Bonneville Concrete Fish Ladder Rebuild (FY 2019 Fish Accords-Lamprey Passage)
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W9127N24R0003
- Agency
-
ENDIST Portland
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z2KA Repair Or Alteration Of Dams
- Place of performance
- North Bonneville, Washington 98639, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Corps of Engineers Engineering District Portland is seeking proposals for the Bonneville Concrete Fish Ladder Rebuild (FY 2019 Fish Accords-Lamprey Passage) project. The project involves demolishing and rebuilding concrete structures, installing custom metal fabrication, and designing and installing a fiberglass walkway at the Bonneville Lock and Dam in North Bonneville, Washington. Proposals will be evaluated based on past performance and the offeror's work plan, with the technical approach being significantly more important than price. Proposals are due by July 1, 2024.
This is a 100% small business set-aside procurement with a NAICS code of 237990 (Other Heavy and Civil Engineering Construction) and an estimated magnitude between $1M and $5M. No potential incumbents or current contractors are named. The place of performance is North Bonneville, Washington 98639, USA. Key requirements include working in confined spaces, meeting schedule constraints for winter conditions and limited in-water work windows, and adhering to Davis-Bacon wage rates.
Notice text
7 versions
Update #7 · Latest ·
25 June 2024: Amendment 5 issued.
14 June 2024: Amendment 4 issued.
14 June 2024: Amendment 3 issued.
07 June 2024: Amendment 2 issued.
07 June 2024: Site visit attendance sheet attached.
29 May 2024: Amendment 1 issued.
23 May 2024: Request for Proposals (RFP) with specifications, drawings and reference drawings posted.
Update #6 ·
14 June 2024: Amendment 4 issued.
14 June 2024: Amendment 3 issued.
07 June 2024: Amendment 2 issued.
07 June 2024: Site visit attendance sheet attached.
29 May 2024: Amendment 1 issued.
23 May 2024: Request for Proposals (RFP) with specifications, drawings and reference drawings posted.
Update #5 ·
14 June 2024: Amendment 3 issued.
07 June 2024: Amendment 2 issued.
07 June 2024: Site visit attendance sheet attached.
29 May 2024: Amendment 1 issued.
23 May 2024: Request for Proposals (RFP) with specifications, drawings and reference drawings posted.
Update #4 ·
07 June 2024: Amendment 2 issued.
07 June 2024: Site visit attendance sheet attached.
29 May 2024: Amendment 1 issued.
23 May 2024: Request for Proposals (RFP) with specifications, drawings and reference drawings posted.
Update #3 ·
07 June 2024: Site visit attendance sheet attached.
29 May 2024: Amendment 1 issued.
23 May 2024: Request for Proposals (RFP) with specifications, drawings and reference drawings posted.
Update #2 ·
29 May 2024: Amendment 1 issued.
23 May 2024: Request for Proposals (RFP) with specifications, drawings and reference drawings posted.
Update #1 ·
23 May 2024: Request for Proposals (RFP) with specifications, drawings and reference drawings posted.
Files
Show all 17
Notice history
| Notice | Type | Posted |
|---|---|---|
| Bonneville Concrete Fish Ladder Rebuild (FY 2019 Fish Accords-Lamprey Passage) | Award Notice | |
| This notice | Solicitation | |
| Bonneville Concrete Fish Ladder Rebuild (FY 2019 Fish Accords-Lamprey Passage) | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Bonneville Powerhouse II Unwatering Pump Replacement | ENDIST Portland | Total Small Business | |
| LLA Navigation Lock Switchgear | ENDIST Walla Walla | Total Small Business | |
| John day DAM navigation lock tainter valve (TV) repairs TV3 and TV4 | ENDIST Portland | No set-aside | |
| FY27 Euclid Creek Fishway Construction | ENDIST Buffalo | Total Small Business | |
| John day DAM unit 10 packing box replacement | ENDIST Portland | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity