Summary of Contract Documents and Specifications
This is a comprehensive bid contract document for water, sewer, drainage, and paving improvements prepared by Pape-Dawson Consulting Engineers for Montgomery County Municipal Utility District No. 152A in Montgomery County, Texas (Project No. 14042574-010/020-402). The project encompasses the construction of water distribution lines (ranging from 4-inch to 8-inch diameter PVC pipe totaling approximately 2,981 linear feet), sanitary sewer infrastructure including 8-inch and 6-inch pipes with multiple manholes and drop connections (totaling approximately 3,718 linear feet), storm drainage facilities with reinforced concrete pipe and box culverts, concrete paving with curbs and sidewalks covering approximately 11,500 square yards, and associated site work including clearing, grubbing, and turf establishment across 20.6 acres. Electronic sealed bids were to be submitted through the CivCastUSA website no later than 10:30 a.m. on Wednesday, September 9, 2026, with bid results automatically posted on the website. No pre-bid conference was held for this project. The contract documents require bidders to submit qualifications within five days of award notification and to execute the agreement within nine days of receiving the notice of award.
Contract pricing is structured on a unit price basis with bid items organized into five major categories: Water Line Items, Sanitary Sewer Items, Drainage Items, WS&D Miscellaneous Items, WS&D Supplemental Items, Paving Items, and Paving Miscellaneous Items. Bid security requirements are 10 percent for bids under $250,000 and 5 percent for bids of $250,000 or more, with bid security forfeited if the successful bidder fails to execute the contract. Progress payments will retain 10 percent of completed work value until 50 percent completion is achieved; remaining retainage beyond 50 percent completion accrues interest at the owner's depository bank rate. The contractor must achieve Substantial Completion within 120 calendar days maximum and Final Completion within 130 calendar days maximum from the Notice to Proceed, with economic disincentives of $1,500 per calendar day assessed for delays and a mobilization requirement to begin work within 10 days of Notice to Proceed. The contract requires performance, payment, and maintenance bonds equal to 100 percent of the contract amount, prevailing wage compliance per Texas Government Code Chapter 2258, and compliance with multiple Texas statutory requirements including ethics disclosures, anti-boycott verifications, and critical infrastructure protection provisions.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DOCUMENTS &
SPECIFICATIONS
FOR
WATER, SEWER, DRAINAGE
AND PAVING IMPROVEMENTS
FOR WOODSON’S RESERVE
SEC 34
FOR
MONTGOMERY COUNTY MUD
NO. 152A
Project No. 14042574-010/020-402
AUGUST 2026
14042574-010/020-402 00001- 1
CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS
FOR THE CONSTRUCTION OF
WATER, SEWER, DRAINAGE AND PAVING IMPROVEMENTS FOR WOODSON’S
RESERVE SEC 34 FOR MONTGOMERY COUNTY MUD NO. 152A
LOCATED IN
MONTGOMERY COUNTY, TEXAS
PAPE DAWSON PROJECT NO. 14042574-010/020-402
Seals & Certifications
Pape-Dawson
Texas P.E. Board Firm Registration No. 470 James Parker, P.E.
AUGUST 2026
The Professional Engineer whose signed and dated seal appears above was responsible for preparing the following sections of the Contract Documents, which are fully identified by Section Number and Title and Number of Pages in the TABLE OF CONTENTS:
00100,00200,01410, 01415, 01500, 01560, 01600, 01660, 01710, Technical Specifications as listed in the Table of Contents
08/26/2026
WSD&P IMPROVEMENTS FOR WOODSON’S RESERVE SEC 34
TABLE OF CONTENTS
14042574-010/020-402 00110 - 1
DIVISION 00 – BIDDING AND CONTRACT REQUIREMENTS
00100 INVITATION TO BIDDERS
00115 LIST OF DRAWINGS
00200 INSTRUCTIONS TO BIDDERS
00410 BID FORM
00520 AGREEMENT BETWEEN OWNER AND CONTRACTOR FOR CONSTRUCTION CONTRACT
00530 SPECIAL CONDITIONS-2018 EJCDC
00610 PERFORMANCE BOND
00615 PAYMENT BOND
00620 MAINTENANCE BOND
00700 GENERAL CONDITIONS
00750 SUPPLEMENTARY CONDITIONS – INSURANCE
00800 SUPPLEMENTARY CONDITIONS – GENERAL
00810 ADDITIONAL CONDITIONS
00820 RESOLUTION ADOPTING PREVAILING WAGE RATE SCALE FOR CONSTRUCTION PROJECTS-
MONTGOMERY COUNTY MUD NO. 152A
DIVISION 01 – GENERAL REQUIREMENTS
01330 SUBMITTALS
01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
01350 CONSTRUCTION SCHEDULE
01410 TESTING LABORATORY SERVICES
01415 OBSERVATION OF CONSTRUCTION
01500 TEMPORARY FACILITIES AND CONTROLS
01550 BARRICADES AND WARNING DEVICES
01560 TRAFFIC SIGNS
01600 MATERIALS AND EQUIPMENT
01640 MANUFACTURER’S SERVICES
01660 CLEANING AND ADJUSTING
01710 PROJECT RECORD DOCUMENTS
TECHNICAL SPECIFICATIONS
DIVISION 02 – SITE WORK
02030 CUTTING AND CONNECTING WORK
02050 DEMOLITION ON WATER WASTEWATER FACILITY SITES
02055 REMOVING AND REPLACING MISCELLANEOUS EXISTING STRUCTURES
02100 WASTE MATERIAL DISPOSAL
02105 VEGETATION STRIPPING
02110 CLEARING AND GRUBBING
02111 TREE PROTECTION AND TREATMENT
02115 SITE PREPARATION FOR WATER-WASTEWATER FACILITIES
02120 STRIPPING, STOCKPILING, AND PLACING TOPSOIL
02130 CONSTRUCTION AND MAINTENANCE OF SILT FENCE BARRIERS
02140 CONTROL OF GROUND WATER AND SURFACE WATER
02150 STABILIZED CONSTRUCTION EXIT
14042574-010/020-402 00110 - 2
DIVISION 02 – SITE WORK (CONTINUED)
02160 TRENCH SAFETY
02200 EXCAVATION
02215 EXCAVATING, TRENCHING AND BACKFILLING FOR UTILITIES
02219 JACKING, BORING OR TUNNELING PIPE
02225 STRUCTURAL EXCAVATION AND BACKFILL
02314 EARTHWORK FOR UTILITIES
02315 EARTHWORK FOR PAVING
02316 EXCAVATION AND BACKFILL FOR STRUCTURES
02318 SCARIFY, PLOW, HARROW, SPRINKLE AND COMPACT EXISTING SUBGRADE OR FILL MATERIALS
02320 BACKFILL MATERIALS
02321 CEMENT STABILIZED SAND
02340 COMPACTED FILL
02403 PORTLAND CEMENT STABILIZED SUBGRADE
02404 LIME STABILIZED SUBGRADE
02405 LIME FLYASH OR FLYASH STABILIZED SUBGRADE
02406 SUBGRADE STABILZATION
02410 PORTLAND CEMENT CONCRETE PAVING
02411 CONCRETE CURB OR CONCRETE CURB AND GUTTER
02478 PAINTED PAVING MARKINGS
02501 DUCTILE IRON PIPE AND FITTINGS
02502 STEEL PIPE AND FITTINGS
02506 POLYVINYL CHLORIDE PIPE
02600 WATER DISTRIBUTION FACILITIES
02601 HYDROSTATIC TESTING OF WATER MAINS
02605 DISINFECTION OF WATER LINES AND WATER PLANTS
02720 STORM SEWER FACILITIES
02723 HEADWALLS AND WINGWALLS
02725 PRECAST REINFORCED CONCRETE BOX
02740 SANITARY SEWER FACILITIES
02743 ABANDONMENT OF SANITARY SEWERS
02763 ADJUSTING MANHOLES AND INLETS
02910 TREE PROTECTION, MAINTENANCE AND EVALUATION
02914 TOPSOIL
02915 TURF ESTABLISHMENT
02916 BROADCAST SEEDING
02917 SODDING
02920 HYDRO-MULCH
02925 SOD ESTABLISHMENT
DIVISION 03 – CONCRETE
03055 CONCRETE STRUCTURES
03200 CONCRETE REINFORCEMENT
03300 CAST-IN-PLACE CONCRETE
03303 HOT MIX ASPHALTIC CONCRETE SURFACING
03310 STRUCTURAL CONCRETE
14042574-010/020-402 00110 - 3
DIVISION 03 – CONCRETE (CONTINUED)
03311 PORTLAND CEMENT CONCRETE – SITE WORK
03320 HOT MIX LAID ASPHALTIC CONCRETE
03341 CONCRETE MISCELLANEOUS MATERIALS
APPENDIX – FORMS SPECIFIED IN THE CONTRACT
CONTRACTOR’S STATEMENT OF QUALIFICATIONS
AFFIDAVIT OF BILLS PAID
TEXAS CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
TEXAS CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
TEXAS UNCONDITONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
TEXAS UNCONDITONAL WAIVER AND RELEASE ON FINAL PAYMENT
Notes:
A. The General Conditions of this Contract is the Engineers Joint Contract Documents Committee (EJCDC) Document C-700 "Standard General Conditions of the Construction Contract", 2018 Edition, hereinafter referred to as the "General Conditions".
B. If a discrepancy occurs between the Technical Specifications in these Contract Documents and the technical specifications of the jurisdiction where the Work is being performed, the more stringent shall take precedence.
* END *
K:\Projects\425\74\010\4-0 Construction Project 1\4-1 Bid Phase\Contract Documents\Project Manual\002 TOC.Doc
14042574-010/020-402 00100 - 1
SECTION 00100
INVITATION TO BIDDERS
OWNER Montgomery County Municipal Utility District No. 152A c/o Schwartz, Page & Harding, LLP 1300 Post Oak Boulevard, Suite 2400 Houston, TX 77056
ENGINEER Pape-Dawson 2107 CityWest Blvd., 3rd Floor Houston, Texas 77042 Attn: James Parker, P.E.
Telephone: 713-428-2400
PROJECT/WORK Water, Sewer, Drainage and Paving Improvements for Woodson’s
Reserve Sec 34
BID OPENING TIME Wednesday, September 9, 2026 @ 10:30 a.m.
Sealed electronic bids, addressed to Montgomery County MUD No. 152A will be electronically received on the CivCastUSA Website (www.CivCastUSA.com) until 10:30 a.m. local time, Wednesday, September 9, 2026 and the Apparent Low Bidders will be automatically generated and posted on the CivCastUSA Website for construction of Water, Sewer, Drainage and Paving Improvements for Woodson’s Reserve Sec 34 for Montgomery County MUD No. 152A (Pape- Dawson Project Number: 14042574-010/020-402). A pre-bid conference will not be held for this project. Plans, specifications and bid documents may be viewed and downloaded free of charge (with the option to purchase hard copies) at the CivCastUSA Website. Reproduction charges will apply according to CivCastUSA rates.
The Owner reserves the right to reject any or all PROPOSALS and to waive irregularities in the bidding. In case of ambiguity or lack of clearness in stating the prices in the PROPOSAL, the Owner reserves the right to consider the most advantageous construction thereof or to reject the
PROPOSAL.
– END OF SECTION –
14042574-010/020-402 00115 - 1
SECTION 00115
LIST OF DRAWING SHEETS
WATER, SEWER, DRAINAGE AND PAVING IMPROVEMENTS FOR WOODSON’S RESERVE SEC 34
DESCRIPTION SHEET NO.
COVER SHEET 1
CONSTRUCTION NOTES 2
LAYOUT SHEETS
PAVING & DRAINAGE LAYOUT 3
DRAINAGE CALCULATIONS 4
WATER & SANITARY SEWER LAYOUT 5
GRADING PLAN (SHEET 1 0F 2) 6
GRADING PLAN (SHEET 2 OF 2) 7
SIGNAGE AND STRIPING SEWER LAYOUT 8
POLLUTION PREVENTION PLAN 9
PLAN & PROFILES
BROOK CROSSING COURT & WATER CONNECTION 10
WOODSONS CROSSING DRIVE 11
DELTA FOREST DRIVE 12
OVERLOOK PASS COURT & OFFSITE WATERLINE 13
BROOKING POINT LN 14
STM CONNECTION 1 & 2 15
STM CONNECTION 3 & STM CHANNEL 3 16
SAN CONNECTION & STM CHANNEL 1 17
STM CONNECTION 4 & STM CONNECTION 5 18
DETAIL SHEETS
SWPPP-DETAILS 19
PAVING-DETAILS 20
PAVING-MARKING-DETAILS 21
STEEL CASING DETAILS 22
SLOPE PAVING & RIPRAP DETAILS 23
BEDDING-DETAILS 24
STORM-DETAILS 25
SIDEWALK DETAILS 26
WATER-DETAILS 27
SANITARY-DETAILS (SHEET 1 OF 2) 28
SANITARY-DETAILS (SHEET 2 OF 2) 29
CONCRETE WINGWALL DETAILS & CONCRETE WINGWALL (FW-S) DETAILS 30
PLAT 31
STRUCTURAL SHEETS
RETAINING WALL STRUCTURAL NOTES S1
RETAINING WALL STRUCTURAL SCHEDULES S2
RETAINING WALL SECTIONS S3
RETAINING WALL DETAILS S4
14042574-010/020-402 00200 - 1
SECTION 00200
INSTRUCTIONS TO BIDDERS
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the Standard General
Conditions of the Construction Contract (General Conditions) and the Supplementary Conditions.
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Bidding Documents may be viewed and downloaded free of charge (with the option to purchase hard copies) at the CivCastUSA Website (www.CivCastUSA.com). Reproduction charges may apply according to CivCastUSA rates.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not confer a license or grant for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 When requested by either the Owner or Engineer, the apparent most qualified, responsible bidder must submit to Owner, within 5 days of notification of award of the Contract, either (i) a fully completed contractor’s statement of qualification or (ii) a written statement that the most recently submitted contractor’s statement of qualification is accurate, which statement of qualification must be considered in the award of the Contract. Failure to accurately complete the contractor’s statement of qualifications or to timely submit the statement of qualifications will, at Owner’s option, disqualify the bidder from consideration in the award of the Contract. The form of the Contractor’s statement of qualifications is available from the Engineer upon request.
Owner may reject, at Owner’s sole discretion, a bidder’s statement of qualifications if the bidder’s statement of qualifications is not on the form provided. Evidence of out-of-state incorporation to conduct business in the state in which the Work is to be performed, along with state contractor license number, as applicable, must also be provided and is a consideration in the award of the Contract.
ARTICLE 4 – EXAMINATION OF BIDDING DOCUMENTS AND SITE
4.01 Provisions concerning subsurface conditions and other physical conditions, Underground
Facilities, and possible changes in the Bidding Documents due to differing or unanticipated conditions appear in Articles 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning any potentially Hazardous Environmental Conditions at the Site and possible http://www.civcastusa.com/
14042574-010/020-402 00200 - 2 changes in the Contract Documents due to any such conditions uncovered or revealed at the Site appear in Article 5.06 of the General Conditions.
4.02 Upon request, Owner will provide Bidder access to the Site to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid.
Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.
4.03 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, the other related data identified in the Bidding Documents, and any Addenda;
B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all (if available): (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities), and (2) reports and drawings of Hazardous Environmental Conditions at the Site;
E. consider the information known to Bidder; information commonly known to
Contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs;
F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relate to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and
14042574-010/020-402 00200 - 3
I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work.
4.04 The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.
ARTICLE 5 – PRE-BID CONFERENCE
5.01 There will be no pre-bid conference for this project.
ARTICLE 6 – SITE AND OTHER AREAS
6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes to existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to
Engineer in writing online to the www.CivCastUSA.com system or website. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda, through the www.CivCastUSA.com website. Questions will be received up to 72 hours prior to the time and date for opening of Bids. Addenda, if issued, will be provided 48 hours prior to the time and date for opening bids. No explanation or interpretation of the Contract Documents, other than written addenda, is binding. Oral and other interpretations or clarifications will be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by a Bid security made payable to Owner. The Bid security required is an amount of 10% if the Bidder’s maximum Bid price is less than $250,000. The Bid security required is an amount of 5% if the Bidder’s maximum Bid price is $250,000 or more. The Bid security shall be in the form of a Bid bond issued by a surety meeting the requirements of Articles
6.01 and 6.02 of the General Conditions. CASHIER CHECKS WILL NOT BE ACCEPTED.
14042574-010/020-402 00200 - 4
8.02 The Bid security is a guarantee that the successful bidder will enter into the Contract within 9 days and execute the required Bonds on the forms provided and provide the required insurance certificates and Bonds within 5 days after the date Contract Documents are received by the successful bidder. Bid Securities will be returned to all but the 3 most qualified, responsible bidders within 3 days after opening of Bids, and the latter’s Bid Securities will be returned after complete execution of the Contract Documents. If the successful bidder does not enter the Contract after notice of award, then the bidder’s Bid Security will be forfeited and will be retained by Owner. If the award of the Contract to the successful bidder is canceled or not executed for any reason, the Owner may accept the next lowest bid and proceed with the next lowest qualified bidder.
8.03 The Bid security of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within 7 days after the Bid opening.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which, or the dates by which (Milestones are to be achieved and) the Work is to be completed and ready for final payment are set forth in the Agreement (Section 00520). All bidders submitting a Bid must accept the Contract Times as a requirement to the Contract Documents.
ARTICLE 10 – ECONOMIC DISINCENTIVES
10.01 Provisions for economic disincentives, if any, are set forth in the Agreement.
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract, if awarded, will be based on materials and equipment specified or described in the
Bidding Documents. Where materials or equipment are specified by a trade or brand name, it is not the intention of the Owner to discriminate against an equal product or another manufacturer, but to set a definite standard of quality or performance, and to establish an equal basis for the evaluation of the completed Bid Form. In preparing his Bid, the Bidder is expected to include the cost of the item so specified. A Bidder wishing to offer substitute items of equipment or materials for those specified is invited to do so by written request to Engineer explaining the substitutions and any cost savings that would result if the substitute item were accepted by the Owner. Each such request shall conform to the requirements of Article 7.05 and
7.06 of the General Conditions. No item of material or equipment will be considered by Engineer as a substitute or “or-equal” unless written request for approval has been submitted by Bidder.
The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. In some cases, approval of substitute or “or equal” items will be set forth in an Addendum issued to all prospective Bidders.
ARTICLE 12 – PREVAILING WAGE RATE SCALE
12.01 Chapter 2258 of the Texas Government Code provides that any political subdivision of the State of Texas shall ascertain the general prevailing wage rate received by the classes of Workers employed on Projects like this Project and shall specify in the call for bids and in the Contract the minimum wage rates which shall be paid for each type of Worker. This statute further provides
14042574-010/020-402 00200 - 5 that the CONTRACTOR or subcontractors shall pay a penalty to the OWNER sixty dollars for each Worker employed for each calendar day or part of the day that the Worker is paid less than the wage rates stipulated in the Contract.
12.02 The OWNER is authorized to withhold from the CONTRACTOR the amount of this penalty from any payment due under the Contract.
12.03 The statute also requires that the CONTRACTOR and subcontractors keep an accurate record of the names and occupations of all persons employed by them in the construction of the Project and to show the actual per diem wages paid to each Worker. These records shall be open to the inspection of the OWNER.
12.04 The minimum wage rates that apply to this Contract are specified in the attachment hereto.
CONTRACTOR and subcontractors shall review and ascertain such wage rates and pay at least such minimum rates.
ARTICLE 13 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS
13.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within 5 days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, in which case apparent Successful Bidder shall submit an acceptable substitute, Bidder’s price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
13.02 If the apparent Successful Bidder declines to make any such substitution, Owner may award the
Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make the requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Article 7.07 of the General Conditions.
ARTICLE 14 – PREPARATION OF BID
14.01 The Bid Form is included with the Bidding Documents.
14.02 All blanks on the electronic Bid Form shall be completed. Section 004100 shall also be completed and uploaded to the www.CivCastUSA.com website. Discrepancies between the unit
14042574-010/020-402 00200 - 6 prices in the electronic Bid Form and the unit prices in Section 00410 will be resolved in favor of the unit prices in the electronic Bid Form. A Bid price shall be indicated for each section, Bid item, alternative, adjustment unit price item, and unit price item listed therein. If no amount is to be included, zeroes or the words “No Bid,” “No Change,” or “Not Applicable” shall be entered in the spaces. No segregated bids or assignments will be considered. Unbalanced bids may be rejected. An “unbalanced” Bid means a Bid containing unit prices that are significantly less than cost for some items and significantly more than cost for others. This may be evidenced by submission of unit price Bid items where the cost is significantly higher/lower than the cost of the same Bid items submitted by other Bidders on the same Project.
14.03 A Bid by a CORPORATION shall be executed in the corporate name by the president or a vice-president (or other corporate officer accompanied by evidence of authority to sign). The corporate seal shall be affixed in the space provided and attested by the secretary or assistant secretary of the corporation. The official address of the corporation shall be shown.
14.04 A Bid by a PARTNERSHIP shall be executed in the partnership name and signed by a partner
(whose title must appear under the signature). The official address of the partnership shall be shown.
14.05 A Bid by a LIMITED LIABILITY COMPANY shall be executed in the name of the firm by a member authorized to sign. The official address of the firm shall be shown.
14.06 A Bid by an INDIVIDUAL shall be executed by the individual with the individual’s name and official address.
14.07 A Bid by a JOINT VENTURE shall be executed by each joint venturer. The official address of the joint venture shall be shown.
14.08 All names shall be typed or printed in ink below the signatures.
14.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form. Any bids not showing all Addenda may be rejected.
14.10 Postal and email addresses and telephone number for communications regarding the Bid shall be shown.
14.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state Contractor license number, if any, shall also be shown on the Bid Form.
ARTICLE 15 – BASIS OF BID
15.01 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the Bid Form.
14042574-010/020-402 00200 - 7
B. The total of all estimated prices will be the sum of the products of the estimated quantity of each item and the corresponding unit price. The final quantities and Contract Price will be determined in accordance with Article 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
15.02 The Bid price shall include such amounts as the Bidder deems proper for overhead and profit on account of cash allowances, if any, named in the Contract Documents as provided in Article 13.02 of the General Conditions.
15.03 The Bid Form may include Supplemental Items that may be required to complete the Work. If minimum unit prices have been established for Supplemental Items shown on the Bid Form, the bidder may not bid a unit price less than the minimum; however, he may increase the unit price.
If maximum unit prices have been established for Supplemental Items shown on the Bid Form, the bidder may not bid a unit price more than the maximum; however, he may decrease the unit price. When Work covered by Supplemental Items is requested by the Owner or Contractor and approved by the Engineer, payment will be based on the quantity actually constructed and the unit prices in the Bid Form. Award of the Contract will be based on the total amount bid, which may include selected Supplemental and Alternate Bid Items (See Article 22.02 below).
ARTICLE 16 – SUBMITTAL OF BID
16.01 Bids shall be completed electronically on the www.CivCastUSA.com website on the Bid Form provided.
16.02 Bids shall be submitted electronically to the www.CivCastUSA.com website no later than the date and time prescribed in the Advertisement or Invitation to Bid.
16.03 An acceptable Bid shall include the completed on-line Bid Form and any other documents that are required to be uploaded to the www.CivCastUSA.com website. The Bid security is a required upload. Other required uploads may include Section 00410 Bid Form, the List of Subcontractors and the List of Substitutions.
16.04 It is each bidder’s responsibility to deliver its Bid and Bid Security as stated in the Instructions to Bidders before the closing time. The fact that a Bid and a Bid Security were dispatched will not be considered. The Bid and Bid Security must be timely delivered to be considered.
ARTICLE 17 – MODIFICATION AND WITHDRAWAL OF BID
17.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.
17.02 If within 24 hours after Bids are received, any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a http://www.civcastusa.com/
14042574-010/020-402 00200 - 8 material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned.
ARTICLE 18 – OPENING OF BIDS
18.01 Bids will be opened electronically on www.CivCastUSA.com at the time indicated in the
Advertisement or Invitation to Bid and read aloud publicly via a Microsoft Teams Meeting. See Section 00100 Invitation to Bid or the Advertisement for the Teams Meeting telephone no. and meeting ID. The “Apparent Low Bidders” will be automatically generated and posted on the www.CivCastUSA.com website for furnishing all plant, labor, material and equipment and performing all work required for the Project.
ARTICLE 19 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE
19.01 All Bids will remain subject to acceptance for the period stated in Section 00410 Bid Form, but
Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 20 – HOUSE BILL 1295.
20.01 Provision of Texas Ethics Commission Form 1295 (“TEC Form 1295”) pursuant to Texas
Government Code § 2252.908 (the “Interested Party Disclosure Act” or the “Act”): Unless bidder is exempt from such requirements pursuant to Texas Government Code Section2252.908(c)(4), the District may not award the contract to a bidder unless the bidder has provided to the District a completed and signed TEC Form 1295 which has been assigned a certificate number by the Texas Ethics Commission (the “TEC”). Pursuant to the rules prescribed by the TEC, the TEC Form 1295 must be completed online through the TEC’s website, assigned a certificate number, printed, signed, and provided to the District. The TEC Form 1295 may accompany the bid or may be submitted separately, but must be provided to the District prior to the award of the contract. For purposes of completing the TEC Form 1295, the entity’s name is MONTGOMERY COUNTY MUNICIPAL UTILITY DISTRICT NO. 152A; the contract ID number is (14042574-010/020) provided by the Engineer; and the description of goods and services is WATER, SEWER, DRAINAGE AND
PAVING IMPROVEMENTS FOR WOODSON’S RESERVE SEC 34 FOR MONTGOMERY COUNTY
MUD NO. 152A. Neither the District nor its consultants have the ability to verify the information included in a TEC Form 1295, and neither have an obligation nor undertake responsibility for advising any bidder with respect to the proper completion of the TEC Form 1295.
ARTICLE 21 – CONFLICTS OF INTEREST
21.01 Effective January 1, 2006, Chapter 176 of the Texas Local Government Code (“Chapter 176”) mandates the disclosure of certain items by contractors doing business with or proposing to do business with local government entities, including municipal utility districts, road utility districts, road improvement districts, levee improvement districts, drainage districts, water control and improvement districts, bayou improvement districts, regional water authorities, fresh water supply districts, management districts, tax increment reinvestment zones, development authorities, etc.
21.02 Bidders should review Chapter 176 with their attorney and, if required, Bidder shall provide
14042574-010/020-402 00200 - 9 the TEC completed FORM CIQ with their Bid. The following is a list of the Board of Directors of Owner to facilitate Bidder’s compliance with Chapter 176.
Board of Directors MONTGOMERY COUNTY MUNICIPAL UTILITY DISTRICT NO. 152A
“ C/o Ms. Dianna Miller, Montgomery County MUD No. 152A - District Attorney ”
ARTICLE 22 – AWARD OF CONTRACT
22.01 Owner reserves the right to reject any or all Bids, including without limitation, non-conforming, non-responsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible.
Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.
22.02 The Owner reserves the right to award the project based on any combination of items in the Bid
Form.
22.03 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.
22.04 In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.
22.05 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.
22.06 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities to perform the Work in accordance with the Contract Documents.
22.07 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is in the best interests of the Project.
ARTICLE 23 – CONTRACT SECURITY AND INSURANCE
23.01 Article 6 of the General Conditions, and as modified by Section 00750 Supplementary Conditions
- Insurance, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it shall be accompanied by such bonds and a Certificate of Insurance.
14042574-010/020-402 00200 - 10
ARTICLE 24 – SIGNING OF AGREEMENT
24.01 When Owner gives a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement with the other Contract Documents which are identified in the Agreement as attached thereto. Within 10 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within 10 days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Construction Plans.
ARTICLE 25 – SALES AND USE TAXES
25.01 Provisions concerning state sales and use taxes are set forth in the Supplementary Conditions.
ARTICLE 26 – RETAINAGE
26.01 Provisions concerning retainage are set forth in the Agreement.
ARTICLE 27 – WORKERS’ COMPENSATION INSURANCE COVERAGE
27.01 Provisions concerning workers’ compensation insurance coverage are set forth in Section 00750
Supplementary Conditions - Insurance.
- END OF SECTION –
WSD&P IMPROVEMENTS FOR WOODSON'S RESERVE SECTION 34 LOCATED IN MCMUD NO. 152A
FOR:
Located in Montgomery County MUD No. 152A
DATE:
SUBMITTED BY:
Bidding Firm's Full Name
Address
City, State Zip
Phone Number
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
Addendum No. ______ Dated _____________ Addendum No. ______ Dated _____________
SECTION 00410
BID FORM
Water, Sewer, Drainage and Paving Improvements for Woodson's Reserve Sec 34
Having received and carefully examined the Bidding Documents, the other related data identified in the Bidding Documents, the Project Site, and the Addenda listed in the following table, I, the Undersigned submit this Bid Form.
c/o Pape-Dawson Consulting Engineers, LLC Montgomery County Municipal Utility District No. 152A
ATTN: Mr. James A. Parker, P.E.
2107 CityWest Blvd, 3rd Flr Houston, Texas 77042
14042574-010/020-402 00410 - 1
(1)
(2)
(3)
(4)
(5)
(6)
I acknowledge that:
(1)
(2) (3) (4)
(5)
(6)
Furthermore, I certify that:
(1)
(2)
(3) (4) (5) this Bid is made without collusion involving any other person, group, partnership, or the amounts given in this Bid have been carefully checked and are submitted as correct and the Contractor's Statement of Qualifications has been completed true and accurate and is included with this Bid.
For the performance of the Work, the enclosed amounts are bid. The unit prices and extended totals on the following pages are written in figures with the unit prices prevailing in the event of any discrepancies. In submitting this Bid Form, I agree:
to accept all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security;
no other individuals or entities have been solicited or induced to refrain from bidding or to submit a false Bid;
that this Bid will be open to acceptance and is irrevocable for 60 calendar days from the Bid closing date.
that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted;
to enter into and execute the Agreement within 9 calendar days of receipt of Notice of Award or acceptance of this Bid and to furnish the required bonds and a certificate of insurance within 5 calendar days of receipt of Notice of Award or acceptance of this Bid;
to accomplish the Work in accordance with the Contract Documents by furnishing all materials, equipment, and labor for proper construction and completion of the Work; and to the Contract Times as specified in the Agreement.
the estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price bid items will be based on actual quantities, determined as provided in the Contract Documents;
that the Owner reserves the right to award any combination of the items in the Bid Form;
the Owner reserves the right to reject any and all Bids;
the Owner reserves the right to reject any or all proposals and to waive irregularities in the bidding. In case of ambiguity or lack of clearness in stating the prices in the proposal, the Owner reserves the right to consider the most advantageous construction thereof or to reject the proposal;
the total Contract Price may be increased or decreased or the total Contract Time reduced or extended to compensate for changes in the Work as ordered by the Owner; and this Bid is genuine, and the only person or parties associated with or having an interest in this Bid as principals are those named herein;
The Undersigned hereby declares that he has visited the site and has carefully examined the Site Conditions, Drawings, Specifications, Contract Documents, and Bidding Documents related to the work covered by his Bid.
00410 - 2
Bidder: Witness:
By:
Title:
Address:
Phone:
E-Mail:
E-Mail:
Name of Insurance Agency:
Phone Number:
Bonds on Behalf of Corporate Surety:
[Corporate Seal]
Performance, Payment and Maintenance Bonds will be issued by (Name of Corporate Surety):
Name and Address of Local Agency for Corporate Surety:
Phone Number:
Name of Person(s) Executing
00410 - 3
BASE BID ITEMS:
WS&D ITEMS:
Water Line Items Subtotal $
Sanitary Sewer Items $
Drainage Items Subtotal $
WS&D Miscellaneous Items Subtotal $
WS&D Supplemental Items Subtotal $
PAVING ITEMS:
Paving Items Subtotal $
Paving Miscellaneous Items Subtotal $
CONTRACT TIME:
CONSTRUCTION OF WATER, SEWER, DRAINAGE AND PAVING IMPROVEMENTS FOR WOODSON'S
RESERVE SEC 34
PD PROJECT NO. 14042574-010/020-402
BID SUMMARY
Water, Sewer, Drainage and Paving Improvements for Woodson's Reserve Sec. 34 Grand Total
We will achieve Substantial Completion of the Work in _______ calendar days (120 days maximum) and achieve Final Completion of the Work in _______ (130 days maximum) from the Notice to Proceed.
Completion time includes ________ calendar days (10 days minimum) for adverse weather conditions, and we acknowledge that time is of the essence to Owner and additional adverse weather days will not be granted.
00410 - 4
Water, Sewer, Drainage and Paving Improvements for Woodson's Reserve Sec 34 Item No.
Item Description Unit Approx.
Quantity
Unit Price Total Amount
1 8-Inch Water Line, All Depths, Complete in Place (include fittings)
Linear Foot
1908 $ $
2 8-Inch Class 235, C900 Polyvinyl Chloride (PVC) Water Line, With Restraint Devices for Pipe Joints and Fittings, All Depths, By Open Cut, Complete in Place (include fittings)
Linear Foot
83 $ $
3 8-Inch, Class 235, C900, DR-18, Polyvinyl Choloride (PVC) Water Line, With Restraint Devices for Pipe Joints and Fittings with 14- Inch Steel Casing, All Depths, Complete in Place (include fittings)
Linear Foot
33 $ $
4 6-Inch Water Line, All Depths, Complete in Place (include fittings)
Linear Foot
539 $ $
5 4-Inch Water Line, All Depths, Complete in Place (include fittings)
Linear Foot
451 $ $
6 6-Inch AWWA Gate Valve and Box, Complete in Place
Each 8 $ $
7 8-Inch AWWA Gate Valve and Box, Complete in Place
Each 6 $ $
8 2-Inch Blow-Off Valve & Box, Complete in Place
Each 3 $ $
9 8-Inch Wet Connection, Including Removal and Disposal Offsite of Existing 8-Inch Plug and Clamp, All Depths, Complete in Place
Each 2 $ $
10 8-Inch Plug and Clamp, Complete in Place Each 1 $ $
11 4-Inch Plug and Clamp, Complete in Place Each 2 $ $
12 Flushing Valve, All Depths, Complete in Place
Each 7 $ $
13 6-Inch by 4-Inch Reducer, All Depths, Complete in Place
Each 2 $ $
14 8-Inch by 6-Inch Reducer, All Depths, Complete in Place
Each 2 $ $
15 Trench Safety System Greater Than 5-Feet, Complete in Place
Linear Foot
3014 $ $
Water Line Items
Water Line Items Subtotal $
00410 - 5
Item No.
Item Description Unit Approx.
Quantity
Unit Price Total Amount
8-Inch Sanitary Sewer Pipe, Depth of 0 Feet to 8 Feet from Proposed Top of Curb, Complete in Place
Linear Foot
35 $ $
8-Inch Sanitary Sewer Pipe, Depth of 8 Feet to 16 Feet from Proposed Top of Curb, Complete in Place
Linear Foot
2115 $ $
8-Inch Sanitary Sewer Pipe, Depth of 16 Feet and Greater from Proposed Top of Curb, Complete in Place
Linear Foot
815 $ $
8-Inch Sanitary Sewer Pipe with 14-Inch Steel Casing, Bore and Jack, Including all Necessary Bore Pits, All Depths, Complete In Place
Linear Foot
63 $ $
6-Inch Sanitary Sewer Pipe for Service Laterals, All Depths, Including All Wyes, Tees, Bends, and Marker Pipe, Complete in Place
Linear Foot
691 $ $
City of Houston Sanitary Sewer Precast Concrete Manhole (4-Foot Diameter), With Inflow Preventor, Depth of 0 Feet to 8 Feet, Complete in Place
Each 1 $ $
City of Houston Sanitary Sewer Precast Concrete Manhole (4-Foot Diameter), With Inflow Preventor, Depth of 8 Feet to 16 Feet, Complete in Place
Each 12 $ $
City of Houston Sanitary Sewer Precast Concrete Manhole (4-Foot Diameter), With Inflow Preventor, Depth of 16 Feet and Greater, Complete in Place
Each 6 $ $
8-Inch Standard Sanitary Sewer Drop Connection, All Depths, Complete in Place
Each 2 $ $
6-Inch Standard Sanitary Sewer Drop Connection, All Depths, Complete in Place
Each 3 $ $
6-Inch Standard Sanitary Sewer Stack, All Depths, Complete in Place
Each 30 $ $
8-Inch Sanitary Sewer Plug, Complete in Place
Each 1 $ $
Trench Safety System Greater Than 5-Feet, Complete in Place
Linear Foot
3593 $ $
Sanitary Sewer Items
Sanitary Sewer Items Subtotal $
00410 - 6
Item No.
Item Description Unit Approx.
Quantity
Unit Price Total Amount
24-Inch Reinforced Concrete Pipe (RCP), C76, Class III, With Rubber Gasket Joints, All Depths, Complete in Place
Linear Foot
1030 $ $
30-Inch Reinforced Concrete Pipe (RCP), C76, Class III, With Rubber Gasket Joints, All Depths, Complete in Place
Linear Foot
210 $ $
36-Inch Reinforced Concrete Pipe (RCP), C76, Class III, With Rubber Gasket Joints, All Depths, Complete in Place
Linear Foot
777 $ $
6-Foot By 4-Foot Reinforced Concrete Box, Including Bedding with Cement Stabilized Sand, All Depths, Complete in Place
Linear Foot
92 $ $
Type "C" Manhole for 42-Inch and Smaller Pipe, All Depths, Complete in Place
Each 17 $ $
Type "H-2" Inlet, Stage I & II Construction, All Depths, Complete in Place
Each 17 $ $
Drainage Swale with 3:1 Side Slopes, Complete in Place
Linear Foot
141 $ $
Regrade Existing Creek within Defined Limits, Complete in Place
Linear Foot
138 $ $
Demuck Existing Creek within Defined Limits, Complete in Place
Linear Foot
425 $ $
20' Bottom Drainage Swale with 4:1 (MAX) Side Slopes, Complete in Place. Final Grading Only - Excavation and Placement Under Separate Pay Items.
Linear Foot
556 $ $
Excavation of Channel Improvements, Including Uniform Shaping of Excavated Side Slopes to Lines and Grades as Shown on the Plans, Complete in Accordance with Plans and Specifications
Cubic Yard
3,723 $ $
Spread and Compact Channel Excavation Spoils within Section 34 Limits, as Shown in the Construction Plans, Including Proof Rolling, Interim Drainage (Including Cutting Swales to Provide Positive Drainage), Onsite Hauling, and Uniformly Spreading, Shaping, Grading, and Compacting Spoil Material as Directed by Engineer and When Authorized by Owner, Complete in Place
Cubic Yard
3,723 $ $
Drainage Items
00410 - 7
Item No.
Item Description Unit Approx.
Quantity
Unit Price Total Amount
TXDOT FW-S Headwall with Flared Wingwalls for 3~36" RCP, As Shown in Construction Plans, Complete in Place
Each 2 $ $
TXDOT FW-S Headwall with Flared Wingwalls for 6'x4' Box Culverts, As Shown in Construction Plans, Complete in Place
Each 2 $ $
5-Inch Thick Reinforced Concrete Slope Paving With 24-Inch Deep Concrete Toewall, All Sides, Complete in Place
Square Yards
59 $ $
18-Inch Thick Broken Concrete Riprap With "Mirafi-600", or Approved Equal, Woven Filter Fabric, Complete in Place
Square Yards
84 $ $
Trench Safety System Greater Than 5-Feet, Complete in Place
Linear Foot
2109 $ $
Move-in and Start-up as Required to Begin Construction
Lump Sum
1 $ $
Performance and Payment Bonds for 100 Percent (100%) of the Contract Amount
Lump Sum
1 $ $
Control and Construction Staking for Construction and/or Installation of Water Line, Storm Sewer Items and Required Appurtenances, Including, but not Limited to Pipes, Valves, Manholes, and Inlets;
Staking for Construction to be Provided by the Engineer; Complete in Place
Lump Sum
1 $ 25,800.00 $ 25,800.00
As-Built Staking at Construction Completion for Water Line, Storm Sewer Items and Required Appurtenances, Including, but not Limited to Pipes, Valves, Manholes, and Inlets, to be provided by the Engineer, Complete in Place
Lump Sum
1 $ 15,000.00 $ 15,000.00
WS&D General Control and Construction Staking for Construction when Required and Approved by Owner or Engineer; To be Provided by the Engineer
Lump Sum
1 $ 4,500.00 $ 4,500.00
WS&D Miscellaneous Items
Drainage Items (Cont.)
Drainage Items Subtotal
00410 - 8
Item No.
Item Description Unit Approx.
Quantity
Unit Price Total Amount
Clearing and Grubbing for Lightly/Heavy Vegetated Areas Within Woodson's Reserve Section 34 (Unusable Cleared Material to be Chipped and Hauled Offsite), to Prepare for Placement of Fill; to Include Stripping and Site Preparation of Sparsely Vegetated Areas (Suitable Stripped Material to be Stockpiled), in Accordance With the Specifications, Complete in Place
Acre 1.30 $ $
Dewatering System for Installation of Utiliites, When Authorized by Owner, Complete in Place (Minimum Unit Price of $25.00 per Linear Foot)
Linear Foot
8,716 $ $
Crushed Stone Support for Manholes as per City of Houston Drawing No. 02081-05
Each 17 $ $
Extra Cement-Stabilized Sand, When Authorized by Owner, Complete in Place (Minimum Unit Price of $20.00 per Cubic Yard)
Cubic Yard
20 $ $
Roadway Excavation, Complete Cubic
Yard 3,840 $ $
Spread and Compact Excavation Spoils Onsite as Shown in the Construction Plans;
Includes Proof Rolling, Interim Drainage (Includes Cutting Swales to Provide Positive Drainage); Onsite Hauling, and Uniformly Spreading, Shaping, Grading, and Compacting Spoil Material, As Directed by Engineer, Complete in Place
Cubic Yard
3,840 $ $
Spread and Compact Utility Spoils Onsite as Shown in the Construction Plans;
Includes Proof Rolling, Interim Drainage (Includes Cutting Swales to Provide Positive Drainage); Onsite Hauling, and Uniformly Spreading, Shaping, Grading, and Compacting Spoil Material, As Directed by Engineer, Complete in Place
Cubic Yard
4,720 $ $
WS&D Miscellaneous Items Subtotal $
WS&D Miscellaneous Items (Cont.)
Paving Items
WS&D Supplemental Items
WS&D Supplemental Items Subtotal $
00410 - 9
Item No.
Item Description Unit Approx.
Quantity
Unit Price Total Amount
Conrete Retaining Wall, All Heights, Per Details Included in Construction Plans.
Includes Concrete, Steel, Weep Holes and select backfill, Complete in Place.
Square Foot
6,952 $ $
Lime for Subgrade Stabilization, When Required by Soil Conditions and When Authorized by Owner, Complete in Place
Ton 94 $ $
Fly-Ash for Subgrade Stabilization, When Required by Soil Conditions and When Authorized by Owner, Complete in Place
Ton 218 $ $
Manipulation of Lime and Fly-Ash for Stabilization of 6-Inch Compacted Subgrade, When Required by Soil Conditions and When Authorized by Owner, Complete in Place
Square Yards
11,500 $ $
6-Inch Reinforced Concrete Pavement, Complete in Place
Square Yards
11,500 $ $
6-Inch Reinforced Concrete Curb, Complete in Place
Linear Foot
3,297 $ $
4-Inch Reinforced Concrete Curb, Complete in Place
Linear Foot
3,591 $ $
Type-7 Concrete Wheel Chair Ramp Meeting ADA Requirements, Complete in Place
Each 12 $ $
Tie Into Existing Pavement, Complete in Place
Each 2 $ $
2…
This is the start of the file's text. The full file is on GovTribe.