15kV Switchgear & Station Service Replacement at Lake Tenkiller, OK

Pre-Solicitation Posted

Solicitation number
W912BV26RA032
Agency
Responses due
Not on record
Set-aside
Total Small Business

Opportunity facts

Place of performance
Paradise Hill, Oklahoma, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers Tulsa District has posted solicitation W912BV27RA003 on October 27, 2026, for a 15kV Switchgear and Station Service Replacement at Lake Tenkiller, Oklahoma, as a Total Small Business set-aside. The update supersedes the July 6, 2026 pre-solicitation notice, which described the same Small Business Set-Aside. The procurement is a design-bid-build, firm-fixed-price contract under Revolutionary FAR Overhaul (RFO) Part 15, using Lowest Price Technically Acceptable evaluation with no tradeoffs permitted. Coded NAICS 238210 and PSC Y1NZ, the place of performance is Lake Tenkiller, Oklahoma.

The scope replaces three existing 15kV switchgear lineups serving generator breakers and station service transformer feeder breakers. Work includes removing the existing 500 kVA, 13.8 kV/480V station service transformer, the 15kV switchgear and breakers beneath the control room, and the 480V station service switchgear in the control room. It also covers removing 15kV cables, potheads, and asbestos cable trays containing 15kV cables in the cable tunnel. New installations include 15kV cables and potheads to the switchyard bus, new cable trays in the cable tunnel, front-accessible double-ended 480V switchgear beneath the control room with feeder circuit breakers, and 15kV switchgear with new vacuum circuit breakers and redundant 500 kVA, 13.8kV/480V high-resistance grounded wye station service equipment.

Notice text

2 versions

Update #2 · Latest ·

*This Pre-Solicitation Notice is being updated to notify industry that the solicitation number for this requirement has been updated to W912BV27RA003. The Solicitation has been posted on 27 OCT 2026. 

Pre-solicitation Notice

For

15kV Switchgear & Station Service Replacement

at Lake Tenkiller, OK

This is a PRE-SOLICITATION NOTICE for the construction of a 15kV Switchgear & Station Service Replacement at Lake Tenkiller, in Oklahoma. THIS IS NOT A SOLICITATION FOR PROPOSALS AND NO CONTRACT WILL BE AWARDED FROM THIS SYNOPSIS.  No reimbursement will be made for any costs associated with providing information in response to this pre-solicitation notice or any follow up postings.

The U.S. Army Corps of Engineers – Tulsa District has been tasked to solicit for and award a contract to perform the 15kV Switchgear & Station Service Replacement at Lake Tenkiller, Oklahoma. The proposed design-bid-build project will be procured as a Small Business Set-Aside, firm-fixed price contract in accordance with Revolutionary FAR Overhaul (RFO) Part 15, Negotiated Procurement, using the Lowest Price Technically Acceptable approach. Tradeoffs will not be permitted.

Project Description:

The work includes Replace the three existing 15kV switchgear lineups for the generator breakers and station service transformer feeder breakers.

  • Removal of existing 500 kVA, 13.8 kV/480V station service transformer
  • Removal of existing 15 kV switchgear and breakers located beneath control room
  • Removal of 480V station service switchgear in control room
  • Removal of the existing 15kV cables to the switchyard
  • Removal of existing potheads for the 15kV cable transition to switchyard bus
  • Removal of the existing asbestos cable trays containing 15kV cables in cable tunnel
  • Installation of new 15kV cables to the switchyard
  • Installation of new potheads for the 15kV cable transition to switchyard bus
  • Installation of new cable trays containing the new 15kV cables in cable tunnel
  • Installation of front accessible double-ended 480V switchgear beneath control room with feeder

circuit breakers

  • Installation of 15kV switchgear with new vacuum circuit breakers and redundant 500 kVA

13.8kV/480V, high-resistance grounded wye station service transformers

  • Reconfiguration of project diesel generator to wye-grounded with high-resistance grounding

resistor.

  • New control and annunciation wiring for new 480V and 15kV switchgear where existing cables

are not reused.

  • Modifications to protective relay settings and new protection relays for the new station service

feeders.

  • Automatic transfer functionality for the 480V switchgear main & tie breakers, along with local arc

flash mitigation switches.

  • Replacement and relocation of existing Lighting Transformer

The estimated magnitude of construction for this project is between $5,000,000 and $10,000,000.

The North American Industrial Classification System (NAICS) Code for this procurement is 238210, Electrical Contractors and Other Wiring Installation Contractors, which has a small business size standard of $19M.

The Product Service Code is: Y1NZ (Construction of Other Utilities)

Estimated duration of construction of this project is 900 calendar days.

Anticipated solicitation issuance date is on or about 20 July 2026, and the estimated proposal due date will be on or about 19 August 2026.

Update #1 ·

Pre-solicitation Notice

For

15kV Switchgear & Station Service Replacement

at Lake Tenkiller, OK

This is a PRE-SOLICITATION NOTICE for the construction of a 15kV Switchgear & Station Service Replacement at Lake Tenkiller, in Oklahoma. THIS IS NOT A SOLICITATION FOR PROPOSALS AND NO CONTRACT WILL BE AWARDED FROM THIS SYNOPSIS.  No reimbursement will be made for any costs associated with providing information in response to this pre-solicitation notice or any follow up postings.

The U.S. Army Corps of Engineers – Tulsa District has been tasked to solicit for and award a contract to perform the 15kV Switchgear & Station Service Replacement at Lake Tenkiller, Oklahoma. The proposed design-bid-build project will be procured as a Small Business Set-Aside, firm-fixed price contract in accordance with Revolutionary FAR Overhaul (RFO) Part 15, Negotiated Procurement, using the Lowest Price Technically Acceptable approach. Tradeoffs will not be permitted.

Project Description:

The work includes Replace the three existing 15kV switchgear lineups for the generator breakers and station service transformer feeder breakers.

  • Removal of existing 500 kVA, 13.8 kV/480V station service transformer
  • Removal of existing 15 kV switchgear and breakers located beneath control room
  • Removal of 480V station service switchgear in control room
  • Removal of the existing 15kV cables to the switchyard
  • Removal of existing potheads for the 15kV cable transition to switchyard bus
  • Removal of the existing asbestos cable trays containing 15kV cables in cable tunnel
  • Installation of new 15kV cables to the switchyard
  • Installation of new potheads for the 15kV cable transition to switchyard bus
  • Installation of new cable trays containing the new 15kV cables in cable tunnel
  • Installation of front accessible double-ended 480V switchgear beneath control room with feeder

circuit breakers

  • Installation of 15kV switchgear with new vacuum circuit breakers and redundant 500 kVA

13.8kV/480V, high-resistance grounded wye station service transformers

  • Reconfiguration of project diesel generator to wye-grounded with high-resistance grounding

resistor.

  • New control and annunciation wiring for new 480V and 15kV switchgear where existing cables

are not reused.

  • Modifications to protective relay settings and new protection relays for the new station service

feeders.

  • Automatic transfer functionality for the 480V switchgear main & tie breakers, along with local arc

flash mitigation switches.

  • Replacement and relocation of existing Lighting Transformer

The estimated magnitude of construction for this project is between $5,000,000 and $10,000,000.

The North American Industrial Classification System (NAICS) Code for this procurement is 238210, Electrical Contractors and Other Wiring Installation Contractors, which has a small business size standard of $19M.

The Product Service Code is: Y1NZ (Construction of Other Utilities)

Estimated duration of construction of this project is 900 calendar days.

Anticipated solicitation issuance date is on or about 20 July 2026, and the estimated proposal due date will be on or about 19 August 2026.

Notice history

Notice Type Posted
This notice Latest pre-solicitation Pre-Solicitation
15kV Switchgear & Station Service Replacement at Lake Tenkiller, OK Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Tenkiller 15KV switchgear and station service replacement NAICS 238210 ENDIST Tulsa Total Small Business
Tenkiller Hydropower Excitation System Replacement Gore, Oklahoma, United States · NAICS 237990 ENDIST Tulsa No set-aside
Webbers Falls Excitation System Replacements NAICS 237990 ENDIST Tulsa No set-aside
Switchgear Transformer Replacement 57330 Mustang Dr Bldg 42 Mcconnellafb, KS 67221, United States · NAICS 335311 Army National Guard Total Small Business