Archer – stegall no. 1 115-KV transmission line 2020 storm damage repair
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 89503221BWA000042
- Agency
-
Western Area Power Administration
Department of Energy
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237130 Power and Communication Line and Related Structures Construction
- Place of performance
- Cheyenne, Wyoming 82009, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is seeking a contractor to provide all labor, materials, tools, equipment, transportation and other resources necessary to complete a storm damage repair project for the ARCHER – STEGALL NO. 1 115-KV transmission line located in Laramie County, WY. The work includes removing an existing sho-fly transmission line and steel monopole structures, rebuilding the transmission line between identified structures, and providing motion control devices on 19.6 miles of transmission line. Responses are due by July 12, 2021 and shall be submitted through FedConnect in accordance with the solicitation to be issued by the Department of Energy Western Area Power Administration on or about June 12, 2021.
This requirement has been set aside 100% for small businesses with a NAICS code of 237130 and size standard of $39.5M. The period of performance is 220 days after notice to proceed and the estimated value is between $1,000,000 to $5,000,000. Bidders must identify any non-domestic materials in their proposals as the Buy American Act applies.
Notice text
NOTE: All responses to this IFB shall be submitted via FedConnect in accordance with the instructions provided in the solicitation.
The Western Area Power Administration, Rocky Mountain Region has a requirement for a contractor to provide all the labor, materials, tools, equipment, transportation, and other resources necessary to complete this project. The work includes the removal of 1.2-miles of 115-kV wood pole shoo-fly transmission line, removing and replacing five (5) steel monopole structures, rebuilding 1.2-miles of 115-kV transmission line from structures 29/2 to 30/1, and providing motion control devices on 19.6-miles of transmission line between Pole Creek Tap and Round Top Tap. The project is located in Laramie County, WY with a period of performance of 220 days after Notice To Proceed. The estimated order of magnitude is between $1,000,000 and $5,000,000. FAR Part 14 is being utilized for this requirement. The solicitation will be issued as a 100% small business set-aside. The applicable NAICS Code is 237130; Size Standard is $39.5M. The solicitation including specifications and drawings will be issued electronically at this site on or about 12 June 2021 at the following sites: https://www.fedconnect.net and https://www.fbo.gov/
NOTE: the Buy American Act applies to the solicitation. Refer to FAR Clause 52.225-9 (Section I) and FAR Provision 52.225-10 (Section L) if any non-domestic material will be proposed. Bidders must identify any non-domestic materials (not manufactured in United States) included in their bid. Please check with your suppliers and subcontractors to verify whether or not their quotes include non-domestic material.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Archer – stegall no. 1 115-KV transmission line 2020 storm damage repair | Award Notice | |
| Archer – stegall no. 1 115-KV transmission line 2020 storm damage repair | Solicitation | |
| This notice | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity