Barren River Lake Repair Drainage Ditch at Tailwater Stilling Basin
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912QR26QA094
- Agency
-
ENDIST Louisville
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238910 Site Preparation Contractors
- Place of performance
- United States Corps of EngineersBarren River Lake11088 Finney RdGlasgow, KY 42141 42141
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Corps of Engineers Engineering District Louisville seeks repair of a drainage ditch at the tailwater stilling basin at Barren River Lake, with quotes due September 18, 2026 (extended from September 11 by Amendment 0001). The procurement is 100% set-aside for Small Business under NAICS 238910, Site Preparation Contractors, with a size standard of $19 million.
Place of performance is Barren River Lake, Glasgow, Kentucky. The contractor must furnish all labor, materials, supplies, tools, and equipment necessary to complete the work. Work must begin within 10 calendar days of Notice to Proceed and conclude 180 calendar days thereafter. Award will be based on lowest total price to the Government. Bid bonds are required and must accompany the quote submission. Payment will be by Electronic Funds Transfer to a contractor-specified commercial bank account.
A site visit is scheduled for September 8, 2026 at 9:00 AM Central Time; contractors should contact Ryan Weaver at 270-646-2055 or Ryan.A.Weaver@usace.army.mil to confirm attendance. The site visit is recommended to review work-site complexities, verify existing conditions, and confirm exact measurements. Amendment 0001 revised the Statement of Work, Performance-Based Schedule (PBS), and extended the quote due date. The PSC code is Z2AA, Repair or Alteration of Office Buildings.
Notice text
2 versions
Update #2 · Latest ·
*** Amendment 0001 posted, revised SOW, PBS and the quote due date has been extended to 18 September 2026*** Barren River Lake Repair Drainage Ditch at Tailwater Stilling BasinThe contractor s work and responsibility will include furnishing all labor, materials, supplies, tools and, equipment necessary to assure that all work is conducted in accordance with the contract requirements and all applicable Federal, State and Local laws and regulations. All work will be performed in strict compliance with the attached specifications and all other terms and conditions incorporated herein. Work will shall begin within 10 calendar days of Notice to Proceed and must conclude 180 calendar days after Notice to Proceed.Location:United States Corps of EngineersBarren River Lake11088 Finney RdGlasgow, KY 42141This procurement is 100% set-aside for Small Business, NAICS 238910, Size Standard $19M.Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.Note: The contract award will be based on lowest total price to the Government.** Bid Bonds are required and must be provided at the same time of your submission. **A site visit is highly recommended, Contractors are encouraged to attend a site visit to review the complexities of the work site, verify existing conditions, and exact measurements. The site visit is scheduled for 8 September 2026, 0900 CT. Please reach out to Ryan Weaver at 270-646-2055 or Ryan.A.Weaver@usace.army.mil to confirm your attendance.Quotes are due 11 September 2026, 12:00PM Eastern Time.
Update #1 ·
Barren River Lake Repair Drainage Ditch at Tailwater Stilling BasinThe contractor s work and responsibility will include furnishing all labor, materials, supplies, tools and, equipment necessary to assure that all work is conducted in accordance with the contract requirements and all applicable Federal, State and Local laws and regulations. All work will be performed in strict compliance with the attached specifications and all other terms and conditions incorporated herein. Work will shall begin within 10 calendar days of Notice to Proceed and must conclude 180 calendar days after Notice to Proceed.Location:United States Corps of EngineersBarren River Lake11088 Finney RdGlasgow, KY 42141This procurement is 100% set-aside for Small Business, NAICS 238910, Size Standard $19M.Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.Note: The contract award will be based on lowest total price to the Government.** Bid Bonds are required and must be provided at the same time of your submission. **A site visit is highly recommended, Contractors are encouraged to attend a site visit to review the complexities of the work site, verify existing conditions, and exact measurements. The site visit is scheduled for 8 September 2026, 0900 CT. Please reach out to Ryan Weaver at 270-646-2055 or Ryan.A.Weaver@usace.army.mil to confirm your attendance.Quotes are due 11 September 2026, 12:00PM Eastern Time.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Barren River Lake Repair Drainage Ditch at Tailwater Stilling Basin | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity