Accelerated Design-Build to Budget Construct Barracks, Multi-Use Training Facility, Galley & Firehouse at USCG TRACEN Cape May, Cape May, NJ

Award Notice Posted

Solicitation number
70Z04726RPCNI0006
Agency
Awarded
to The Whiting-Turner Contracting Company
Set-aside
No set-aside

Opportunity facts

Contract number
70Z04723DPCNI0006-70Z04726FPCNI0009 Federal contract award
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1FC Construction Of Troop Housing Facilities
Place of performance
Cape May, New Jersey 08204, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Coast Guard awarded an accelerated design-build contract on April 29, 2026, for construction of barracks, a multi-use training facility, galley, and firehouse at USCG Training Center Cape May in Cape May, New Jersey.

The scope includes demolition of abandoned steam trenches and buildings, relocation of electrical duct banks, construction of new VIP review stand and grandstands with cantilevered shading, and a new parade path. The contractor must design and construct barracks facilities to maintain TRACEN Cape May's annual operational capacity of 5,600 recruits without interruption throughout the project duration. A minimum of three barracks buildings must remain operational at all times during construction. The designer of record has flexibility to modify the number of barracks buildings from the four shown in RFP drawings, provided the core mission-critical recruit accommodation capacity is fully satisfied. The project can be delivered in phases, with phasing to commence following award and finalization of the Base Item 0001 process. The award was made under unrestricted competition with no set-aside applied.

Notice text

The project will be to Design/Build new facilities at TRACEN Cape May, NJ. The scope of work includes but is not limited to construction of barracks buildings to accommodate an annual capacity of 5,600 recruits. It is a critical and non-negotiable requirement that the annual operational capacity of TRACEN Cape May be maintained without interruption for the entire duration of the construction project. Therefore, all construction efforts must be planned and executed in a manner that ensures no reduction in the annual number of recruits processed. The continuity of operations is a paramount objective of this project.

While the RFP drawings indicate the construction of four barracks buildings, the Designer of Record is granted the flexibility to modify this number. The ultimate number of buildings is secondary to achieving the essential operational throughput. This approach allows for potential design optimizations and innovative solutions, provided the core mission-critical requirement of recruit accommodation capacity is fully satisfied.

The scope of work includes but is not limited to; demolition and disposal of abandoned steam trenches, buildings and building old foundations, relocation of electrical duct banks and salvaging of transformers, temporary office trailer setup, construction of new VIP review stand, grandstands with cantilevered shading and new parade path. During construction of the new barracks a minimum of 3 barracks buildings must remain operational at all times.  This project can be delivered in phases. However, the construction phases outlined here will occur only after the Base Item 0001 process is awarded and finalized.  Proposed phasing is as follows: During phase 1, the existing MCPOCG (Bldg. 911) can be demolished and two temporary office trailers will be provided complete with water, sewer, electrical and C5IT connections. Two new barracks buildings can be constructed.  Then James and Healy Halls can be demolished.  Phase 2 will require construction of all remaining barracks facilities. In addition to the remaining barracks facilities, construction of several facilities is required in order of precedence:

1.Multi-purpose training facility (~80,000GSF)

2.Galley or expansion of existing galley to meet future throughput requirements. (~35,000GSF)

3.Fire station (~20,000GSF)

  • The firehouse must have a natural gas generator and automatic transfer switch meeting the requirements of NFPA 70, Article 701, Legally Required Standby Systems.  The generator shall be sized to power all the loads within the entire building.
  • The UPS shall power all loads associated with emergency services.  Emergency services loads include, but are not limited to: radio communication system, emergency response system, fire alarm front end, burglar alarm front end, all communication equipment, etc.

Note: See Attachment H

Prior to demolition of existing galley and fire station, the new facilities will need to be constructed.  All facilities are required to be sustainable in accordance with the Council on Environmental Quality (CEQ) Guiding Principles for Federal Buildings, Dec 2020. All facilities shall strive to incorporate the best in energy efficiency, environmental performance, and advanced controls using a “whole building” integrated design approach, as well as comply with ENERGY STAR standards.  The final phasing of these additional facilities will have to be determined by the Designer of Record (DOR) in coordination with the TRACEN Cape May Facility Engineering office. See site civil drawings.

Awarded contract 70Z04723DPCNI0006 to WHITING-TURNER CONTRACTING COMPANY, THE for 400000000.00 on 2026-04-29.