Statement of Work Summary Department of Transportation (DOT) regulations require commercial vehicles tires not to exceed 10yrs in age – several of FEMA’s vehicles are approaching this threshold and require replacement.

Project Scope

This SOW covers the following activities and deliverables. The quote provided by the contractor shall include the following as well as all labor required to the complete the project. The quote shall be submitted on a Firm Fixed Price Basis, The vendor will provide the desired tires, stem and balancing beads (when required), and dispose of the old tire. The vendor will complete the tire replacement at FEMA MERs Bothell alternate site [7720 Hardison Rd, Everett, WA] and completing cleanup of the area. All equipment used to replace the tires will be provided by the vendor.

Tires to be replaced are:

Tire Pattern
Tire Size
Quantity
R268 ECOPIA
12R22.5 / Steer
6
M726ELA /
11R22.5 / Drive
27
R123 Trailer
295/75R22.5 / Trailer
24

Schedule

Upon signing the Purchase Order, the vendor will contact MERS Bothell logistics staff to initiate start and finish date. All work to be completed within 90 days after date of award.