DESIGNED

CHIEF, ENGINEERING DIVISION

DATE

APPROVED

RECOMMENDED

BRANCH CHIEF

SUBMITTED

PROJECT MANAGER

CHECKED

DRAWN BY

NO. DATE

DRAWING NUMBER

SCALE

SHEET OF

SHEET

DESCRIPTION

REVISIONS

APPROVEDBY

SHEET SIZE

ANSI D

DRAWING TITLE

WHITE SANDS MISSILE RANGE, NEW MEXICO

DIRECTORATE OF PUBLIC WORKS

ENGINEERING SERVICES DIVISION

CESAR LIMON

C.LIMON

RAFAEL H. ACOSTA

BUILDING 19467 OVERHEAD CRANE HOIST UPGRADE

WS-19467-2021-G-G1-01

COVER SHEET

BUILDING 19467

1 04

W H

I T E

S ANDS MIS S I LE

RA

N

G E

B I RTHPLACE

OF

AMERI CA' S MI SSI LE & SPACE

AC

TI

V

IT

Y

LUCIANO RIGALES

CONCURRENCES

Note: Signatures affixed on this sheet indicate official recommendation and approval of all the drawings in this set as indexed on this sheet

Safety

Security

Department

Environmental

Force Protection

Management

Maintenance

Customer 1

Customer 2

DPW

Information

Anti-Terrorism

Fire

Physical

Garrison

Operations &

03/10/21

AutoCAD SHX Text

WHITE SANDS MISSILE RANGE, NEW MEXICO

AutoCAD SHX Text

DIRECTORATE OF PUBLIC WORKS

AutoCAD SHX Text

ENGINEERING DIVISION

AutoCAD SHX Text

BID SET 100%%% DESIGN

AutoCAD SHX Text

ISSUED FOR CONSTRCUTION

SHEET INDEX

DRAWING NUMBER TITLE

WS-19467-2021-G-G1-01 BUILDING 19467 COVER SHEET

WS-19467-2021-G-G1-02 BUILDING 19467 INDEX SHEET/LOCATION MAP

WS-19467-2021-W-FP-03 BUILDING 19467 CRANE LAYOUT

WS-19467-2021-E-04 BUILDING 19467 ELECTRICAL LAYOUT FOR CRANE

DESIGNED

CHIEF, ENGINEERING DIVISION

DATE

APPROVED

RECOMMENDED

BRANCH CHIEF

SUBMITTED

PROJECT MANAGER

CHECKED

DRAWN BY

NO. DATE

DRAWING NUMBER

SCALE

SHEET OF

SHEET

DESCRIPTION

REVISIONS

APPROVEDBY

SHEET SIZE

ANSI D

DRAWING TITLE

WHITE SANDS MISSILE RANGE, NEW MEXICO

DIRECTORATE OF PUBLIC WORKS

ENGINEERING SERVICES DIVISION

CESAR LIMON

C.LIMON

RAFAEL H. ACOSTA

WS-19467-2021-G-G1-02

INDEX SHEET/LOCATION MAP

BUILDING 19467

2 04

PROJECT LOCATION BUILDING 19467

LAS CRUCES GATE

LUCIANO RIGALES

03/10/21

AutoCAD SHX Text N

AutoCAD SHX Text N

AutoCAD SHX Text

BID SET 100%%% DESIGN

' 6

6'

" 2'

' 0

44' 0"

C L

12"

ROOF

SCALE: 14" = 1' 0"

SECTION

SCALE: 3/8" = 1' 0"

EXISTING LONG

WALL SHOWN

DOTTED

EXISTING FLOOR

EXISTING WALL

METAL WALL BETWEEN

RAILS

12' X 10' SWING

DOOR W/HV

EXISTING LONG WALL

SHOWN DOTTED

EXISTING BRIDGE CRANE

DESIGNED

CHIEF, ENGINEERING DIVISION

DATE

APPROVED

RECOMMENDED

BRANCH CHIEF

SUBMITTED

PROJECT MANAGER

CHECKED

DRAWN BY

NO. DATE

DRAWING NUMBER

SCALE

SHEET OF

SHEET

DESCRIPTION

REVISIONS

APPROVEDBY

SHEET SIZE

WHITE SANDS MISSILE RANGE, NEW MEXICO

DIRECTORATE OF PUBLIC WORKS

ENGINEERING SERVICES DIVISION

DRAWING TITLE

ANSI D

CESAR M. LIMON

C.LIMON

LUCIANO RIGALES

RAFAEL ACOSTA

3 04

KEY NOTES:

WS-19467A-2021-FP-03

CONTRACTOR SHALL REMOVE THE TWO EXISTING

CRANE HOIST AND INSTALL ONE NEW 5 TON

CAPACITY CRANE HOIST, 3 PHASE, 460 V, AND TWO

SPEED HOIST ON EXISTING CRANE RAIL SYSTEM

WITH A HANDHELD CONTROL BOX AND INCLUDE

REPLACING MOTORS, CHAINS, AND GEARS USED TO

MOVE BEAM ON RAILS. GOVERNMENT SHALL

SALVAGE EXISTING CRANE HOIST ONCE THEY ARE

REMOVED. CONTRACTOR SHALL INSTALL NEW

HORIZONTAL STOPS, PAINT AS LISTED IN

MIL-HDBK-1038 SECTION 4.3.6.41, AND RE-LABEL

EXISTING BEAM AND RAILS. THE CONTRACTOR

SHALL CONDUCT THE NECESSARY SYSTEM LOAD

TEST TO CERTIFY THE NEW CRANE HOIST AND

PROVIDE A COPY OF THE TEST RESULTS WITH THE

CERTIFICATION TO THE COR. NEW CRANE HOIST

SHALL MATCH EXISTING CLEARANCES.

BUILDING 19467

CRANE LAYOUT

1. THIS PROJECT IS TO BE DONE IN BUILDING 19467. IT IS

THE CONTRACTORS RESPONSIBILITY TO PERFORM

ABATEMENT AS SPECIFIED IN THE STATEMENT OF

WORK.

2. THE CONTRACTOR SHALL KEEP THE WORK AREA CLEAR

OF ANY CONSTRUCTION DEBRIS AT ALL TIMES AND TO

PUT A TEMPORARY FENCE DIMENSIONS 6 FT H X 15 FT

W X 20 FT L TO KEEP NON CONSTRUCTION PERSONAL

FROM GOING INTO BUILDING 19467 WHILE

CONSTRUCTION IS ON GOING. ALL DEBRIS GENERATED

BY THIS PROJECT SHALL BE PROPERLY DISPOSED OF

OFF POST.

3. ALL WORK SHALL BE PERFORMED IN ACCORDANCE

WITH ALL APPLICABLE FEDERAL, STATE, AND

LOCAL REQUIREMENTS.

4. THE OVERHEAD CRANE HOIST SHALL BE

MANUFACTURED AND INSTALLED TO THE EXISTING

OVERHEAD CRANE RAILS FOR A FACILITY

THAT HANDLES EXPLOSIVES. THE HOOK FOR THE

HOIST SHALL BE FABRICATED OF CORROSION

RESISTANT STEEL FOR USE IN HAZARDOUS

ENVIRONMENTS (EXPLOSIVES) LISTED IN THE

UFC 3-320-07N MIL-HDBK-1038 SECTION 4.3.6.19 HOOKS.

CONTRACTOR SHALL SUBMIT SET OF SHOP DRAWINGS

WITH THE STAMP OF A REGISTERED ENGINEER OF ANY

STATE IN THE US WITH A CURRENT LICENSE AS LISTED

IN MIL-HDBK-1038 SECTION 7.1.1 DESIGN

RESPONSIBILITY. CONTRACTOR SHALL CONSIDER THE

STRUCTURAL DESIGN LOADS THAT INCLUDE THE DEAD

LOAD AND RATED LOAD AS LISTED IN MIL-HDBK-1038

SECTION 5.1.1 STRUCTURAL DESIGN LOAD, 5.1.1.1 DEAD

LOAD, AND 5.1.1.2 RATED LOAD.

5. CONTRACTOR SHALL PROVIDE THE GOVERNMENT THE

CERTIFICATES LISTED IN MIL-HDBK-1038

SECTION CERTIFICATES 7.6 a, b, c, d, e, f, g, i and l WHEN

THE CONSTRUCTION IS FINISHED AND NEW CRANE

HOIST IS OPERATIONAL.

6. BUILDING 19467 PERSONAL MR. TOM ESTES OR MR

MIGUEL TORRES SHALL NOTIFY COR A WEEK IN

ADVANCE TO INFORM THE CONTRACTOR IF THEY WILL

BE DELAYED TO NOT COME A DAY OF THE WEEK DUE

TO THE FORECASTED TESTING SCHEDULE OR

SECURITY REASONS.

7. CONTRACTOR SHALL COMPLY AND FOLLOW THE FIRE

PREVENTION GUIDE FOR CIVILIAN CONTRACTORS

WITH THE HOT WORK PERMIT FOR ANY WELDING

DURING THE CONSTRUCTION AT WSMR LISTED IN

SOW SECTION 3.12 HOT WORK PERMITS ALONG WITH

THE EMERGENCY REPORTING PROCEDURES. ENSURE

THAT PROPER FIRE EXTINGUISHERS OR FIRE

BLANKETS ARE ON HAND WHEN PERFORMING HOT

WORK OPERATIONS. ALL EQUIPMENT BEING USED

FOR HOT WORK OPERATIONS MUST BE IN PROPER

OPERATING CONDITION AND POSE NO POTENTIAL FOR

FIRE OR HAZARDS. CALL (575) 678-1234 FOR ANY

EMERGENCIES AND REPORT ANY ACCIDENTAL FIRES.

GENERAL NOTES

NOTES:

THE EAST AND WEST CRANE HOIST MANUFACTURE AND

CAPACITY INFORMATION BELOW.

1) HOIST MANUFACTURE: N/A

S/N: 7Q760

HOIST CAPACITY: 1-TON

CRANE CAPACITY: 2-TON

TYPE: MONORAIL

VOLTAGE: 208V/3/60 HZ

2) CRANE MANUFACTURE: CHECO

HOIST MANUFACTURE: DETROIT

S/N: 24386E

HOIST CAPACITY: 4-TON

CRANE CAPACITY: 8-TON

TYPE: SGTRUH

VOLTAGE: 460 V/3/60 HZ

03/10/21

AutoCAD SHX Text N

AutoCAD SHX Text

BID SET 100%%% DESIGN

ELECTRICAL LEGEND

DISTRIBUTION PANEL

SAFETY FUSE DISCONNECT SWITCH

DESIGNED

CHIEF, ENGINEERING DIVISION

DATE

APPROVED

RECOMMENDED

BRANCH CHIEF

SUBMITTED

PROJECT MANAGER

CHECKED

DRAWN BY

NO. DATE

DRAWING NUMBER

SCALE

SHEET OF

SHEET

DESCRIPTION

REVISIONS

APPROVEDBY

SHEET SIZE

NTS

WHITE SANDS MISSILE RANGE, NEW MEXICO

DIRECTORATE OF PUBLIC WORKS

ENGINEERING SERVICES DIVISION

DRAWING TITLE

WS-19467-2020-E-04

03/10/21 ANSI D

CESAR M. LIMON

C.LIMON

LUCIANO RIGALES

RAFAEL ACOSTA

4 04

KEY NOTES:

3BAY 4

BLDG 19467

BUILDING 19467

ELECTRICAL LAYOUT FOR

CRANE

PANEL D-3 PHASE, 208 / 120 V, THE WEST CRANE

CIRCUIT BREAKER #8-60 AMP, 3 POLE, WHERE THE

EXISTING WIRE SHALL BE REMOVED. CIRCUIT

BREAKER #8 SHALL REMAIN IN THE PANEL ON

"OFF" POSITION.

PANEL A-3 PHASE, 480 / 277 V, THE EAST CRANE

CIRCUIT BREAKER #18-60 AMP (GOVERNMENT

SHALL SALVAGE CIRCUIT BREAKER ) , 3 POLE,

SHALL BE REPLACED WITH A 150 AMP (SIZED

ACCORDING TO NEC 2020 610.42 (A), NEMA 7), 3

POLE BREAKER, AND MOLDED CASE

TO POWER A 460 V, 3 PHASE, 40 HP INDUCTION

MOTOR, AND CONTRACTOR SHALL REMOVE 125

FEET LONG OF BOTH EXISTING WIRE AND CONDUIT

AND RUN BOTH 90 FEET OF NEW CONDUCTORS

# 1 / 0 AWG (#6 AWG EQUIPMENT GROUND WIRE) ,

THHN, COPPER STRANDED, 600 V RATED AND 2"

RIGID CONDUIT.

REMOVE AND INSTALL 1 WALL MOUNTED HEAVY

DUTY FUSE EXPLOSION PROOF DISCONNECT

SWITCH NEMA 4, 7, AND 9, 200 AMP, 600 VOLT, 3

POLE, WITH 3-150 AMP DUAL ELEMENT TIME DELAY

FUSES (3 TOTAL).

AMPLIFIER

ROOM

NOTES:

ALL ELECTRICAL AND MECHANICAL INSTALLATION SHALL COMPLY IN

ACCORDANCE WITH THE NEC 2020 ARTICLE 250, 500, 610, 610-III, 610-VI,

430.112 EX, 610-IV, 668.32, 400.10(A)(5), 250.22(1), 250.112(E), 250.116(1),

610-VII, 503.155, 610.3A, 430.112 EX, 610.14(G), 610-V, 610.53, 610-II, AND

UFC 3-320-07NMIL-HDBK-1038 SECTION 6.3 HAZARDOUS (EXPLOSIVE)

ENVIRONMENT, AND SECTION 6.5 ORDANANCE/EXPLOSIVE HANDLING

AND NFPA 70 (CMAA 70) SERVICE CLASSIFICATION CLASS D

(HEAVY-DUTY) FOR HANDLING ORDNANCE/EXPLOSIVES. ALL NEW

CONDUIT SHALL BE RIGID CONDUIT SHALL BE SURFACE MOUNTED OR

INSIDE WALLS, ABOVE CEILING. CONCEAL MOST OF THE CONDUIT

ABOVE AND BELOW CEILINGS WHEREVER POSSIBLE AND TIGHTEN ALL

CONDUIT SECURE. EXPOSURE OF CONDUIT IS ALLOWED IN AREAS

WHERE IS OPEN CEILING OR CMU WALLS. SEAL ALL PENETRATIONS

AND IF NECESSARY APPLY PAINT AS NEEDED WHERE AREAS ARE

SCRATCHED ON THE WALL RESULTING FROM THE WORK THAT IS BEING

PERFORMED. ALL NEW CONDUCTORS SHALL BE 600 VOLT, THHN, AND

COPPER STRANDED FOR ALL THE CIRCUITS TO INCLUDE GROUNDS.

CONDUIT SHALL BE SURFACE MOUNTED OR INSIDE WALLS, ABOVE

CEILING.

AutoCAD SHX Text N

AutoCAD SHX Text

BID SET 100%%% DESIGN

Sheets and Views
WTD036470P- PLANS AND DRAWINGS - 08 JANUAURAY 2021 -100% Design Review Upgrade Overhead Crane for Building 19467-BUILDING ELEVATION (2)
WTD036470P- PLANS AND DRAWINGS - 08 JANUAURAY 2021 -100% Design Review Upgrade Overhead Crane for Building 19467-BUILDING ELEVATION (3)

File details come from the government source that posted it. Updated .