Notice text

5 versions

Update #5 · Latest ·

This Solicitation has been cancelled.  A new Solicitation will be issued shortly. 

Update #4 ·

This Solicitation has been cancelled.  A new Solicitation will be issued shortly. 

Update #3 ·

AMENDMENTS:

A. Contractor must be approved and permitted to perform asbestos removal in Allegheny County. Permits and/or license will be submitted prior to NTP.


B. Removal of VCT under any permanently installed equipment is not required.


C. Disposal will be done using an EPA approved landfill. All copies of landfill receiving documents will be returned to the contracting office upon completion of the project.


D. Air quality samples and test will be conducted by the contractor and results will be made available within 14 days of completion of remediation.

Update #2 ·

AMENDMENT / CLARIFICATION (11/28): ROOM SIZE IS ROOM SIZE: 9' x 9' -- 81 Sq. Feet


**IMPORTANT** Quotes will only be accepted from vendors who participate in the Site Visit, schedule for Thursday, 1 December at 10:00AM EST.

IN ORDER TO TAKE PART IN THE SITE VISIT, prospective vendors MUST email the following information to Michael.w.boyd2.mil@mail.mil by 3:00PM EST on Wednesday, 30 November:


-Company Name
-Names of All Personnel Attending
-Drivers License State & Number of All Personnel Attending


 


STATEMENT OF WORK
Repair B102 Utility Room Floor
Project: JLSQ162019
Date: 16 June 2016



SCOPE: The work consists of furnishing all labor, materials, tools, equipment, supplies, transportation, supervision, and inspection required to perform all tasks described below.


LOCATION/SITE VISITS: This project is located at the Air National Guard Base, Pittsburgh International Airport, Pennsylvania, 15108-1940. Site visits may be arranged through the 171st Civil Engineer Squadron, Commercial (412) 776-7519.


GENERAL REQUIREMENTS:


A. Normal duty hours of operation at the base are:
1st week: Monday to Thursday from 0700 to 1630 hours as well as Friday from 0700 to 1530 hours
2nd week: Tuesday to Friday from 0700 to 1630 hours


B. Construction shall be accomplished according to a phased schedule to limit impact on airfield operations. In specified phased areas, construction may be accomplished any time during the aforementioned hours unless the base is closed for a holiday.


C. Prior coordination with the Contracting Officer (CO) is required to work outside these hours.


PRINCIPLE ELEMENTS OF WORK:


A. Remove and dispose of asbestos containing materials in B102's utility room (room 108).
a. Contractor shall remove all existing asbestos in black mastic and 9"x9" VCT and properly dispose of debris and waste off site.


Contractor shall supply SDS for all products used on this project.


Contractor shall provide a report on materials removed from the project site. Indicate volume (CY) and tonnage of materials that are disposed in landfills. Indicate volume (CY) and tonnage of materials that are reused or recycled. Indicate other methods of disposal as indicated on the report form provided.


 


 

Update #1 ·

**IMPORTANT** Quotes will only be accepted from vendors who participate in the Site Visit, schedule for Thursday, 1 December at 10:00AM EST.

IN ORDER TO TAKE PART IN THE SITE VISIT, prospective vendors MUST email the following information to Michael.w.boyd2.mil@mail.mil by 3:00PM EST on Wednesday, 30 November:


-Company Name
-Names of All Personnel Attending
-Drivers License State & Number of All Personnel Attending


 


STATEMENT OF WORK
Repair B102 Utility Room Floor
Project: JLSQ162019
Date: 16 June 2016



SCOPE: The work consists of furnishing all labor, materials, tools, equipment, supplies, transportation, supervision, and inspection required to perform all tasks described below.


LOCATION/SITE VISITS: This project is located at the Air National Guard Base, Pittsburgh International Airport, Pennsylvania, 15108-1940. Site visits may be arranged through the 171st Civil Engineer Squadron, Commercial (412) 776-7519.


GENERAL REQUIREMENTS:


A. Normal duty hours of operation at the base are:
1st week: Monday to Thursday from 0700 to 1630 hours as well as Friday from 0700 to 1530 hours
2nd week: Tuesday to Friday from 0700 to 1630 hours


B. Construction shall be accomplished according to a phased schedule to limit impact on airfield operations. In specified phased areas, construction may be accomplished any time during the aforementioned hours unless the base is closed for a holiday.


C. Prior coordination with the Contracting Officer (CO) is required to work outside these hours.


PRINCIPLE ELEMENTS OF WORK:


A. Remove and dispose of asbestos containing materials in B102's utility room (room 108).
a. Contractor shall remove all existing asbestos in black mastic and 9"x9" VCT and properly dispose of debris and waste off site.


Contractor shall supply SDS for all products used on this project.


Contractor shall provide a report on materials removed from the project site. Indicate volume (CY) and tonnage of materials that are disposed in landfills. Indicate volume (CY) and tonnage of materials that are reused or recycled. Indicate other methods of disposal as indicated on the report form provided.


 


 

Files

File Type Posted
AF_Form_66_-_Repair_Mech_Room_Floor.doc DOC document

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors