BIE/nmnn/FM/add handrails/ladder water tower for B
Award Notice Posted
- Solicitation number
- 140A0918R0010
- Agency
-
Central Office
Bureau of Indian Affairs and Indian Education, Department of the Interior
- Awarded
- to Hodishooh Specialty Maintenance, Inc.
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- 140A0918P0081 Federal contract award
- NAICS code
- 238190 Other Foundation, Structure, and Building Exterior Contractors
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
6 versions
Update #6 · Latest ·
BIE/NMNN/FM/ADD HANDRAILS/LADDER WATER TOWER FOR BIE-SANOSTEE DAY SCHOOL
Update #5 ·
Amendment Four (04)done to Request for Proposal No. 140A0918R0010 as follows:
1. To extend the Proposal due date to Thursday, January 25, 2018 at 5:00 p.m. and will not be extended.
2. To attached pictures and revised SOW.
ALL OTHER TERMS AND CONDITIONS ARE TO REMAINS THE SAME IN FULL FORCE AND EFFECT..
Update #4 ·
Amendment Three (03)done to Request for Proposal No. 140A0918R0010 as follows:
1. To extend the Proposal due date to Friday, January 19, 2018 at 5:00 p.m. and will not be extended.
2. NO more questions to be asked.
3. To answer Questions asked and the Governments Response:
1. Questioned Asked: Are there any drawings and specifications for the work requested?
Governments Response: NO
2. Questioned Asked: Are there any associated pictures available?
Governments Response: WILL PROVIDE.
3. Questioned Asked: Will the tank need to be drained? If so by whom?
Governments Response: YES BY BIE PERSONAL.
4. Questioned Asked: Will the interior require recoating after welding?
Governments Response: YES
5. Questioned Asked: What are the existing coatings interior/exterior?
Governments Response: ALL WE HAVE IS EXTERIOR SHERWIN WILLIAMS PALLET TAN SW4003.
6. Questioned Asked: Will potability tests be required.
Governments Response: YES
7. Questioned Asked: Will there be an extension for response/bid due date?
Governments Response: IF NEEDED WOULD LIKE WORK TO BE DONE DURING BREAK IF POSSIBLE TO DRAINING OF TANK.
ALL OTHER TERMS AND CONDITIONS ARE TO REMAINS THE SAME IN FULL FORCE AND EFFECT..
Update #3 ·
Amendment Two (02)done to Request for Proposal No. 140A0918R0010 as follows:
1. To extend the Proposal due date to Tuesday, January 16, 2018 at 5:00 p.m.
2. The Questions Asked will be posted in another amendment when the government answers those questions.
ALL OTHER TERMS AND CONDITIONS ARE TO REMAINS THE SAME IN FULL FORCE AND EFFECT.
Update #2 ·
BIE/NMNN/FM/ADD HANDRAILS/LADDER WATER T
Update #1 ·
BIE/NMNN/FM/ADD HANDRAILS/LADDER WATER T
Files
| File | Type | Posted |
|---|---|---|
| FedConnect File | — |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity