WHITE CIRCLE STABILIZATION PLAN.pdf
PDF 19 MB Posted
- Attached to
- White Circle Stabilization
- Solicitation number
- PE-63363-NONST-2024-000000014
- Issued by
- Cobb County, Georgia
About this file
The document is the "WHITE CIRCLE STABILIZATION PLAN" related to a state and local contract opportunity in Cobb County, Georgia. The project consists of installing guardrail, grading and shaping slope, and clearing. No additional details are provided regarding item quantities, response dates, due dates, site visits, bidder's meetings and conferences, award dates, or the term of the contract.
The document does not contain any information regarding pricing terms, set asides, incumbents, the current environment, funding requirements and sources, or any other salient details. The document appears to be solely focused on providing an overview of the project scope and the jurisdictions involved.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFB_24_50341 WHITE CIRCLE STABILIZATION.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OHP
O H
P
O H
P
O H
P
O H
P
O H
P
OHP
W
W
W
W
W
W
SS
SS
SS
SS
SS
SS
T
Project
Date
Sheet Name and Number
01-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
8/8/23
COVER SHEET
N
EW
S
CITY OF MARIETTA
COBB COUNTY, GA
WHITE CIRCLE STABILIZATION
Project
Date
Sheet Name and Number
02-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
8/10/23
INDEX
01-001 COVER SHEET
02-001 INDEX SHEET
04-001 to 04-002 GENERAL NOTES
05-001 TYPICAL SECTIONS
06-001 SUMMARY OF QUANTITIES
13-001 to 13-002 MAINLINE ROADWAY PLAN SHEETS
24-001 UTILITIES
40-001 to 40-004 DETAILS
INDEX
Sheet Name and Number
04-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
10/4/23
GENERAL NOTES
PROJECT GENERAL NOTES:
TOTAL SITE AREA = .25 AC
TOTAL AREA TO BE DISTURBED = .15 AC
AN N.O.I. (NOTICE OF INTENT) IS NOT REQUIRED FOR THIS PROJECT.
1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE GEORGIA DEPARTMENT OF TRANSPORTATION STANDARD AND
SUPPLEMENTAL
2. ALL KNOWN UTILITY FACILITIES ARE SHOWN SCHEMATICALLY ON PLANS, AND ARE NOT NECESSARILY ACCURATE IN LOCATION AS TO PLAN OR ELEVATION. UTILITY FACILITIES SUCH AS SERVICE LINES OR UNKNOWN FACILITIES NOT SHOWN ON PLANS WILL NOT RELIEVE THE CONTRACTOR OF THEIR RESPONSIBILITY UNDER THIS REQUIREMENT. “EXISTING UTILITY FACILITIES” MEANS ANY UTILITY THAT EXISTS ON THE PROJECT IN ITS ORIGINAL, RELOCATED OR NEWLY INSTALLED POSITION.
3. THE FOLLOWING UTILITIES HAVE FACILITIES IN THE PROJECT AREA:
A.CITY OF MARIETTA TRAFFIC
i.MORGAN PATTERSON (770) 794-3955
B. AT&T:
i.KRISTOPHER DITTRICH (678) 435-3673
C.ATLANTA GAS LIGHT RESOURCES:
i.NITOU MAKIDI (470) 464-6206
D.COMCAST CABLE:
i.DAVID TYSON (404) 597-1098
E.MARIETTA POWER
i.CODY TIBBITS (770) 794-5124
F. MARIETTA WATER & SEWER
i.JACOB DEWOODY (770) 794-5186
4. INGRESS AND EGRESS SHALL BE MAINTAINED AT ALL TIMES TO ADJACENT PROPERTIES. REFER TO SUB-SECTION 107.07 OF
THE GEORGIA STANDARD SPECIFICATIONS.
5. RIGHT-OF-WAY MARKERS SHALL BE PLACED FLUSH WITH THE FINISHED SURFACE UNLESS OTHERWISE NOTED.
6. IT SHALL BE THE CONTRACTORS RESPONSIBILITY TO FURNISH SUITABLE BORROW MATERIAL FOR THE PROJECT AND TO DISPOSE OF ANY UNSUITABLE OR WASTE MATERIAL IN COMPLIANCE WITH ALL LOCAL, STATE AND FEDERAL REGULATIONS.
CONCRETE AND ASPHALT MATERIALS REMOVED FROM THE PROJECT SITE MAY NOT BE PLACED IN FILL LOCATIONS THAT FALL
WITHIN THE EASEMENT AREAS.
7. STRUCTURES, TREES, SHRUBS AND OTHER PLANT MATERIAL THAT FALL WITHIN THE RIGHT-OF-WAY AND EASEMENT LIMITS, BUT OUTSIDE THE LIMITS OF CONSTRUCTION, SHALL NO BE DISTURBED UNLESS DIRECTED BY THE ENGINEER.
8. THE CONTRACTOR SHALL OBSERVE ALL APPLICABLE LOCAL, STATE AND FEDERAL SAFETY REGULATIONS REGARDING PIPE INSTALLATION IN TRENCHES. NO SEPARATE PAYMENT WILL BE MADE FOR ANY COST INCURRED TO COMPLY WITH THIS
REQUIREMENT.
9. ALL EXISTING PIPE REMOVED FROM SERVICE SHALL BE REMOVED UNLESS OTHERWISE NOTED ON PLANS OR AS DIRECTED BY THE ENGINEER. REMOVAL OF PIPE SHALL BE INCLUDED IN PRICE BID FOR “GRADING COMPLETE”.
10. UNLESS SPECIFIED OTHERWISE, ALL DRIVEWAYS SHALL BE MAINTAINED DURING CONSTRUCTION. ALL DRIVEWAYS TO BE CONSTRUCTED SHALL BE REPLACED IN KIND I.E. ASPHALT FOR ASPHALT, CONCRETE FOR CONCRETE ETC. ANY OTHER DRIVEWAY MATERIAL OR SPECIALIZED DRIVEWAY WILL NOT BE REPLACED IN KIND (I.E. PAVERS) AND WILL BE REPLACED WITH ASPHALT OR CONCRETE. ALL EARTH OR GRAVEL DRIVES SHALL BE PAVED WITH ASPHALT TO THE RIGHT-OF-WAY OR TIE-IN
POINT. DRIVEWAYS SHALL BE PAVED AS FOLLOWS:
ASPHALTIC DRIVES:
RESIDENTIAL - 1-1/2” ASPH. CONC. 12.5 MM SUPERPAVE, 165 LB/SY
- 6” GRADED AGGREGATE BASE
COMMERCIAL - 1-1/2” ASPH. CONC. 12.5 MM SUPERPAVE, 165 LB/SY
- 2” ASPH. CONC. 19MM SUPERPAVE, 220 LB/SY
- 6” GRADED AGGREGATE BASE
CONCRETE DRIVES:
RESIDENTIAL - 6” CONCRETE VALLEY GUTTER
- 4” CONCRETE DRIVEWAY
COMMERCIAL - 8” CONCRETE VALLEY GUTTER
- 6” CONCRETE DRIVEWAY
11. SPRINKLER SYSTEMS TO BE HANDLED AS FOLLOWS:
CASE 1 - FOR SYSTEMS WITHIN THE CONSTRUCTION LIMITS OWNED BY INDIVIDUALS OR PRIVATE COMPANIES, OWNER MAY RELOCATE THE FACILITIES IN ADVANCE OF DISTURBANCE AND INVOICE THE CITY DIRECTLY FOR THE WORK. OTHERWISE CONTRACTOR SHALL REMOVE AND PLUG AND OWNER MAY STILL INVOICE THE CITY DIRECTLY FOR REPAIRS.
CASE 2 - SYSTEMS SHOWN BY THE PLANS TO BE REMOVED AND RELOCATED SHALL BE RELOCATED TO THE BACK OF THE SIDEWALK OR DISTURBANCE. COST SHALL BE INCLUDED IN THE PRICE BID FOR “GRADING COMPLETE”.
12. LUMP-SUM TRAFFIC CONTROL: THE PRICE BID FOR LUMP-SUM TRAFFIC CONTROL SHALL INCLUDE THE COST OF STAGED CONSTRUCTION, MAINTENANCE OF TRAFFIC (INCLUDING AGGREGATE SURFACE COURSE), INSTALLATION AND REMOVAL OF ALL TEMPORARY SIGNAGE, INTERIM PAVEMENT MARKINGS, BARRICADES, AND OTHER INTERIM TRAFFIC CONTROL DEVICES NECESSARY FOR THE CONSTRUCTION AND MAINTENANCE OF THE PROJECT. DEVICES UTILIZED ON THE PROJECT SHALL BE IN COMPLIANCE WITH THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD), CURRENT EDITION AND SECTION 150. ALL DEVICES, SIGNS, POST, BARRICADES, ETC SHALL BE FROM THE GDOT QUALIFIED PRODUCTS LIST (QPL). ALL DEVICES SHALL BE CRASHWORTHY UNDER AASHTO AND NCHRP 350 REQUIREMENTS. THE ENGINEER MAY DIRECT THAT ADDITIONAL DEVICES AND MARKINGS BE ADDED TO THE TRAFFIC CONTROL PLAN. THE COST OF NOMINAL ITEMS ADDED BY THE ENGINEER SHALL BE INCLUDED IN LUMP-SUM TRAFFIC CONTROL EXCEPT FOR THE ADDITION OF A CHANGEABLE MESSAGE SIGN(S). THE CONTRACT UNIT PRICE WILL BE PAID FOR A CHANGEABLE MESSAGE SIGN(S) OR A UNIT PRICE WILL BE DETERMINED WHEN A CHANGEABLE
MESSAGE SIGN(S) IS NOT INCLUDED IN THE CONTRACT.
13. DETOURS IN THE PLANS: DETOURS SHOWN IN THE PLANS SHALL BE SIGNED AND MARKED AS PER THE PLANS. THE COST OF MAINTENANCE, GRADING, TEMPORARY DRAINAGE, TEMPORARY SIGNAGE, TEMPORARY MARKINGS AND TEMPORARY DEVICES SHALL BE INCLUDED IN LUMP-SUM TRAFFIC CONTROL. THE COST OF STONE BASE (GAB) AND THE PLACEMENT OF THE TYPICAL PAVEMENT SECTION INCLUDED IN THE PLANS FOR THE DETOUR WILL BE PAID AT THE CONTRACT UNITS PRICES.
WHEN INSTALLED FOR A DETOUR SHOWN IN THE PLANS, TEMPORARY CONCRETE BARRIERS, ATTENUATORS, TEMPORARY GUARDRAIL AND ANCHORS WILL BE PAID AT CONTRACT UNIT PRICES. THE UNIT PRICES BID FOR THESE PAY ITEMS SHALL INCLUDE INSTALLATION AND REMOVAL. PERMANENT DEVICES, TO BE INCORPORATED INTO THE FINAL WORK, MAY BE USED FOR INTERIM/TEMPORARY DUTIES PROVIDED THE PERMANENT DEVICES ARE NOT DAMAGED DURING THE INTERIM USAGE. THE COST FOR REPLACEMENT OF DAMAGED COMPONENTS SHALL BE INCLUDED IN LUMP-SUM TRAFFIC CONTROL.
DETOURS NOT SHOWN IN THE PLANS (DETOURS PROPOSED BY THE CONTRACTOR): THE COST TO INSTALL, MAINTAIN AND REMOVE ANY DETOUR SHALL BE INCLUDED IN THE PRICE BID FOR LUMP-SUM TRAFFIC CONTROL. THE COST OF GRADING, PAVEMENT, SIGNING, MARKINGS, TEMPORARY DEVICES, TEMPORARY CONCRETE BARRIERS, ATTENUATORS, TEMPORARY GUARDRAIL AND ANCHORS, ETC SHALL BE INCLUDED IN THE PRICE BID FOR LUMP-SUM TRAFFIC CONTROL. DETOURS NOT
SHOWN IN THE PLANS WILL NOT BE ELIGIBLE TO BE PAID AT CONTRACT UNIT PRICES.
14. ALL CUT AND FILL SLOPES SHALL BE STABILIZED TO COMPLY WITH SECTION 161.3.05.B OF THE SPECIFICATIONS IN ORDER TO REDUCE THE POTENTIAL FOR EROSION. IF THE SEASON DOES NOT PERMIT SOD PERMANENT GRASSING, TEMPORARY STRAW MULCH AND/OR TEMPORARY VEGETATION SHALL BE USED AS PER THE EROSION AND SEDIMENTATION POLLUTION
CONTROL (ESPCP) OR AS DIRECTED BY THE ENGINEER.
15. EROSION CONTROL MEASURES SHALL BE INSTALLED TO BE IN COMPLIANCE WITH THE APPROVED EROSION AND SEDIMENTATION POLLUTION CONTROL PLAN (ESPCP). EROSION CONTROL MEASURES SHALL BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITIES THAT INVOLVE ENVIRONMENTAL SENSITIVE AREAS (ESA'S) AS DEFINED UNDER SECTION 107.23.F OF THE SPECIFICATIONS AND THE ESPCP. IN GENERAL, EROSION CONTROL ITEMS SHOULD BE INSTALLED PRIOR TO THE START OF ANY LAND DISTURBING ACTIVITIES. THE INSTALLATION OF THE EROSION CONTROL ITEMS MAY BE INSTALLED CONCURRENT WITH THE START OF THE LAND DISTURBING ACTIVITIES, IF ALLOWED BY THE ESPCP.
16. THE CONTRACTOR WILL COORDINATE WITH THE CITY OF MARIETTA AND SHALL BE RESPONSIBLE FOR REMOVING, RELOCATING, AND MAINTAINING THE PROPERTY OWNER'S MAILBOX TO AN AREA OUTSIDE CONSTRUCTION LIMITS DURING THE LIFE OF THE CONTRACT. THE LOCATION OF THE BOX SHOULD BE CONVENIENT TO BOTH THE MAIL CARRIER AND THE PATRON, YET NOT INTERFERE WITH PROPOSED WORK. IT MAY BE NECESSARY FOR THE CONTRACTOR TO CONFER WITH THE POST OFFICE SERVING THE AREA. ALL COSTS INCURRED FOR COMPLIANCE WITH THESE REQUIREMENT SHALL BE INCLUDED IN THE
PRICE BID FOR OTHER ITEMS.
17. ATTENTION IS CALLED TO SECTION 149.3, CONSTRUCTION REQUIREMENTS, CONTRACTOR IS REQUIRED TO TAKE THREE-POINT LEVELS ON WIDENING AND RECONSTRUCTION PROJECTS AND OBTAIN THE ENGINEER'S APPROVAL OF THE “BEST FIT” PROFILE AND CROSS SLOPE, TO MINIMIZE LEVELING REQUIREMENTS OF THE EXISTING ROADWAY. THE CONTRACTOR MUST GET THE ENGINEER'S APPROVAL OF THE PROPOSED BEST FIT BEFORE BEGINNING WIDENING AND RECONSTRUCTIONS. COST FOR SURVEY WORK TO BE INCLUDED IN THE GRADING COMPLETE OR OTHER ITEMS, NO SEPARATE
PAYMENT SHALL BE MADE.
18. ALL ROADWAY DRAINAGE PIPES SHALL BE REINFORCED CONCRETE UNLESS SPECIFIED OTHERWISE.
19. CONTRACTOR TO PROVIDE PRE-CONSTRUCTION PHOTOS OF ALL DRIVEWAYS TO PROJECT ENGINEER PRIOR TO
CONSTRUCTION. PHOTOS TO BE DIGITAL.
20. ALL EXISTING STORM DRAIN PIPES INCLUDING BOX CULVERTS WITHIN THE CONSTRUCTION LIMITS SHALL BE CLEANED
PRIOR TO COMPLETION OF PROJECT. COST TO BE INCLUDED IN GRADING COMPLETE.
21. ALL GRASSED MEDIANS, LANDSCAPED AREAS BETWEEN THE BACK OF CURB AND SIDEWALK AND SHOULDER BREAK POINT SHALL BE SODDED WITH BERMUDA SOD, UNLESS THERE IS EXISTING GRASS, THEN THE SOD TYPE FROM BACK OF CURB TO EXISTING GRASS SHALL MATCH ADJACENT GRASS. ALL COST ASSOCIATED WITH THIS REQUIREMENT SHALL BE INCLUDED IN
THE PRICE FOR 700-9000.
22. ALL EXISTING PEDESTRIAN FACILITIES, INCLUDING ACCESS TO TRANSIT STOPS, SHALL BE MAINTAINED. WHERE PEDESTRIAN ROUTES ARE CLOSED, ALTERNATE ROUTES SHALL BE PROVIDED. WHEN EXISTING PEDESTRIAN FACILITIES ARE DISRUPTED, CLOSED, OR RELOCATED WITHIN THE LIMITS OF THE PROJECT, THE TEMPORARY PEDESTRIAN FACILITIES SHALL BE DETECTABLE AND SHALL INCLUDE ACCESSIBILITY FEATURES CONSISTENT WITH THE FEATURES PRESENT IN THE EXISTING
PEDESTRIAN FACILITIES SHALL BE INCLUDED IN THE PRICE BID FOR GRADING COMPLETE.
23. THE CITY WILL PROVIDE BRICK PAVERS FOR ADA DETECTION SURFACES, BRICK SIDEWALK, BRICK MEDIANS, AND BRICK CROSSWALKS. THE CONTRACTOR IS RESPONSIBLE FOR PICKUP AND LOADING AT A CITY STORAGE YARD, DELIVERY TO THE
PROJECT LOCATION, AND UNLOADING/STORAGE.
Sheet Name and Number
04-002
WHITE CIRCLE GUARDRAIL ONLY OPTION
8/8/23
GENERAL NOTES
MAINTENANCE OF TRAFFIC GENERAL NOTES:
1. ALL ITEMS NECESSARY FOR COMPLIANCE WITH THESE REQUIREMENTS SHALL BE INCLUDED IN THE PRICE BID
FOR “TRAFFIC CONTROL”.
2. ALL SIGNS AND PAVEMENT MARKINGS SHALL CONFORM TO THE MANUAL ON UNIFORM TRAFFIC CONTROL
DEVICES, LATEST EDITION.
3. TYPE 3 RETROREFLECTIVE SHEETING SHALL BE USED FOR ALL STANDARD HIGHWAY SIGNS REQUIRED REFLECTORIZED BACKGROUNDS EXCEPT AS SPECIFIED BELOW OR SPECIFIED OTHERWISE IN THE PLANS. TYPE 11 RETROREFLECTIVE SHEETING SHALL BE USED FOR ALL RED-SERIES SIGNS (R1-1, R1-2, R1-3, R5-1a), WARNING SIGNS AND OVERHEAD SIGNS, SCHOOL AND PEDESTRIAN0RELATED SIGNS, WITH THEIR REQUIRED PLAQUES AND ADVISORY NAME BLADES, SHALL HAVE FLORESCENT YELLOW/GREEN COLOR AND TYPE 11 SHEETING.
4. IN RESIDENTIAL AREAS, TEMPORARY AND PERMANENT SIGNS SHALL BE LOCATED ON OR AS CLOSE AS
POSSIBLE TO PROPERTY LINES.
5. EXISTING TRAFFIC SIGNS SHALL BE MAINTAINED BY THE CONTRACTOR THROUGHOUT CONSTRUCTION.
MAINTENANCE INCLUDES REPLACING DAMAGED AND STOLEN SIGNS, AND PERIODIC CLEANING OF EXISTING
SIGNS AND CONSTRUCTION RELATED TRAFFIC CONTROL DEVICES.
6. THE WORKSITE TRAFFIC CONTROL SUPERVISOR (WTCS) SHALL BE RESPONSIBLE FOR THE ELIMINATION OF ANY CONFLICTING PAVEMENT MARKINGS. THE WTCS SHALL NOT USE “BLACK OUT PAINT” TO ERADICATE CONFLICTING MARKINGS. THE ENGINEER SHALL MAKE THE FINAL DETERMINATION WHETHER THE CONFLICTING
MARKINGS HAVE BEEN ADEQUATELY ELIMINATED.
7. TEMPORARY TRAFFIC BARRIERS SHALL HAVE A TWO (2') FEET MINIMUM OFFSET FROM THE EDGE OF ANY TRAVEL LANE. VERTICAL PANELS MEETING THE MINIMUM REQUIREMENTS OF THE MUTCD AND SECTION 150, AND TEMPORARY BARRIERS THAT ARE CRASHWORTHY SHALL BE USED ADJACENT TO TRAVEL LANES, UNLESS PRIOR APPROVAL IS GRANTED BY THE CITY, THE TEMPORARY BARRIERS CANNOT BE PLACED LESS THAN TWO (2') FEET FROM THE EDGE OF THE TRAVEL LANE. THE USE OF TYPE I AND II BARRICADES AND TRAFFIC CONES IS
PROHIBITED.
8. TRAFFIC PANELS MEETING THE MINIMUM REQUIREMENTS OF THE MUTCD AND SECTION 150 SHALL BE USED FOR CHANNELIZATION OF TRAFFIC IN ALL TRAFFIC SHIFTS. FOR ANY WORK ZONE, THE MAXIMUM PANEL SPACING, IN FEET, SHALL BE THE DESIGN OR POSTED SPEED LIMIT, WHICHEVER IS LESS. BASED ON FIELD CONDITIONS, THE
MAXIMUM SPACING OF THE TRAFFIC PANELS MAY NEED TO BE FURTHER REDUCED.
9. ALL TRAFFIC CONTROL DEVICES SHALL BE MAINTAINED BY THE CONTRACTOR SO AS TO NOT INTERFERE WITH
SIGHT DISTANCES ALONG ANY ADJACENT SIDE ROAD OR DRIVEWAY.
10. THE CITY OF MARIETTA RESERVES THE RIGHT TO MODIFY THIS MAINTENANCE OF TRAFFIC PLAN AS FIELD CONDITIONS WARRANT. IF ADDITIONAL TRAFFIC CONTROL DEVICES ARE REQUIRED, THESE SHALL BE PROVIDED
BY THE CONTRACTOR AT NO ADDITIONAL EXPENSE TO THE DEPARTMENT.
11. ALL TRAFFIC CONTROL ACTIVITIES MUST BE REQUESTED THROUGH THE CITY OF MARIETTA WEBSITE AT LEAST 48 HOURS PRIOR TO THE ACTIVITY WITH THE EXCEPTION OF ROAD CLOSURES WHICH MUST BE REQUESTED 2 WEEKS PRIOR TO THE ROAD CLOSURE. THE REQUEST CAN BE COMPLETED ON THE CITY WEBSITE (WWW.MARIETTAGA.GOV) FROM THE ENGINEERING PAGE LOCATED IN THE PUBLIC WORKS PAGE. ANY
WORK BEING COMPLETED ON A STATE ROUTE MUST BE SUBMITTED TO GDOT FOR APPROVAL.
12. REFLECTORIZED TYPE 3 BARRICADES SHALL BE USED AT THE ACTUAL LOCATION OF TOTAL STREET CLOSURE. EACH BARRICADE SHALL HAVE TWO TYPE 'A' LIGHTS AND ONE R11-2 (ROAD CLOSED) SIGN
ATTACHED.
13. ALL M4-9 SIGNS SHALL HAVE ADVISORY BLADES (INSTALLED ABOVE THE “DETOUR” SIGN) IDENTIFYING THE
CLOSED STREET THAT THE DETOUR ROUTE SERVES.
14. INFORMATION SIGNS, INFORMING MOTORISTS OF THE ROAD CLOSURE, SHALL BE INSTALLED A MINIMUM OF 1 WEEK PRIOR TO THE ROAD CLOSURE. THESE SIGNS SHALL BE INSTALLED AT OR AS NEAR AS POSSIBLE TO THE ROAD CLOSURE. THE MESSAGE DISPLAYED MUST BE SUBMITTED TO THE CITY FOR REVIEW AND APPROVAL
OUTSIDE OF THE ROAD CLOSURE REQUEST FORM.
15. NO LANE CLOSURES ARE ALLOWED BETWEEN 6-9AM AND 4-7PM WITHOUT APPROVAL BY THE CITY OR AS
STIPULATED IN THE CONTRACT DOCUMENTS.
16. THE CONTRACTOR SHALL MAINTAIN INGRESS AND EGRESS TO ALL DRIVEWAYS AT ALL TIMES.
Sheet Name and Number
05-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
10/4/23
SECTIONS
Sheet Name and Number
06-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
8/24/23
QUANTITIES
TP 1 STONE
CONTROLLED LOW STRENGTH MATERIAL
TP 1 STONE WITH
CONTROLLED LOW-
STRENGTH MATERIAL (CLSM)
INSTALL GUARDRAILEND TREATMENT
TP 1 STONE
CONTROLLED LOW STRENGTH MATERIAL
GUARDRAIL POST
MIN 3' 6" FROM EP
INSTALL GUARDRAIL
END TREATMENT
RIP RAP MUST BE KEYED
INTO THE TOE OF THE SLOPE
MINIMUM OF 18" TO PREVENT FUTURE
UNDERCUTTING OF BANK
MINOR GRADING/SHAPING OF THE BANK
MAY BE NECESSARY IN ORDER TO STABILIZE SLOPE
FOR ROCK REPLACEMENT
Project
Date
Sheet Name and Number
13-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
10/4/23
MAINLINE PLAN
Fe et
ESTIMATED ROW
GDOT HEADWALL
W/POURED IN PLACE
SPLASH PAD
W/DISSAPATORS AT
OUTLET
BALLOON LINE
EXISTING 36" PIPE
TO 34" PIPE
TP 1 STONE
CONTROLLED LOW STRENGTH MATERIAL
TP 1 STONE
CONTROLLED LOW STRENGTH MATERIAL
INSTALL GUARDRAIL
END TREATMENT
MINOR GRADING/SHAPING OF THE BANK
MAY BE NECESSARY IN ORDER TO STABILIZE SLOPE
FOR ROCK REPLACEMENT
Project
Date
Sheet Name and Number
13-002
WHITE CIRCLE GUARDRAIL ONLY OPTION
10/4/23
MAINLINE PLAN
1" = 20'
Fe et
O H
P
O H
P
O H
P
OHP
OHP
OHP
OHP
OHP
OHP
OHP
OHP
OHP
OHP
OHP
OHP
OHP
O H
P
O H
P
OHP
OHP
OHP
OHP
W
W W
W
W
W
W
W
W
W W
W W W
W
W
W
W
W
W
W
W
W W W
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
T T
T T
T T T
T
Project
Date
Sheet Name and Number
24-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
8/8/23
UTILITIES
Fe et
1:
Sheet Name and Number
40-001
WHITE CIRCLE GUARDRAIL ONLY OPTION
8/10/23
DETAILS
Sheet Name and Number
40-002
WHITE CIRCLE GUARDRAIL ONLY OPTION
Sheet Name and Number
40-003
WHITE CIRCLE GUARDRAIL ONLY OPTION
Sheet Name and Number
40-004
WHITE CIRCLE GUARDRAIL ONLY OPTION
| White Circle Guardrail Only Option-01-001 |
| 01-001 |
| White Circle Guardrail Only Option-02-001 |
| 02-001 |
| White Circle Guardrail Only Option-04-001 |
| 04-001 |
| White Circle Guardrail Only Option-04-002 |
| 04-002 |
| White Circle Guardrail Only Option-05-001 |
| 05-001 |
| White Circle Guardrail Only Option-06-001 |
| 06-001 |
| White Circle Guardrail Only Option-13-001 |
| 13-001 |
| White Circle Guardrail Only Option-13-002 |
| 13-002 |
| White Circle Guardrail Only Option-24-001 |
| 24-001 |
| White Circle Guardrail Only Option-40-001 |
| 40-001 |
| White Circle Guardrail Only Option-40-002 |
| 40-002 |
| White Circle Guardrail Only Option-40-003 |
| 40-003 |
| White Circle Guardrail Only Option-40-004 |
| 40-004 |
File details come from the government source that posted it. Updated .