BEAVERHEAD-DEERLODGE NATIONAL FOREST - Nez Perce CDNSTrail Reconstruction

Award Notice Posted

Solicitation number
AG-0356-S-15-0021
Agency
Awarded
to Wildwood Trails, Inc.
Set-aside
Total Small Business

Opportunity facts

Contract number
AG-0356-C-15-0010 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record
Place of performance
Butte Ranger District 1820 Meadowlark Lane Butte, Montana 59701, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

Z- Nez Perce CDNSTrail Reconstruction on the Butte Ranger District

Project Location and Directions. To get to this project take I-15 North of Butte to the Elk Park Exit No. 138. Turn right or south at the Exit onto the Frontage Road. Take an immediate left onto the Nez Perce Road and travel along this road 3 miles to the Nez Perce Trailhead. The work begins at the Nez Perce Trailhead. The trailhead is accessible by passenger car.

Description of Work. This project will construct much needed drainage features along an existing trail located off of the Elk Park Exit just north of Butte. The trail is currently a single-track motorized trail that was constructed in the early 2000's. The trail has not received significant maintenance in several years, and the switchbacks are all rutted and will need to be reconstructed.

Equipment Requirments.
All tools and equipment shall be furnished by the contractor. Excavators shall be limited to a maximum 39-inch track width. 2-wheeled motor vehicles are allowed for construction purposes only, such as transportation of employees and materials. 4-wheeled motor vehicles are not allowed. When not on site, keep valuable tools hidden from the trail.
A blasting plan (including copy of Montana Blaster license holder) is required at time of quote submission.

No formal site visit will be held. Contractors should inspect the site on their own.

Construction Magnitude
is $25,000 to $100,000

Performance Period
is from July 1, 2015 thru September 30, 2016.  No work can be done on site from 10-1-2015 thru 06-01-2016.

Update #2 ·

Z- Nez Perce CDNSTrail Reconstruction on the Butte Ranger District

Project Location and Directions. To get to this project take I-15 North of Butte to the Elk Park Exit No. 138. Turn right or south at the Exit onto the Frontage Road. Take an immediate left onto the Nez Perce Road and travel along this road 3 miles to the Nez Perce Trailhead. The work begins at the Nez Perce Trailhead. The trailhead is accessible by passenger car. Although this project lies directly off the interstate early snow could prevent viewing the end of the project by late October.

Description of Work. This project will construct much needed drainage features along an existing trail located off of the Elk Park Exit just north of Butte. The trail is currently a single-track motorized trail that was constructed in the early 2000's. The trail has not received significant maintenance in several years, and the switchbacks are all rutted and will need to be reconstructed. There is a significant amount of rock in this area, and non-certified rock blasters are not encouraged to bid.

Equipment Requirments. All tools and equipment shall be furnished by the contractor. Excavators shall be limited to a maximum 39-inch track width. 2-wheeled motor vehicles are allowed for construction purposes only, such as transportation of employees and materials. 4-wheeled motor vehicles are not allowed. When not on site, keep valuable tools hidden from the trail.
A blasting plan (including copy of Montana Blaster license holder) is required at time of quote submission.

No formal site visit will be held. Contractors should inspect the site on their own.

Construction Magnitude
is $25,000 to $100,000

Performance Period
is from July 1, 2015 thru September 30, 2016.  No work can be done on site from 10-1-2015 thru 06-01-2016.

Complete solicitation, specifications and drawings will be posted to this site in approximately 15 days from today. 

Update #1 ·

Z- Nez Perce CDNSTrail Reconstruction on the Butte Ranger District

Project Location and Directions. To get to this project take I-15 North of Butte to the Elk Park Exit No. 138. Turn right or south at the Exit onto the Frontage Road. Take an immediate left onto the Nez Perce Road and travel along this road 3 miles to the Nez Perce Trailhead. The work begins at the Nez Perce Trailhead. The trailhead is accessible by passenger car. Although this project lies directly off the interstate early snow could prevent viewing the end of the project by late October.

Description of Work. This project will construct much needed drainage features along an existing trail located off of the Elk Park Exit just north of Butte. The trail is currently a single-track motorized trail that was constructed in the early 2000's. The trail has not received significant maintenance in several years, and the switchbacks are all rutted and will need to be reconstructed. There is a significant amount of rock in this area, and non-certified rock blasters are not encouraged to bid.

Equipment Requirments. All tools and equipment shall be furnished by the contractor. Excavators shall be limited to a maximum 39-inch track width. 2-wheeled motor vehicles are allowed for construction purposes only, such as transportation of employees and materials. 4-wheeled motor vehicles are not allowed. When not on site, keep valuable tools hidden from the trail.
A blasting plan (including copy of Montana Blaster license holder) is required at time of quote submission.

No formal site visit will be held. Contractors should inspect the site on their own.

Construction Magnitude
is $25,000 to $100,000

Performance Period
is from June 1, 2015 thru September 30, 2016.  No work can be done on site from 10-1-2015 thru 06-01-2016.

Complete solicitation, specifications and drawings will be posted to this site in approximately 15 days from today. 

Files

File Type Posted
Experience_Questionaire.docx DOCX document
Amendment_001.pdf PDF
sf1442pdf.pdf PDF
Davis_Bacon_Wages_MT76.pdf PDF
Specifications.pdf PDF
Maps _Log_and_Drawings.pdf PDF
AG0356S150021.pdf PDF