4 versions

Update #4 · Latest ·

The purpose of this Amendment is to publish the questions and answers from the Pre-Bid Site Visit held July 21, 2015 and to attach the Bid Bond form:

Q1-Spec says park will haul grindings - will they be able to keep up, how far away will they be hauled?

A1-Park will have 2 large dump trucks and a small one. Grindings will be stockpiled near project sites so will not slow work progress.



Q2-At Narada Falls site - what material is under asphalt?

A2-Concrete



Q3-Are there weight limits on bridge?

A3-Park regularly drives equipment over 50k pounds, not a concern.



Q4-Horsetail vegetation along edge at Narada, pave over? What about other vegetation near edge?

A4-Park will be responsible for removal of edge vegetation. No spraying allowed.



Q5-Small section of raised berm to stay or be flat?

A5-No raised berm, all flat.



Q6-Will payment be lump sum or price per ton laid?

A6-Paid per ton laid.



Q7-Narada Falls area - do you want risers on the sewer covers?

A7-Yes



Q8-On Steven's Canyon - how deep to grind butt joints?

A8-2"



Q9-Who will be responsible for striping?

A9-Park will do striping.



Q10-Do you want us to grind and pave all of each location at one time before moving to next?

A10-No, can grind all and pave one lane of each location then do other lane paving to allow for traffic to flow.



No other changes.





No other changes.



Update #3 ·

The purpose of this Amendment is to correct an error in Section M - Evaluation Factors for Award as follows:



AMENDMENT 0001 Correction to Evaluation Factor 3



SECTION M: Evaluation Factors for Award



EVALUATION FACTORS FOR AWARD

3. Qualifications and Experience of Key Personnel factors. The Government will evaluate the submitted documentation of the key personnel assigned to this project as to their qualifications and experience based on the scope, magnitude, and relevance of past work similar to the proposed project. Specific attention will be paid to work involving asphalt overlay similar to the proposed project including overlay and grinding on mountainous roads.



Specifically, review will be made of documentation of the key personnel assigned for this project

a)Documented experience by the on-site job superintendent in completing asphalt grinding and overlay projects similar to the proposed work.

b)Documented experience of on-site personnel in working on asphalt overlay projects of similar size and complexity.



No other changes.



Update #2 ·

Asphalt Road Paving, Narada & Steven's Canyon Rds, Mount Rainier National Park

Update #1 ·

Asphalt Road Paving, Narada & Steven's Canyon Rds, Mount Rainier National Park

Files

Notice history

Notice Type Posted
Narada & Steven's Canyon Asphalt Overlay Latest Award Notice
This notice Original Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors