Basin, Brandon Road L and D, Joliet, Illinois, Flushing Lock and Dam Gates Fabrication NAICS 326199 ENDIST Rock Island Total Small Business
Sources Sought/Request for Information Upper Mississippi River Restoration (UMRR) – Quincy Bay Habitat Rehabilitation and Enhancement Project- Stage 1 Quincy, Illinois 62301, United States · NAICS 237990 ENDIST Rock Island No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity