The document provided is a Window Replacement Study for the Wing Hall Wing building at Cornell University, as well as a related state and local contract opportunity for the replacement of the building's window system.

The study assesses the existing conditions of the building's windows and recommends the complete replacement of the curtain wall system, including the insulated glass panels and metal spandrel panels. The study outlines the project scope, which includes repairing interior finishes, and provides a cost analysis estimate of $425,000 to $450,000 for the construction. The related contract opportunity, SUCF#161063 Replace Windows - Wing Hall Wing, seeks design and construction administration services for the window replacement project. The project has an estimated design completion date of February 2025 and a contract term of 1-2 years. The contract opportunity includes Minority- and Women-Owned Business Enterprise (MWBE) and Service-Disabled Veteran-Owned Business Enterprise (SDVOB) participation requirements, with goals of 6.6% for MBE, 16.9% for WBE, and 6% for SDVOB.

View the file

Other files

File Type Posted
Subconsultant Staffing List.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Facilities Engineering

14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

FACILITIES

AND CAMPUS SERVICES

FINAL

FACILITIES

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Preface Existing Conditions Plans Existing Conditions - Observations Existing Conditions Assessment - Observations Existing Conditions Photos .....................................................................................................................................7-8 Recommendations and Cost Analysis

Table of Contents

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Facilities Engineering has been engaged to assess the existing window conditions at Wing Hall Wing (1042W). Observations were made at a site visit on October 16, 2023.

Wing Hall Wing addition to Wing Hall was built in two phases. The first phase included the basement and first floors in 1965.

The second phase included the second and third floors in 1977. In 1994, during an overall building renovation to the Wing Hall complex, the curtain wall windows were replaced.

Preface

1042W

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Wing Hall Wing 1042W

Existing Conditions Plans

Basement Floor Plan - Not To Scale First Floor Plan - Not To Scale

Second Floor Plan - Not To Scale Third Floor Plan - Not To Scale

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Several deficiencies have been observed and are explained on the following pages.

1 Glazing 2 Metal Panel 3 Frame

Existing Conditions - Observations

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Existing Conditions Assessment - Observations

Wing Hall Wing (1042W)

Glazing

The glazing panel is a 1 inch insulated glass panel. It consist of (2) 1/4 inch panes of glass and an 1/2 inch air space. The glazing panel is past its remaining useful life (RUL). There are signs of air leakage as some of these panel have become cloudy between the glass panels.

Insulated Metal Spandrel Panel

The insulated metal spandrel panel is 1 inch thick. These panels are past their remaining useful life (RUL). There are rust holes in the panels on the south and east sides of the building which allows leakage into the building. The north side has panels that are showing signs of delamination and oil canning. The rust from the panels is staining the surrounding brick.

Aluminum Curtain Wall Frame

In 1994, the size of the frame profile changed from 2 inches wide by 7 inches deep to 1 3/4 inches wide by 6 inches deep.

The frame profile at the existing concrete beams is 4 1/2 inches deep. The frame is clear anodized aluminum on the inside and bronze on the outside. The window sill is an aluminum clear anodized sill. There are plastic clip that hold the panels into the frame. These clips are failing and are no longer available for repairs.

Interior Finishes

The interior of the exterior walls on the basement and first floors are concrete masonry units, while the second and third floors are 1/2 inch gypsum wall board and 1/2 inch insulation board adhered over 8 inch concrete masonry units. The gypsum wall board on the upper levels and the adjacent ceilings on all levels will require repairs.

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Existing Conditions Photos

Figure 1

Figure 4 Figure 5

Figure 3

Figure 6

Figure 2

Wing Hall Wing (1042W)

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Existing Conditions Photos - Cont.

Figure 1

Figure 4

Figure 2

Figure 5

Figure 3

Figure 6

Wing Hall Wing (1042W)

AND CAMPUS SERVICES 14 December 2023

Wing Hall Wing Window Replacement Study (1042W)

Recommendations

Curtain Wall Window Replacement:

• Remove existing curtain wall system.

• Provide new curtain wall system with spandrel panels to match existing.

• Possible replacement manufacturers - New Castle, Kawneer, Tubelite, and EFCO.

• Provide 1 inch insulated glass and metal spandrel panel.

• Repair interior finishes (Walls and Ceilings).

• Clean rust off of brick

Work should be performed from the outside to minimize the impact of the lab spaces.

Wing Hall Wing (1042W) Window Replacement

Cost Analysis

Curtain Wall Window Replacement and Associated Repairs ...............................................$425,000 - $450,000

Note: The estimate (listed above) are construction costs only and that soft costs (Design, PM, Contingency, etc.

are not included. (Add 40% - 50% to the total construction cost to establish a project cost).