This is a project specification document prepared by the Washington State Department of Transportation (WSDOT) Olympic Region for the SR 510 & I-5 Yelm Loop Oak and Gopher Mitigation project (Contract No. 25C510) located in Thurston County, Washington. The project involves implementing a comprehensive mitigation strategy to compensate for habitat losses caused by roadway improvements on SR 510 Spur (MP 13.61 to MP 13.98) and I-5 (MP 91.52 to MP 91.75). The work includes establishing, enhancing, and preserving approximately 1.71 acres of Oregon White Oak Woodland habitat across two mitigation sites in Thurston County, as well as maintaining prairie habitat for the Yelm Pocket Gopher species. The project encompasses clearing and grubbing, selective vegetation removal with herbicide application, soil decompaction, biotic soil amendment installation, culvert installation, erosion and sediment control, roadside restoration with native seed establishment, and five years of monitoring. Bids are scheduled to open on Wednesday, September 30, 2026, at 11:00:59 A.M. Pacific Time, with proposals to be submitted electronically via BidExpress to the WSDOT address in Tumwater, Washington. The contractor must commence work on or before December 1, 2026, and complete the project within 85 working days, with liquidated damages assessed at $1,000 per working day for non-completion.
The contract requires a Commercial General Liability insurance policy with minimum limits of $1,000,000 per occurrence. The contractor must secure a Right of Way Permit from Thurston County before performing work within county right-of-way and will be responsible for all associated permit costs. All project documentation must be submitted electronically through the WSDOT Unifier system, with contractor personnel requiring access to submit a Unifier Access Request Form within five days of contract award. The contractor must participate in a Project Partnering workshop, with costs for the partnering facilitator, facilities, and materials reimbursed at 50 percent by WSDOT. Coordination is required with concurrent projects including the SR 507/Vail Road SE Intersection Compact Roundabout Project, SR 510 Spur/Yelm Loop ITS, Fiber & VMS project, SR 507/Bald Hills Road and Morris Road Roundabout, City of Yelm Rhoton Road NW Reconstruction, and SR 510/Yelm Loop New Alignment Phase 2. The project is governed by the 2026 Standard Specifications for Road, Bridge, and Municipal Construction and includes provisions for nondiscrimination compliance with Title VI of the Civil Rights Act and other federal civil rights authorities. Subcontractors and lower-tier subcontractors must have their payments reported through WSDOT's Diversity Management and Compliance System, with reporting required by the 20th of each month for payments made in the previous month.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Construction of:
A STATE PROJECT
Washington State1 Department of Transportation 2 Olympia, Washington 98504 3
SR 510 & I-56
YELM LOOP7
OAK AND GOPHER MITIGATION 8
25C510 9
THURSTON COUNTY10
Notice to All Planholders14 The Engineer assigned to answer questions regarding these bid documents, show 15 this project to prospective bidders, and act as the Contracting Agency’s 16 representative who directly supervises the engineering and administration of this 17 project is: 18
Casey Fraisure, P.E.21 7407 31st Ave NE22 Lacey, WA 9851623 Phone: (360) 357-2623 24 Email: casey.fraisure@wsdot.wa.gov 25
Troy Cowan, P.E. 30
Olympic Region Administrator 31
As the Engineer in direct responsible charge of developing these contract provisions, 35 I certify these provisions have been developed or incorporated into this project under 36 my supervision or as a result of certified specifications provided by other licensed 37 professionals. 38
SR 510 & I-5
YELM LOOP
OAK AND GOPHER MITIGATION
25C510 A
CONTENTS 1
INTRODUCTION--------------------------------------------------------------------------------------- 1 5
SPECIAL PROVISIONS 6
DIVISION 1 7
GENERAL REQUIREMENTS 8
DESCRIPTION OF WORK -------------------------------------------------------------------------- 1 9 BID PROCEDURES AND CONDITIONS -------------------------------------------------------- 1 10 Examination of Plans, Specifications and Site of Work ------------------------------------ 2 11 General ------------------------------------------------------------------------------------------------ 2 12 Preparation of Proposal ---------------------------------------------------------------------------- 2 13 Delivery of Proposal -------------------------------------------------------------------------------- 2 14 Public Opening of Proposals --------------------------------------------------------------------- 2 15 Date Of Opening Bids ------------------------------------------------------------------------------ 2 16 SCOPE OF THE WORK ----------------------------------------------------------------------------- 3 17 Coordination of Contract Documents, Plans, Special Provisions, Specifications, and 18
Addenda -------------------------------------------------------------------------------------------- 3 19 Procedure, Protest, and Dispute by the Contractor ----------------------------------------- 3 20 CONTROL OF WORK -------------------------------------------------------------------------------- 5 21 Cooperation with Other Contractors ------------------------------------------------------------ 5 22 Other Contracts Or Other Work ------------------------------------------------------------------ 5 23 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC ------------------------- 5 24 Environmental Regulations ----------------------------------------------------------------------- 5 25 Air Quality --------------------------------------------------------------------------------------------- 5 26 Asbestos Containing Material -------------------------------------------------------------------- 5 27 Load Limits -------------------------------------------------------------------------------------------- 5 28 High-Visibility Apparel ------------------------------------------------------------------------------ 6 29 Traffic Control Personnel -------------------------------------------------------------------------- 6 30 Requirements For Nondiscrimination ----------------------------------------------------------- 6 31 Regulatory Authorities ------------------------------------------------------------------------------ 6 32 Nondiscrimination Authorities --------------------------------------------------------------------- 6 33 Temporary Water Pollution Prevention --------------------------------------------------------- 7 34 Spill Prevention, Control, and Countermeasures Plan ------------------------------------- 7 35
PAGE
OAK AND GOPHER MITIGATION
25C510 B
Protection And Restoration Of Property -------------------------------------------------------- 8 1 Vegetation Protection and Restoration --------------------------------------------------------- 8 2 Utilities and Similar Facilities --------------------------------------------------------------------- 8 3 Public Liability And Property Damage Insurance -------------------------------------------- 9 4 Required Insurance Policies ---------------------------------------------------------------------- 9 5 Rights Of Way -------------------------------------------------------------------------------------- 10 6 PROSECUTION AND PROGRESS ------------------------------------------------------------- 10 7 Subcontracting ------------------------------------------------------------------------------------- 10 8 Subcontractor Approval -------------------------------------------------------------------------- 10 9 Payments to Subcontractors and Lower-Tier Subcontractors -------------------------- 10 10 Payment Reporting ------------------------------------------------------------------------------- 10 11 Submittal of Executed Subcontracts ----------------------------------------------------------- 11 12 Prosecution Of Work ------------------------------------------------------------------------------ 11 13 Time For Completion ------------------------------------------------------------------------------ 11 14 Liquidated Damages ------------------------------------------------------------------------------- 11 15
DIVISION 3 16
EARTHWORK 17
Clearing, Grubbing, and Roadside Cleanup ------------------------------------------------- 11 18 Description ------------------------------------------------------------------------------------------- 11 19 Disposal of Usable Material and Debris ------------------------------------------------------ 12 20 Construction Requirements --------------------------------------------------------------------- 12 21 Clearing ---------------------------------------------------------------------------------------------- 12 22 Selective Clearing and Grubbing -------------------------------------------------------------- 13 23 Measurement --------------------------------------------------------------------------------------- 13 24 Payment --------------------------------------------------------------------------------------------- 13 25 Removal of Structures and Obstructions ---------------------------------------------------- 14 26 Construction Requirements --------------------------------------------------------------------- 14 27 Removal and Disposal of Asbestos Material ------------------------------------------------ 14 28
DIVISION 7 29
DRAINAGE STRUCTURES, STORM SEWERS, SANITARY 30
SEWERS, WATER MAINS, AND CONDUITS 31
CULVERT PIPE -------------------------------------------------------------------------------------- 15 32
PAGE
OAK AND GOPHER MITIGATION
25C510 C
DIVISION 8 1
MISCELLANEOUS CONSTRUCTION 2
EROSION CONTROL AND WATER POLLUTION CONTROL --------------------------- 15 3
Construction Requirements --------------------------------------------------------------------- 15 4 General ---------------------------------------------------------------------------------------------- 15 5 ROADSIDE RESTORATION ---------------------------------------------------------------------- 16 6 Seeding, Fertilizing, and Mulching ------------------------------------------------------------ 16 7 Roadside Seeding, Lawn and Planting Area Preparation -------------------------------- 17 8
DIVISION 9 9
MATERIALS 10
APPENDICES ---------------------------------------------------------------------------------------- 21 11 STANDARD PLANS --------------------------------------------------------------------------------- 21 12 SR 510/Yelm Loop - New Alignment Phase 2 Oak Mitigation 13
OAK AND GOPHER MITIGATION
25C510 1
INTRODUCTION 1
This Contract shall be constructed in accordance with the 2026 Standard Specifications for 3 Road, Bridge, and Municipal Construction. 4
SPECIAL PROVISIONS 6
Several types of Special Provisions are included in this contract; General, Region, Bridges 8 and Structures, and Project Specific. Special Provisions types are differentiated as follows: 9
(date) General Special Provision 11 (******) Notes a revision to a General Special Provision 12 and also notes a Project Specific Special 13 Provision. 14 (Regions1 date) Region Special Provision 15
General Special Provisions are similar to Standard Specifications in that they typically apply 17 to many projects, usually in more than one Region. Usually, the only difference from one 18 project to another is the inclusion of variable project data, inserted as a “fill-in”. 19 Region Special Provisions are commonly applicable within the designated Region. Region 21 designations are as follows: 22
Regions1 24 ER Eastern Region 25 NCR North Central Region 26 NWR Northwest Region 27 OR Olympic Region 28 SCR South Central Region 29 SWR Southwest Region 30 WSF Washington State Ferries Division 32
Project Specific Special Provisions normally appear only in the contract for which they were 34 developed. 35
Division 1 37 General Requirements 38
DESCRIPTION OF WORK 40
(March 13, 1995) 42 This Contract provides for the improvement of *** SR 510 Spur from MP 13.61 to MP 13.98 in 43 Thurston county and I-5 from MP 91.52 to MP 91.75 in Thurston county, by implementing a 44 mitigation strategy to compensate for the loss of oak habitat via establishing, enhancing, and 45 preserving Oak Woodland areas and also aims to offset the loss of suitable habitat for the 46 Yelm Pocket Gopher species by maintaining a site dedicated to preservation of the prairie 47 habitat *** and other work, all in accordance with the attached Contract Plans, these Contract 48 Provisions, and the Standard Specifications. 49 Bid Procedures and Conditions 51
OAK AND GOPHER MITIGATION
25C510 2
Examination of Plans, Specifications and Site of Work 1
General 3
Section 1-02.4(1) is supplemented with the following: 5
(September 3, 2019) 7 The Reference Information for this project is available for review by the bidder at the 8 following location: 9
*** 11 https://ftp.wsdot.wa.gov/contracts/ 12 *** 13
The Reference Information includes the following: 15
*** 17
1. CAD Files 18 *** 19
Preparation of Proposal 21 (November 20, 2023) 23 The fourth and fifth paragraphs of Section 1-02.6 are deleted. 24 Delivery of Proposal 26 The first paragraph of Section 1-02.9 is revised to read: 28
(April 9, 2026) 30 For projects scheduled for Bid opening in Olympia, the Proposal shall be sealed and 31 submitted in the envelope provided with it to the address provided below or shall be 32 submitted electronically via Bidx.com through AASHTOWare Project Bids™ software 33 “BidExpress®.” The Bidder shall fill in all blanks on this envelope to ensure proper 34 handling and delivery. Bids are to be received no later than 11:00:59 A.M. Pacific time on 35 the date of Bid opening: 36
Washington State Department of Transportation 38 Room A101 39 1655 2nd Ave SW 40 Tumwater WA 98512 41
Public Opening of Proposals 43 Section 1-02.12 is supplemented with the following: 45
(August 3, 2015) 47 Date of Opening Bids 48 The bid opening date for this project is *** Wednesday September 30, 2026 *** Bids 49 received will be publicly opened and read after 11:00:59 A.M. Pacific Time on this date. 50 https://ftp.wsdot.wa.gov/contracts/
OAK AND GOPHER MITIGATION
25C510 3
Scope of the Work 1 Coordination of Contract Documents, Plans, Special Provisions, 3 Specifications, and Addenda 4 Section 1-04.2 is supplemented with the following: 6
(November 20, 2023) 8 Document Control 9 This specification applies to project documentation and correspondence that occurs after 10 execution of the Contract. The Contractor shall submit all project documentation and 11 correspondence for this Contract in electronic format utilizing the WSDOT Unifier system. 12 Documents that are received by means other than the WSDOT Unifier system will be 13 rejected, except as allowed by this special provision or specifically approved by the 14 Engineer. 15 The Engineer may reject documents that are deemed unsuitable. This includes 17 documents that are illegible, unreadable, locked, etc. Forms that require further 18 information from WSDOT must be unlocked. 19 The Contractor shall submit to the Contracting Agency a Unifier Access Request Form 21 (WSDOT Form 134-092) to WSDOT e-Construction Support (e-22 ConstructionSupport@wsdot.wa.gov) designating all individuals requiring access to 23 WSDOT Unifier no later than 5 days following Contract Award. Training for WSDOT 24 Unifier will be provided by WSDOT at no cost to the Contractor. Throughout the life of the 25 Project, all changes to the Contractor’s personnel who require access to the WSDOT 26 Unifier system shall be submitted on a Unifier Access Request Form. 27 All signed documents shall be in PDF format and will require an electronic signature. An 29 electronic signature is defined as a symbol, or process attached to or logically associated 30 with a record and executed or adopted by a person with the intent to sign the record. All 31 signed documents shall be in PDF format. 32 WSDOT has provided an application to be used to apply electronic signatures to the 34 following documents: 35
Change Orders that are not Minor Change Orders 37 421-009 Release – Retained Percentage (Except Landscaping) 38 134-146 Final Contract Voucher Certificate 39
When the Contract specifies that documentation is to be submitted through other web-41 based systems, such as the Diversity Management and Compliance System, or email 42 addresses, the Contractor shall utilize those systems and email addresses accordingly. 43 Before a Completion Date will be established by the Contracting Agency, all contractor 45 active tasks in Unifier shall be closed out or acknowledged. 46 All costs for submitting project documentation electronically shall be included in the 48 Contract prices for the Bid items of Work involved. 49
Procedure, Protest, and Dispute by the Contractor 51 mailto:e-ConstructionSupport@wsdot.wa.gov mailto:e-ConstructionSupport@wsdot.wa.gov
OAK AND GOPHER MITIGATION
25C510 4
Section 1-04.5 is supplemented with the following: 1
(March 9, 2026) 3 Project Partnering 4 The Engineer and the Contractor’s Project Manager (PM) will plan and host a Project 5 Partnering workshop as soon as practical after Contract execution. The objective of this 6 Partnering workshop is to promote open lines of communication and teamwork between 7 the Contracting Agency and Contractor staff for the effective completion of the work, and 8 to the standard of quality that will be a source of pride to both the Contracting Agency and 9 the Contractor. Commitments made by both parties shall be memorialized in a Project 10 Partnering Agreement at the conclusion of the Partnering workshop. The Partnering 11 agreement will not affect the terms of the Contract. It is intended only to establish an 12 environment of cooperation and mutual understanding between the parties. 13 The planning and execution of the Partnering process is intended to be a collaborative 15 effort between the Engineer and the PM. The length of the partnering workshop should 16 be commensurate with the size and complexity of the project, and familiarity of the parties. 17 For simple projects an expanded pre-construction meeting may suffice. The partnering 18 workshop may be facilitated by the Engineer, the Engineer and PM, or a mutually 19 agreeable Partnering Facilitator (PF). Selection of a PF, dates and location of the 20 workshops, materials needed for the workshop, frequency and location for follow up 21 meetings, and estimated cost associated with this effort should be discussed and agreed 22 to prior to moving forward with the Partnering process. 23 An initial 1 day (or half day) facilitated Project Partnering workshop is recommended to 25 initiate the partnering agreement. 26 The cost to retain the services of a Partnering Facilitator (if mutually selected as the PF), 28 locate and rent a neutral location to hold the workshop (if held offsite), and any additional 29 materials needed to host the workshop, will be paid by the Contractor. The Partnering 30 Field Guide is available as a resource to the Engineer and PM to assist in the planning of 31 the Partnering session(s) at the following link: 32 https://wsdot.wa.gov/publications/fulltext/construction/WSDOTProjects-Partnering-34 FieldGuide.pdf 35
The Contracting Agency will reimburse invoice cost for the Contractor provided Partnering 37 Facilitator, facilities and materials at a rate of 50% under the Bid item, “Project Partnering”. 38 After the initial Partnering workshop, quarterly follow-up meetings on projects with over 40 120 working days shall be scheduled to evaluate how the Partnering process is working, 41 acknowledge successes and opportunities for improvement. 42 When the Project Engineer and Contractor’s Project Manager have determined 44 recognition is warranted, the cost for meals and awards for recognition of project 45 partnering success shall be borne by each party. Expenses shall be divided such that 46 each party pays for their pro rata share of the expenses based on the number of people 47 receiving the meal or award. Reimbursement for expenses initially paid by one party will 48 be made to the other party under the Bid item, “Project Partnering”. 49 Payment 51 “Project Partnering”, by calculation. 52 https://wsdot.wa.gov/publications/fulltext/construction/WSDOTProjects-Partnering-FieldGuide.pdf https://wsdot.wa.gov/publications/fulltext/construction/WSDOTProjects-Partnering-FieldGuide.pdf
OAK AND GOPHER MITIGATION
25C510 5
“Project Partnering” will be calculated and paid for as described above. 1 Control of Work 3 Cooperation with Other Contractors 5 Section 1-05.14 is supplemented with the following: 7
(March 13, 1995) 9 Other Contracts Or Other Work 10 It is anticipated that the following work adjacent to or within the limits of this project will 11 be performed by others during the course of this project and will require coordination of 12 the work: 13
*** SR 507/Vail Rd SE Intersection – Compact Roundabout Project 15 Contact information: Marcus Storvick – Marcus.Storvick@co.Thurston.WA.US 16 SR 510 Spur/Yelm Loop – ITS, Fiber & VMS 17 Contact Information: Casey Fraisure – Casey.Fraisure@WSDOT.WA.gov 18 SR 507/Bald Hills Rd / Morris Rd Roundabout 19 Contact Information: Cody Colt – CodyC@YelmWA.gov 20 City of Yelm Rhoton Rd NW Reconstruction 21 Contact Information: Cody Colt – CodyC@YelmWA.gov 22 SR 510/Yelm Loop – New Alignment Phase 2 23 Contact Information: Casey Fraisure – Casey.Fraisure@WSDOT.WA.gov *** 24
Legal Relations and Responsibilities to the Public 26 Environmental Regulations 28
Air Quality 30
Asbestos Containing Material 32
Section 1-07.5(4)C is supplemented with the following: 34
(October 4, 2021) 36 Asbestos Good Faith Investigation 37 An asbestos Good Faith Investigation (GFI) has been conducted for this project 38 and it has been determined to a reasonable certainty that no known Asbestos 39 Containing Material (ACM) will be disturbed by the work on this project. The 40 asbestos GFI has been provided as Appendix *** B ***. 41
Load Limits 43 Section 1-07.7 is supplemented with the following: 45
(March 13, 1995) 47 If the sources of materials provided by the Contractor necessitates hauling over roads 48 other than State Highways, the Contractor shall, at the Contractor's expense, make all 49 arrangements for the use of the haul routes. 50
OAK AND GOPHER MITIGATION
25C510 6
High-Visibility Apparel 1
Traffic Control Personnel 3
Section 1-07.8(1) is revised to read: 5
(September 16, 2025) 7 All personnel performing the Work described in Section 2-04 (including traffic control 8 supervisors, flaggers, and others performing traffic control labor of any kind) shall 9 comply with the following: 10
1. During daylight hours with clear visibility, workers shall wear a high-visibility 12 ANSI/ISEA 107 Type R Class 2 or 3 garment with background material that 13 are fluorescent yellow-green, fluorescent orange-red, or fluorescent red in 14 color; and a high visibility hardhat that is white, yellow, yellow-green, 15 orange, or red in color; and 16
2. During hours of darkness (½ hour before sunset to ½ hour after sunrise) or 18 other low-visibility conditions (snow, fog, etc.), workers shall wear a high-19 visibility ANSI/ISEA 107 Type R Class 2 or 3 garment with background 20 material that are fluorescent yellow-green, fluorescent orange-red, or 21 fluorescent red in color; a high-visibility lower garment meeting ANSI/ISEA 22 107 Class E, and a high visibility hardhat marked with at least 12 square 23 inches of retroreflective material applied to provide 360 degrees of visibility. 24
Requirements for Nondiscrimination 26
Regulatory Authorities 28
Nondiscrimination Authorities 30
Section 1-07.11(1)C is revised to read: 32
(March 9, 2026) 34 During the performance of this Contract, the Contractor, for itself, its assignees, 35 and successors in interest agrees to comply with the following nondiscrimination 36 statues and authorities; including but not limited to: 37
1. Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 39 stat. 252), and its implementing regulations and case law, prohibit 40 discrimination on the basis of race, color, or national origin. 49 C.F.R. 41 21.5(b)(2) prohibits a recipient of federal funds from utilizing “criteria 42 or methods of administration which have the effect of subjecting 43 persons to discrimination because of their race, color, or national 44 origin, or have the effect of defeating or substantially impairing 45 accomplishment of the objectives of the program with respect to 46 individuals of a particular race, color, or national origin.” This includes 47 taking reasonable steps to provide limited English proficiency (LEP) 48 persons meaningful access to all programs, activities and services, 49 where necessary to avoid discrimination on the basis of national 50 origin. 51
OAK AND GOPHER MITIGATION
25C510 7
2. The Uniform Relocation Assistance and Real Property Acquisition 1 Policies Act of 1970, (42 U.S.C §4601), (prohibits unfair treatment of 2 persons displaced or whose property has been acquired because of 3 Federal or Federal-aid programs and projects). 4
3. Federal-Aid Highway Act of 1973, (23 U.S.C. § 324 et. seq.), as 6 amended, (prohibits discrimination on the basis of sex). 7
4. Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. § 794 et 9 seq.), as amended (prohibits discrimination on the basis of disability); 10 and 49 C.F.R. Part 27. 11
5. The Age Discrimination Act of 1975, as amended (42 U.S.C. § 6101 13 et seq.), (prohibits discrimination on the basis of age). 14
6. Airport and Airway Improvement Act of 1982, (49 U.S.C. § 471, 16
Section 47123), as amended, (prohibits discrimination based on race, 17 creed, color, national origin, or sex). 18
7. The Civil Rights Restoration Act of 1987, (PL 100-209), (Broadened 20 the scope, coverage and applicability of Title VI of the Civil Rights Act 21 of 1964, The Age of Discrimination Act of 1975 and Section 504 of the 22 Rehabilitation Act of 1973, by expanding the definition and terms 23 “programs or activities” to include all of the programs or activities of 24 the Federal-aid recipients, sub-recipients and contractors, whether 25 such programs or activities are Federally funded or not). 26
8. Titles II and III of the Americans with Disabilities Act, which prohibit 28 discrimination on the basis of disability in the operation of public 29 entities, public and private transportation systems, places of public 30 accommodation, and certain testing entities (42 U.S.C. § 12131-31 12189) as implemented by Department of Transportation regulations 32 at 49 C.F.R. parts 37 and 38. 33
9. The Federal Aviation Administration’s Nondiscrimination statute (49 35
U.S.C. § 47123), (prohibits discrimination on the basis of race, color 36 national origin, and sex). 37
10. Title IX of the Education Amendments of 1972, as amended, which 39 prohibits you from discriminating because of sex in education 40 programs or activities (20 U.S.C. 1681 et seq.). 41
Temporary Water Pollution Prevention 43
Spill Prevention, Control, and Countermeasures Plan 45
Section 1-07.15(1) is supplemented with the following: 47
(OR August 14, 2025) 49 The Contractor shall implement the spill prevention measures identified in the SPCC 50 Plan before performing any of the following activities: 51
OAK AND GOPHER MITIGATION
25C510 8
1. Placing materials or equipment in staging or storage areas 1
2. Refueling, washing or maintaining equipment 2
3. Stockpiling contaminated materials 3
Containment and cleanup efforts shall begin immediately and be completed as soon 5 as possible, taking precedence over normal work. Cleanup shall include proper 6 disposal of any spilled material and used cleanup materials. No emulsifiers or 7 dispersants are to be used in waters of the State without written approval from the 8 Department of Ecology. Concentrated waste or spilled chemicals shall be 9 transported off the site for disposal at a facility approved by the Department of 10 Ecology or local County Health Department. 11 Disposal 13 Spilled waste, chemicals or petroleum products shall be transported off site for 14 disposal at a facility approved by the Department of Ecology. The materials shall not 15 be discharged to any sanitary sewer without approval of the local sewer authority. 16
Protection and Restoration of Property 18
Vegetation Protection and Restoration 20
Section 1-07.16(2) is supplemented with the following: 22
(******) 24 Vegetation and soil protection zones for trees shall extend out from the trunk to a 25 distance of 1 foot radius for each inch of trunk diameter at breast height. 26 All Oregon White Oak trees shall be protected, regardless of size, with a protection 28 zone according to their trunk diameter at breast height, as described above, or a 29 minimum of 1 foot radius, whichever is larger. 30 Vegetation and soil protection zones for shrubs shall extend out from the stems at 32 ground level to twice the radius of the shrub. 33 Vegetation and soil protection zones for herbaceous vegetation shall extend to 35 encompass the diameter of the plant as measured from the outer edge of the plant. 36
Utilities and Similar Facilities 38 Section 1-07.17 is supplemented with the following: 40
(April 2, 2007) 42 Locations and dimensions shown in the Plans for existing facilities are in accordance with 43 available information obtained without uncovering, measuring, or other verification. 44 The following addresses and telephone numbers of utility companies known or suspected 46 of having facilities within the project limits are supplied for the Contractor's convenience: 47
*** 49 Astound Broadband 50 Attn: Klayton Pike 51 360-432-5296 52
OAK AND GOPHER MITIGATION
25C510 9 klayton.pike@astound.com 1
Comcast 3 Attn: Brian Hoback 4 253-254-1366 5 Brian_Hoback@comcast.com 6 Lightcurve 8 Attn: Brian Munson 9 253-312-2819 10 brian.munson@lightcurve.com 11 Olympic Pipeline 13 Attn: Chase Wakefield 14 425-981-2575 15 Chase.wakefield@bp.com 16 Puget Sound Energy - Gas 18 Attn: Tony Fay 19 253-213-2514 20 Tony.Fay@pse.com 21
Puget Sound Energy - Power 23 Attn: Brandon Joliff 24 Desk: 253-293-0532 25 Brandon.Joliff@pse.com 26 Bonneville Power Administration 28 Wendy Jansen 29 360-570-4332 30 wejansen@bpa.gov 31 *** 32
The second paragraph of Section 1-07.17 is supplemented with the following: 34
(OR August 14, 2025) 36 The Contractor shall contact the WSDOT Olympic Region Signal Superintendent to obtain 37 the locations of all Contracting Agency-owned utilities within the project limits. To request 38 utility locates, call 360-357-2669 during normal business hours (7:30 AM to 4:00 PM). 39
Public Liability and Property Damage Insurance 41
Required Insurance Policies 43
(September 7, 2021) 45 Item number 1 of Section 1-07.18(5) is deleted. 46
The first sentence of Item No. 2 of Section 1-07.18(5) is revised to read: 48
(September 7, 2021) 50 mailto:Tony.Fay@pse.com
OAK AND GOPHER MITIGATION
25C510 10
2. Commercial General Liability (CGL) Insurance written under ISO Form CG0001 1 with minimum limits of $1,000,000 per occurrence and in the aggregate for each 2 one-year policy period. 3
Rights of Way 5 Section 1-07.24 is supplemented with the following: 7 (******) 9 Thurston County Right of Way Permit 10 The Contractor shall apply for and receive a Right of Way Permit from Thurston County before 11 performing any Work within Thurston County right of way. The Contractor shall be responsible 12 for all costs associated with receiving this permit. The Thurston County properties are located 13 on both gopher mitigation sites, and the permit applies to the driveway work. 14 Upon acceptance of the permit by Thurston County, a copy of the permit shall be provided to 16 the Engineer. 17 The permit application can be found at the following link: 19 https://www.thurstoncountywa.gov/departments/community-planning-and-economic-20 development/permitting/permits-fees-forms/permit-applications-forms. 21 Prosecution and Progress 23 Subcontracting 25
Subcontractor Approval 27
The second sentence in the first paragraph of Section 1-08.1(3) is revised to read: 29
(November 4, 2024) 31 Each request to subcontract shall be submitted through Unifier, Request to Sublet. 32
Payments to Subcontractors and Lower-Tier Subcontractors 34
Payment Reporting 36
Section 1-08.1(7)A is revised to read: 38
(March 9, 2026) 40 The Contractor shall report the actual amounts paid to all firms that were used 41 as subcontractors of any tier, materials suppliers, manufacturers, regular 42 dealers, or service providers on the Contract including all Disadvantaged, 43 Minority, Small, Veteran, or Women’s Business Enterprise firms. The following 44 do not need reported: (1) retail sales or services that are paid for at the time of 45 purchase; (2) payments to materials suppliers or manufacturers that are in 46 normal course of business unless it is to a Disadvantaged, Minority, Small, 47 Veteran, or Women’s Business Enterprise firm in accordance with Section 1-48
07.11. The Contractor shall report this information by entering it into the 49 Contracting Agency’s Diversity Management and Compliance System at: 50 https://wsdot.diversitycompliance.com. Payments shall be reported no later than 51 the 20th of the month for all payments made to firms the previous calendar 52 https://www.thurstoncountywa.gov/departments/community-planning-and-economic-development/permitting/permits-fees-forms/permit-applications-forms https://www.thurstoncountywa.gov/departments/community-planning-and-economic-development/permitting/permits-fees-forms/permit-applications-forms
OAK AND GOPHER MITIGATION
25C510 11 month. For example, the Contractor shall enter all payments made to firms 1 during the month of March into DMCS by April 20th. Payments shall be reported 2 between execution of the Contract and the Contract Completion Date. When no 3 Work occurred or no payments were made for a firm, the reported payment shall 4 be zero. 5 The Contractor shall require all recipients of such payments to use DMCS to 7 acknowledge their receipt of payment. 8
Submittal of Executed Subcontracts 10
The last sentence of Section 1-08.1(9) is revised to read: 12
(May 5, 2025) 14 The executed subcontracts shall be submitted with the Request to Sublet, through 15 Unifier. 16
Prosecution of Work 18 The first sentence of Section 1-08.4 is revised to read: 20
(August 3, 2015) 22 The Contractor shall commence onsite work on or before *** December 1, 2026 *** and 23 shall notify the Engineer in writing a minimum of 10 calendar days in advance of the date 24 on which the Contractor intends to begin work. 25
Time for Completion 27 Section 1-08.5 is supplemented with the following: 29
(December 4, 2006) 31 This project shall be physically completed within *** 85 *** working days. 32 Contract time shall begin on the first working day the Contractor starts onsite work or *** 34 December 1, 2026 ***, whichever occurs first. 35
Liquidated Damages 37 Section 1-08.9 is supplemented with the following: 39
(September 8, 2020) 41 Liquidated damages in the amount of *** $1,000 *** per working day will be assessed for 42 failure to physically complete the Contract within the physical completion time specified. 43
Division 3 45 Earthwork 46
Clearing, Grubbing, and Roadside Cleanup 48 Description 50
OAK AND GOPHER MITIGATION
25C510 12
Section 3-01.1 is supplemented with the following: 1
(******) 3 Herbicide Application Prior to Selective Clearing and Grubbing 4 This Work includes the application of herbicide to selective clearing and grubbing areas 5 prior to selective clearing and grubbing to accommodate the Work and preserve 6 vegetation. 7
Disposal of Usable Material and Debris 9 Section 3-01.2 supplemented with the following: 11
(******) 13 All debris from the selective clearing and grubbing shall be physically removed from the 14 project in accordance with Disposal Method No. 2. Disposal Method No. 3 will not be 15 allowed on this project. 16
Construction Requirements 18
Clearing 20 Section 3-01.3(1) is supplemented with the following: 22
(******) 24 Herbicide Application Prior to Selective Clearing and Grubbing 25 The Contractor shall treat the living unwanted vegetation within selective clearing and 26 grubbing limits or where shown in the Plans as defined below. Treatment shall be with 27 an approved selective broadleaf herbicide two times prior to vegetation and soil 28 disturbance within the specified site. 29
Unwanted Vegetation 31 In addition to noxious weeds, unwanted vegetation within mitigation areas throughout 32 the project limits includes: 33
• Scotch broom (Cytisus scoparius) 35
• Butterfly bush (Buddleia spp.) 36
• Canadian thistle (Cirsium arvense) 37
• Evergreen blackberry (Rubus laciniatus) 38
• Hedge bindweed (Calystegia sepium) 39
• Himalayan blackberry (Rubus discolor or R. procerus) 40
• Purple loosestrife (Lythrum salicaria) 41
The Contractor shall include the proposed timing of this Work in the progress schedule in 43 accordance with Section 1-08.3. The Contractor shall submit the Weed and Pest Control 44 Plan as specified in Section 8-02.3(2)B prior to beginning this Work. 45
Between October 1 and March 31, the Contractor shall perform a foliar application of the 47 approved selective broadleaf herbicide. Two weeks after the first herbicide application, 48 the Contractor shall cut and clear dead vegetation to ground level and dispose of it outside 49 of the project limits. 50
OAK AND GOPHER MITIGATION
25C510 13
Six weeks after cutting and clearing or when the vegetation has regrown to a minimum of 1 six inches in height, whichever comes first, the Contractor shall spot spray any areas that 2 survived previous herbicide application and cutting. Two weeks or more after the second 3 herbicide application, the Contractor shall perform selective clearing and grubbing. 4 Herbicide applications shall be performed in accordance with the requirements of Section 6 8-02.3(3) and the approved Weed and Pest Control Plan. Herbicide shall not be applied 7 during windy or rainy weather, or when rain is forecast. 8
Care shall be taken to prevent herbicide damage to existing vegetation identified to be 10 saved and protected as shown in the Plans. 11
(******) 13 The Contractor shall protect the root systems of the existing vegetation designated to be 14 saved during selective clearing and grubbing activities. The Contractor shall conduct 15 operations so vehicles and equipment do not operate, haul, park, or perform other 16 activity within the drip line of vegetation designated to be saved. Trees identified for 17 removal shall be felled into areas of existing forest cover. Contractor shall not proceed 18 with clearing activities until directed by the Engineer. 19
(******) 21 Work performed by the Contractor in all sensitive areas shall be completed with 22 equipment exerting a ground pressure of less than 5 p.s.i. The Contractor shall be 23 required to submit a Type 1 Drawing to verify the 5 p.s.i. ground pressure. 24
(******) 26 Selective Clearing and Grubbing 27 The Contractor shall selectively clear and grub unwanted vegetation within the existing 28 desirable vegetation at the locations shown in the Plans. Unwanted vegetation shall 29 include all grasses and non-native vegetation. 30 The Contractor shall exercise care to not damage existing desirable vegetation. Work 32 shall only commence when each day's activity has been reviewed and approved on site 33 by the Engineer. 34 The Contractor shall remove or dispose of the debris in accordance with Section 3-01.2. 36
Measurement 38 Section 3-01.4 is supplemented with the following: 40
(******) 42 Herbicide will be measured by the acre by ground slope measurement. 43
(******) 45 Selective Clearing and Grubbing will be measured by the acre by ground slope 46 measurement. 47
Payment 49 Section 3-01.5 is supplemented with the following: 51
OAK AND GOPHER MITIGATION
25C510 14
(******) 1 “Herbicide”, per acre. 2 The unit Contract price for “Herbicide”, per acre shall be full payment for performing the 4 Work as specified, including “Herbicide Application Prior to Selective Clearing and 5 Grubbing”. 6
(******) 8 “Selective Clearing and Grubbing”, per acre. 9 The unit Contract price for “Selective Clearing and Grubbing”, per acre shall be full 11 payment for performing the Work as specified, including “Herbicide Application Prior to 12 Selective Clearing and Grubbing”, and all disposal fees incurred in the removal and 13 disposal of all unwanted vegetation. 14
Removal of Structures and Obstructions 16 Construction Requirements 18 Section 3-02.3 is supplemented with the following: 20
(October 4, 2021) 22 Removal and Disposal of Asbestos Material 23 In the event suspected Asbestos Containing Material (ACM) is encountered, the 24 Contractor shall immediately notify the Engineer and the provisions of Section 1-04.7 shall 25 apply. Prior to commencing asbestos related work, the Contractor shall obtain all permits 26 from and provide notification to, the Washington State Department of Labor and 27 Industries, the Washington State Department of Ecology, the local clean air agency, and 28 other permitting and regulatory agencies with jurisdiction over the work involving asbestos 29 as the laws, rules, and regulations require. 30 The ACM shall only be disturbed under the supervision of a Washington State Certified 32 Asbestos Supervisor (CAS). The CAS shall be certified in accordance with WAC 295-65-33
012. 34 The CAS shall supervise the asbestos removal and ensure that the handling and removal 36 of asbestos is accomplished by certified asbestos workers and in accordance with 37 Washington State Department of Labor and Industries standards. The Contractor shall 38 ensure that the removal and disposal of asbestos meets the requirements of EPA 39 regulation 40 CFR Part 61, local health department regulations, and all other applicable 40 regulations. 41 No asbestos is expected to be encountered. However, if the Contractor believes they 43 have encountered asbestos, they shall immediately notify the Engineer in accordance 44 with Section 1-04.7. 45
Division 7 47
Drainage Structures, Storm Sewers, Sanitary 48 Sewers, Water Mains, and Conduits 49
OAK AND GOPHER MITIGATION
25C510 15
Culvert Pipe 1 (******) 3 Buried Culvert 4 Description 6 This Work consists of excavation, adding bedding material and installing a buried culvert at 7 the location staked by the Contracting Agency prior to the Contractor beginning Work. 8 Materials 10 Materials shall be in accordance with section 7-02.2 and meet the requirements of the 11 following sections: 12 Quarry Spalls 9-13.1(5) 14 Gravel Backfill for Pipe Zone Bedding 9-03.12(3) 15 High-Density Polyethylene (HDPE) Pipe 9-05.23 16 Construction Requirements 18 The Contractor shall excavate below the existing ditch to install the culvert pipe with 3” of 19 bedding material underneath the culvert. The culvert shall match the elevations of the existing 20 ditch. Cover and compaction over top of the culvert shall be done with gravel backfill for pipe 21 zone bedding or equivalent material. 22 Measurement 24 The buried culvert contains the following approximate quantities of materials and work: 25 Quarry Spalls - 2 C.Y. 26 Gravel Backfill for Pipe Zone Bedding - 5 C.Y. 27 High Density Polyethylene Pipe 18 In. Diameter - 20 L.F. 28 Excavation – 1 C.Y. 29 Payment 32 “Buried Cuvert”, lump sum. 33 The lump sum Contract payment shall be full compensation for all costs incurred by the 34 Contractor in performing the Work as specified. 35
Division 8 37 Miscellaneous Construction 38
Erosion Control and Water Pollution Control 40 Construction Requirements 42
General 44
Submittals 46
Section 8-01.3(1)A is supplemented with the following: 48
(OR August 14, 2025) 50 A temporary erosion and sediment control (TESC) narrative is included in the 51 Appendix of these provisions and is made part of the contract. 52
OAK AND GOPHER MITIGATION
25C510 16
Roadside Restoration 2
Seeding, Fertilizing, and Mulching 4
Seeding and Fertilizing 6
Section 8-02.3(9)B is supplemented with the following: 8
(******) 10 Grass seed, of the following composition, proportion, and quality shall be applied at 11 the rate of 48 pounds per acre on all areas requiring Seeding and Fertilizing. 12
Common Name Pounds Pure Live Seed 14 (Botanical Name) (PLS) by Weight 15 Common Yarrow 16 (Achillea millefolium) 0.12 17 Red Columbine 19 (Aquilegia formosa) 1.64 20 Harsh Indian Paintbrush 22 (Castilleja hispida) 2.48 23 Farewell to Spring 25 (Clarkia amoena) 1.0 26 Large Flower Blue Eyed Mary 28 (Collinsia grandiflora) 4.75 29 Maiden Blue Eyed Mary 31 (Collinsia parviflora) 2.05 32 Grand Collomia 34 (Collomia grandiflora) 4.75 35 Poverty Oatgrass 37 (Danthonia spicata) 17.15 38 Roemer’s Fescue 40 (Festuca roemerii) 13.63 41 Bird’s Eye Gilia 43 (Gilia tricolor) 0.43 44 Total Pounds PLS Per Acre 48 46 Non-Source Identified seed shall meet or exceed Washington State Department of 48 Agriculture Certified Seed Standards and be from within the appropriate genetic 49 zones of the Puget Lowland Ecoregion(s) as defined by the US Environmental 50 Protection Agency (EPA). 51
OAK AND GOPHER MITIGATION
25C510 17
The seed certification class shall be Certified (blue tag) in accordance with WAC 1 16-302 and meet the following requirements: 2 Prohibited Weed 0% max 4 Noxious Weed 0% max 5 Other Weed 0.2% max 6 Other Crop 0.4% max 7 The Contractor shall document all Source Identified seed by providing the 9 Association of Official Seed Certifying Agents (AOSCA) yellow seed label for each 10 species in the mix. Site Identification Logs can be supplied for collections where 11 the AOSCA yellow label is not available. 12
Roadside Seeding, Lawn and Planting Area Preparation 14
Section 8-02.3(5) is supplemented with the following: 16
(August 5, 2013) 18 After initial area weed control, grading, and soil placement are completed, all soil 19 shall be covered with compost. 20 Prior to the placement and incorporation of compost, the application and 22 incorporation methods shall be approved by the Engineer. 23 Compost shall not be placed when a condition exists, such as frozen or water 25 saturated soil that may be detrimental to successful application, incorporation, or soil 26 structure. 27 The Contractor shall notify the Engineer a minimum of five working days prior to the 29 start of compost work. 30 Compost shall be uniformly and evenly placed in all designated areas at a depth of 32 *** 3 *** inches. 33 After placement of the compost, the Contractor shall incorporate the layer uniformly 35 into the existing soil to a depth of *** 6 *** inches. 36
(******) 38 Soil Decompaction 39 Description 41 This Work consists of the decompaction of soil at the location shown in the Plans or as 42 specified by the Engineer. 43 Construction Requirements 45 At the locations designated in the Plans or specified by the Engineer, the Contractor shall 46 uniformly decompact the soil to a depth of 18 inches such that a soil penetrometer can be 47 inserted to a minimum depth of 12 inches with no more than 200 PSI of pressure using a ½ 48 inch tip. Soil decompaction operations shall be scheduled between April 1 and October 30. 49 Soil decompaction shall not be done when ground is frozen, excessively wet, or otherwise 50 untillable. 51
OAK AND GOPHER MITIGATION
25C510 18
The Contractor shall notify the Engineer a minimum of five working days prior to the start of 1 soil decompaction work. 2
The Engineer will inspect the soil decompaction method for its ability to fracture and shatter 4 compacted soil to the specified depth with uniformity and without negative consequences to 5 the soil structure. Equipment shall be capable of fracturing and shattering very dense soils in 6 three or fewer passes. When present in the Contract, boring logs may be used to determine 7 the density of soils to be decompacted. 8
The soil decompaction will be approved by the Engineer based on a field inspection of soil 10 penetration measurements within the designated soil decompaction area. The Engineer will 11 measure soil decompaction using a Dickey-JOHN soil penetrometer or approved equivalent. 12 Soil penetrometer measurements will be taken every 12 inches along a transect perpendicular 13 to the direction of soil decompaction operations and spanning the width of the soil 14 decompaction area. Acceptance is based upon at least 75% of the soil decompaction readings 15 meeting the PSI requirements. 16
Following soil decompaction operations, the area shall be graded smooth in preparation for 18 soil amendment installation. Soil amendment installation shall occur no more than 1 week 19 after soil decompaction. 20 Payment 22 “Soil Decompaction”, by force account. 23 All costs as authorized by the Engineer will be paid for by force account as specified in Section 25 1-09.6. 26 For the purpose of providing a common proposal for all bidders, the Contracting Agency has 28 entered an amount for the item “Soil Decompaction” in the Proposal to become a part of the 29 Contractor’s total Bid. 30 (******) 32
OAK ACORN PLANTING HOLES 33
Description 34 This Work consists of preparing planting holes for future oak acorn planting (by Others) and 35 biotic soil amendment work. The Contractor shall notify the Engineer a minimum of seven 36 calendar days prior to the start of biotic soil amendment Work. Biotic soil amendment 37 application and incorporation methods shall be approved by the Engineer prior to installation 38 and be in accordance as shown in the Plans or designated by the Engineer. 39 Order of Work: 41
1. Herbicide application prior to selective clearing and grubbing 43
2. Selective clearing and grubbing 44
3. Planting area staking (by the Engineer) 45
4. Oak Acorn Planting Holes preparation 46
Biotic soil amendment shall not be placed when a condition exists that may be detrimental to 48 successful application, incorporation, or soil structure, such as frozen or water saturated soil. 49
OAK AND GOPHER MITIGATION
25C510 19
Materials 1
Biotic Soil Amendments (BSAs), also known as biotic soil media and hydraulic growth 3 medium, shall be soil amendments engineered to improve the development of deficient 4 soils and to facilitate sustainable vegetation. BSAs shall consist of a blend of organic 5 material, nutrient sources, soil building and biostimulant components. BSAs shall 6 increase the water and nutrient holding capacity of the soil and promote the growth of 7 beneficial microorganisms. BSAs shall provide for enhanced seed germination and 8 vegetative establishment. 9 Biotic Soil Amendment shall be certified to be free of weed seeds and pathogens, free of 11 plastic, composed of non-toxic materials, and be a pre-mixed formulation unaltered by 12 synthetic materials. 13 The biotic soil amendment shall have a minimum of 90% organic matter (organic growth 15 medium) and contain other materials designed to improve seed germination, vegetation 16 establishment and overall soil health. In addition to organic growth medium BSA shall 17 include mycorrhizal fungi and a minimum of three of the following ingredients: 18
• Biochar 20
• Humus/Humic Acid 21
• Porous Ceramics or Water-holding Organic Polymers 22
• Seaweed Extract 23
• Beneficial Bacteria 24
• Micronutrients 25
The Contractor shall provide test results dated within 3 years prior to the date of 27 application from an independent, accredited laboratory that has been recognized by an 28 accrediting organization to test and evaluate products to product safety standards. The 29 independent, accredited lab shall be free from commercial, financial, and other pressures 30 that may influence the results of the testing and evaluation process. Test results shall 31 show that the product meets the following table requirements: 32
Table 1: Biotic Soil Amendment Requirements BSA Properties Test Methods Requirements
Physical Organic Matter ASTM D586 90% minimum pH ASTM D1293 5.0 - 8.5 C:N Ratio ASTM E1508 10:1 minimum 50:1 maximum
Water-Holding Capacity1 ASTM D7367 400% minimum Moisture Content ASTM 2974 10% minimum, 50% maximum Environmental Acute Toxicity EPA Method 2021.0 Non-toxic
EPA Metal Limits SW846-6020 04.06 Pass Performance
Growth Enhancement ASTM D7322 500% minimum 1Water holding capacity of the pre-packaged material without the addition of ancillary amendments.
OAK AND GOPHER MITIGATION
25C510 20
Submittal Requirements 1 At the time of delivery, the Contractor shall submit the specific biotic soil amendment 2 packing list to the Engineer for acceptance. The packing list shall include complete 3 identification including, but not limited to, the following information: 4
• Manufacturer name and location, 6
• Manufacturer telephone number and fax number, 7
• Manufacturer’s e-mail address and web address, and 8
• BSA name. 9
• Certification that the specific BSA meets the physical, environmental and…