618-16-3-6977-0092 Bldg 69 Air Make-Up Replacement 618-15-133 Minneapolis VA Health Care System. Sole Source Pre-Solicitation Notice For Woman Owned Service Disabled Veteran Owned Small Business (WOSDVOSB).

Award Notice Posted

Solicitation number
VA26316R0327
Agency
Awarded
to Midwest Select Contracting LLC
Set-aside
Service-Disabled Veteran-Owned Small Business

Opportunity facts

Contract number
VA26316C0102 Federal contract award
PSC
Not on record
Place of performance
One Veterans Dr. Minneapolis, MN 55417 USA
More information

Notice details come from SAM.gov. Updated .

Notice text

SCOPE OF WORK

MAKE UP AIR UNIT REPLACEMENT BLDG 69

MINNEAPOLIS VA MEDICAL CENTER



A. Base Bid: The Contractor shall provide all labor, materials and equipment to accomplish the "make up air unit replacement bldg. 69" project per construction drawings and specifications. The project shall be accomplished per contract drawings numbered XXXXXXXXXXX, specification number 618-16-3-6977-0092. This work includes, but is not limited to:



1. Demolition: Removal, recycling, and disposal of expended make-up air unit.



2. Contractor shall remove from the VA site and dispose of all equipment and materials not scheduled to be reused.



3. New construction consists of, but is not limited to: Acquisition of new (OEM) air handling unit of appropriate size to provide a surplus of combustion air. Installation and hanging of new air handling unit. Installation of all associated piping, wiring, ventilation, and any other required retrofitting to obtain an operational status. Deploying and automating the make-up air unit's controls with the METASYS control interface for everyday operation. Note: Metasys controls are installed on existing unit.



a. Training employees and commissioning the new unit.



4. DESCRIBE PHASING, OFF-HOURS WORK, OR MAJOR SHUTDOWNS…..



The contractor shall submit the equipment submittals according to the timelines set in the Tentative Schedule listed in this document. The manufacturer has indicated that the lead time to build the replacement equipment will be eight to ten (8-10) weeks, so it is imperative that submittals are presented to the COR with expediency, in order to gain COR approval and the ability to order the equipment to be built. The longest portion of the schedule is expected to be the wait time while the replacement equipment is being built.



B. Cost Range:

The anticipated Magnitude of construction between $25,000 and $100,000.

Files

File Type Posted
VA263-16-R-0327-000.docx DOCX document
VA263-16-R-0327-001.pdf PDF

Notice history

Notice Type Posted
Award notice: Sole source; Women Owned Service Disabled Veteran Small Business. Bldg 69 Air Make-Up Replacement Project No. 618-15-133 MVAMC Latest Award Notice
This notice Original Award Notice