BEAVERHEAD-DEERLODGE NF, Perkins Gulch AOP Construction

Award Notice Posted

Solicitation number
AG-0356-S-14-0014
Agency
Awarded
to R And S Johnson Construction Company
Set-aside
Total Small Business

Opportunity facts

Contract number
AG-0356-C-14-0004 Federal contract award
NAICS code
237310 Highway, Street, and Bridge Construction
PSC
Not on record
Place of performance
Pintler Ranger District Philipsburg, Montana 59858, United States

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

Perkins Gulch AOP on the Pintler Ranger District

Amendment 002 replaced the Schedule of Items and extended the closing date for responses to 04-16-14 at 4:00 PM Mountain Time.

Update #3 ·

See Amendment 001  for more site specific access and conditions.

Update #2 ·

Z- Perkins Gulch AOP Construction on the Pintler Ranger District
Description of Work: The project consists of removal of an 28-inch x 22-inch arch x 21-ft length corrugated metal pipe and installation of a 7-ft span X 4-ft rise X 36-ft length precast concrete box culvert with less than 2 feet of cover per ASTM 1577-10. The project includes erosion control features, excavation, embankment and furnishing & installing the concrete box culvert and furnishing and placing crushed aggregate. The Contractor will provide all equipment, operating supplies, operators, labor, supervision and support functions necessary to perform the work in compliance with these terms, specifications and provisions.

Project Location: The project site is located approximately 6 miles east of Warm Springs, Montana on the Pintler Ranger District of the Beaverhead Deerlodge National Forest. Construction will take place at the intersection of the main stem of Perkins Gulch Creek and FSR 5165 at approximately mile post 6.1. See the Vicinity Map included in
the plans for the specific location.

Construction Magnitude is between $25,000 - $150,000.

No formal site visit is planned.   Interested vendors are urged and expected to inspect the site where services are to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. For technical and site specific details please contact Jim Yarbrough at 406-683-3859.

Period of Performance: All construction work must be accomplished between August 15, 2014 and October 15, 2014. Contract time will run continuously with no shutdown for normal winter season.


 Look for full solicitation, maps and specifications to be posted in mid March.

Update #1 ·

Z- Perkins Gulch AOP Construction on the Pintler Ranger District
Description of Work: The project consists of removal of an 28-inch x 22-inch arch x 21-ft length corrugated metal pipe and installation of a 7-ft span X 4-ft rise X 36-ft length precast concrete box culvert with less than 2 feet of cover per ASTM 1577-10. The project includes erosion control features, excavation, embankment and furnishing & installing the concrete box culvert and furnishing and placing crushed aggregate. The Contractor will provide all equipment, operating supplies, operators, labor, supervision and support functions necessary to perform the work in compliance with these terms, specifications and provisions.

Project Location: The project site is located approximately 6 miles east of Warm Springs, Montana on the Pintler Ranger District of the Beaverhead Deerlodge National Forest. Construction will take place at the intersection of the main stem of Perkins Gulch Creek and FSR 5165 at approximately mile post 6.1. See the Vicinity Map included in
the plans for the specific location.

Construction Magnitude is between $25,000 - $150,000.

No formal site visit is planned.   Interested vendors are urged and expected to inspect the site where services are to be performed to satisfy them regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. For technical and site specific details please contact Jim Yarbrough at 406-683-3859.

Period of Performance: All construction work must be accomplished between September 1, 2014 and October 31, 2014. Contract time will run continuously with no shutdown for normal winter season.


 Look for full solicitation, maps and specifications to be posted in mid March.

Files

File Type Posted
Amend_002.pdf PDF
sf-30_amend_001.rtf RTF text file
FSS_Specifications.pdf PDF
Experience_Questionaire.docx DOCX document
sf_18_request_for_quote.doc DOC document
DRAWINGS.pdf PDF
AG-0356-S-14-0014.rtf.pdf PDF