About this opportunity

This solicitation has been cancelled. The Department of Veterans Affairs Network Contracting Office 10 cancelled Request for Quote 36C25026Q0889 in its entirety effective September 18, 2026.

Prior to cancellation, the RFQ sought removal and replacement of two air compressors at the Marion VA Medical Center Boiler Plant, with a proposal due date of September 10, 2026, and questions due September 8, 2026. The procurement was set aside 100% for small business.

Place of performance was Marion, Indiana (1700 East 38th Street, Marion VA Medical Center, Building 76). The compressors required minimum specifications of 5 horsepower, 135 PSI, and 14.27 CFM, with delivery required within 60 days after receipt of order. The acquisition budget was $19 million with firm-fixed-price contract type. Work scope included equipment supply, sequential removal of existing compressors, installation, electrical and mechanical connections, startup services, and disposal compliant with applicable VA, federal, state, and local regulations.

A mandatory site visit was scheduled for August 31, 2026, at 9:00 AM (attendance optional for responsive quotation submission). Contractors were required to be registered in SAM and the VA's financial system via the 10091 webform. Award was to be made via comparative analysis considering price and past performance. The solicitation clarified that equivalent compressors meeting specified horsepower, PSI, CFM, and electrical requirements were acceptable; manufacturer authorization letters were required when the prime contractor was not the manufacturer; and no bonds, prevailing wage determinations, or special insurance were required. Payment was authorized only after complete delivery, installation, and acceptance, with no progress payments permitted.

NAICS code 238220, PSC code 4310.

Notice text

3 versions

Update #3 · Latest ·

Page 2 of 2

The purpose of this amendment is to cancel Request for Quote 36C25026Q0889 in its entirety.

Update #2 ·

RFQ 36C25026Q0889 Questions and Answers

The solicitation references both VAAR 852.219-75 and 852.219-76 regarding the Limitations on Subcontracting certification. Which certification must be completed and submitted with our quotation, and where can we obtain the required form?

Answer: The VARR references concerning the Limitations on Subcontracting were mistakenly put in the RFQ. All mentions of VAAR 852.219-75 and VAAR 852.219-76 have been removed from the RFQ.

How will the limitation on subcontracting be calculated for this requirement, considering that it includes equipment, materials, removal, installation, electrical and mechanical connections, and startup services?

Answer: Limitations on subcontracting are not pertinent to this RFQ. All mentions of VAAR 852.219-75 and VAAR 852.219-76 have been removed from the RFQ.

The site-visit RSVP deadline is listed as Friday, August 29, 2026, but August 29 falls on a Saturday. Is the correct RSVP deadline Friday, August 28, or Saturday, August 29? Also, is attendance at the site visit mandatory to submit a responsive quotation?

Answer: The site-visit RSVP deadline is Friday, August 28, 2026. Attendance at the site visit is not mandatory.

The Statement of Work identifies the RA-11I Fixed Speed 4 11KW compressor. Is this exact manufacturer and model required, or will an equal compressor meeting or exceeding the listed horsepower, PSI, CFM, electrical, and operational requirements be accepted?

Answer: All mention of any manufacturer verbiage has been removed from the RFQ.

If an equivalent product is permitted, are there any additional specifications that must be met, including voltage, phase, tank size, dryer requirements, controls, connection sizes, or required manufacturer certifications?

Answer: There is no longer any mention of any exact manufacturer.

The solicitation requires a manufacturer authorization letter when the prime contractor is not the manufacturer. Will a letter from the manufacturer confirming that our proposed supplier or installing subcontractor is an authorized dealer or distributor satisfy this requirement, or must the letter specifically name V Notary Service LLC as the authorized seller?

Answer: As stated in the RFQ, if a contractor is not the manufacturer of the products being offered, they must provide a letter/memo from the manufacturer stating they are authorized to sell/distribute the manufacturer s products. A letter/memo stating a subcontractor is authorized to sell/distribute the manufacturers products is not sufficient.

The delivery schedule lists September 30, 2026, while the period of performance is October 1 through October 31, 2026. Should the two compressors and startup kits be delivered by September 30, with removal and installation performed during October?

Answer: Any mention of a period of performance has been removed. The contractor is required to complete the three (3) line items in the RFQ 60 days after receipt of the order (ARO).

Please confirm whether any bid bond, payment bond, performance bond, prevailing-wage determination, or special insurance coverage is required for this procurement.

Answer: There is no requirement for any bid bond, payment bond, performance bond, prevailing wage determination, or special insurance coverage required for this requirement.

Will payment be issued after the complete installation and acceptance of both compressors, or may the contractor invoice separately for delivered equipment and completed installation milestones?

Answer: Payment will be made after the delivery, installation and acceptance of the products. Progress payments are not authorized.

Update #1 ·

Air Compressor removal and replacement at the Marion VA Medical Center.

Files

Notice history

Notice Type Posted
4310--610 - COMPRESSORS Boiler Plant Bldg 76 - ENGINEERING, NIHCS Amendment to Answer Contractor Questions Latest special notice Special Notice
This notice Original Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
CANCELLATION - NTX Steam Trap Monitoring - CANCELLATION Dallas, Texas 75216, United States · NAICS 238220 Veterans Integrated Service Network 17 Service-Disabled Veteran-Owned Small Business
J041--Condenser Coils Replacement for the VA Illiana Health Care System (VAIHCS), located at 1900 E. Main Street, Danville, IL 61832. NAICS 238220 Veterans Integrated Service Network 12 Service-Disabled Veteran-Owned Small Business
J043--Damen Building Vacuum Condensate System Rebuild Jesse Brown VA Medical Center 820 S. Damen Ave, Chicago, IL 60612 · NAICS 238220 Veterans Integrated Service Network 12 No set-aside