Beale AFB 9MUNS K5 Pad - Gravel, Silt Fencing, Straw Wattle Burlap Covers

Closed Solicitation Posted

Solicitation number
FA468625Q0029
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Beale AFB, California 95903, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Air Force Air Combat Command is procuring construction materials for the 9 MUNS K5 pad at Beale Air Force Base to establish a new staging ground for inert explosive material. The required materials include 750 tons of 3/4" crushed rock, 8 stacks of 36x100 foot silt fencing, 36 stacks of 8.5x25 foot straw wattle burlap covers, and 200 stakes for installation with the wattle covers. This firm fixed-price procurement requires delivery only with no installation services needed, and all materials must be delivered within 60 calendar days from the date of award. The contract evaluation will be based on price reasonableness and technical acceptability, with the award going to the responsible contractor offering the best value who is registered in SAM.gov and not listed on the excluded parties list. The solicitation was originally posted on June 5, 2025, with the proposal due date extended from June 23, 2025 to July 17, 2025 through a subsequent amendment.

This opportunity is designated as a total small business set-aside under NAICS code 212321 for Construction Sand and Gravel Mining, with no incumbent contractors identified in the documentation. While specific award values are not disclosed in the solicitation materials, the procurement involves substantial quantities of construction materials including three-quarters of a million tons of crushed rock and nearly 2,000 linear feet of erosion control materials. The materials are required to support block training for Temporary Duty students in the Air Force Combat Ammunition Course and must be delivered to the 9 MUNS MXWM facility at Beale Air Force Base, California by September 30, 2025. The primary point of contact for this procurement is Staff Sergeant Eddie S. Bolos, Resource Advisor for the 9th Munitions Squadron, who can be reached at 530-634-3689 for any questions regarding the material requirements.

Notice text

2 versions

Update #2 · Latest ·

*Amendment 0001: Issuing revised Statement of Need and Amended Solicitation, extending quote due date.

The 9MUNS K5 pad requires the following material to establish new staging ground for Inert Explosive material:

- 3/4”Crushed Rock–750 Tons

- Silt Fencing –36x100 FT, 8 units (800ft total)

- Straw Wattle Burlap Covers with stakes –8.5x25 FT (900ft total), 36 units, 200 stakes

No installation needed, delivery only.

*See attachments*

1) Statement of Need

2) Solicitation 

Update #1 ·

The 9MUNS K5 pad requires the following material to establish new staging ground for Inert Explosive material:

- 3/4”Crushed Rock–750 Tons

- Silt Fencing –36x100 FT, 8 stacks

- Straw Wattle Burlap Covers –8.5x25 FT, 36 stacks

No installation needed, delivery only.

*See attachments*

1) Statement of Need

2) Solicitation 

Files

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Beale AFB 9MUNS K5 Pad - Gravel, Silt Fencing, Straw Wattle Burlap Covers Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Aggregate Stone Material - Fort Riley, Kansas Fort Riley, Kansas 66442, United States · NAICS 212321 MICC Fort Hood Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors